International & G. N. Ry. Co. v. Landa & Storey
International & G. N. Ry. Co. v. Landa & Storey
Opinion of the Court
Appellees alleged; That they shipped over the International & Great Northern Railway, the Texas ■& Pacific and the St. Louis, Iron Mountain & Southern Railways, connecting carriers, certain cattle from Cotulla, Tex., to the stockyards in East St. Louis, Ill., for sale in that market. That said cattle should have arrived at their destination in time to be sold on the market of May 17, 1910, but that, by reason of the negligent delay of appellants in shipping said cattle, they did not arrive until the 18th, by reason of which they were compelled to, and did, hold them over until the 20th. That they were damaged by such negligence (a) in the decrease in the market value, (b) shrinkage in weight, and (c) by increased expense for feed. All of these items of damage were submitted to the jury. There was a general verdict for appellees, apparently for all of the items claimed by them.
Appellants the International & Great Northern and the Texas & Pacific Railway Companies have filed jointly 41 assignments of error, and the St. Louis, Iron Mountain & Southern Railway Company has filed 14 assignments of its own. We will not undertake to pass upon the assignments in this case seriatum, but will discuss briefly the issues raised by them in what appears to us to be their logical order.
“The court erred in refusing to submit to the jury special instruction No. 4, requested by defendants jointly, wherein the jury-were instructed with reference to the requirements of the federal law requiring the unloading of cattle and other live stock; for resting, watering, and feeding.”
It appearing that this case involves an interstate shipment of live stock, and that it required at least 60 hours to make the shipment, it was error to refuse the requested charge. Railway Co. v. Jarman, 138 S. W. 1133; Railway Co. v. Moore, 149 S. W. 302; Railway Co. v. Carlisle, 34 Tex. Civ. App. 268, 78 S. W. 554; Railway Co. v. Jones, 104 Tex. 99, 100, 134 S. W. 328; U. S. Comp. St. 1913, §§ 8651-8654.
■ [9] That portion of the contract of shipment showing that the cattle were to be shipped from Cotulla, Tex., to Longview, Tex., “consigned to Godair-Russell, Nat. Stk. Yrd. Ill.,” having been read in evidence by appellees, the appellants offered the following clause of said contract:
“That the live stock covered by this contract are not to be transported within any specified time, nor delivered at destination at any particular hour, nor in season for any particular market.”
This was objected to on the ground that, this being an interstate shipment, “any stipulation therein is void, and not binding upon plaintiffs.” Had this stipulation been contrary to the provisions of the federal statute, or an attempt to contract against appellants’ negligence, it would have been void; but, as it was neither the one nor the other, it should have been admitted as showing the entire contract between the parties, a portion of which had been read i.n evidence by the appellees. Levy v. Goldsoll, 131 S. W. 420.
L113 H. O. Storey, one of the appellees herein, testified as a witness in his own behalf that he was experienced in the business of shipping cattle over the roads of appellants from points in Texas to East St. Louis, and that he knew the distance per hour ordinarily made over said roads, with stock shipments, the usual and necessary stops made by such trains, and the time that was usually consumed in shipping stock from Cotulla to East St. Louis. Appellants, upon cross-examination of said witness, sought to show by him that he had a similar knowledge as to such shipments from New Braunfels and San Marcos, Tex., in June, 1910, and in 190S, and that he had so testified in another suit by the witness against these appellants, and offered to prove by him what he had so testified as to such time, and what was the fact as to such time. It was admitted that New Braunfels and San Marcos were stations on the International & Great Northern road between Cotulla and East St. Louis, through which appellees’ cattle passed, as was also the distance from Cotulla to said stations, and the reasonable time consumed in running from Cotulla to them, and also the actual time so consumed in the shipment here involved. The purpose of said testimony was to show that adding the reasonable and necessary time consumed between New Braunfels or San Marcos and East St. Louis, as testified to by the witness on a former occasion and as he would have testified on this trial,'to the reasonable and necessary time for the run from Cotulla to New Braunfels or to' San Marcos, it would take a longer time to make the shipment from Co-tulla to East St. Louis than was testified by the witness on the trial then being had. We think this evidence was admissible, and that the court erred in sustaining appellees’ objection thereto. Sterling v. DeLaune, 47 Tex. Civ. App. 470, 105 S. W. 1172.
We overrule assignments of error Nos. 37, 38, 39, 40, and 41. The assignments herein * referred to are those filed by the appellants the International & Great Northern Railway Company and the Texas & Pacific Railway Company. Our decision applies also to the assignments of error by the St. Louis, Iron Mountain & Southern Railway Company, which, so far as they go, raise the same issues as those presented by its codefendants.
For the reasons stated, the judgment of the trial court herein is reversed, and this cause is remanded for a new trial in accordance with this opinion.
Reversed and remanded.
(gsaEor other oases see same topic and KEY-NUMBER In all Key-Numbered Digests and Indexes
<g=Por other oases see same topic and KEY-NUMBER in all Key-Numbered Digests and Indexes
Reference
- Full Case Name
- INTERNATIONAL & G. N. RY. CO. Et Al. v. LANDA & STOREY
- Cited By
- 1 case
- Status
- Published