Rouser v. Wright
Rouser v. Wright
Opinion of the Court
Appellees Wright & Hearne, who had been bondsmen for tbe contractors Crawford & Hogue, on a contract tbe latter made with appellant, Mrs. Rouser, for the erection of a brick building under tbe supervision of ber architect, Watson, at George^ town, Tex., sued all the others named to recover amounts claimed to be due for labor and material put into the’ building both by Crawford & Hogue and themselves. They charged there was a balance due Crawford & Hogue upon the original contract price and for extras the latter had furnished before quitting the work; that Orawford & Hogue had ceased work upon the building before its entire completion, and, by mutual agreement of all parties, they as their bondsmen had taken in hand its completion, including the tearing down of the roof the contractors had put on and the building of a new one; that they thus became subrogated to the rights of the contractors as to all sums due them, and also themselves directly furnished such1 additional work and material necessary for the completion of the building. The main recovery sought was against the owner of the building, Mrs. Rouser; that against her architect and the contractors, whose sureties they had become, being contingent or incidental.
Orawford & Hogue replied by answer and a cross-bill each against Mrs. Rouser and her architect, Watson; that against her being for extra work and material alleged to have been furnished by them before ceasing work upon the building, while their claim against Watson was for one-half the expense of putting certain truss rods into th'e original roof built by .themselves. On the trial no proof was offered upon this latter claim against Watson, and it was so abandoned and lost sight of by both counsel and court that in entering the original judgment no disposition was made of it. Dikewise Mrs. Rouser, after otherwise answering, filed a cross-action against the contractors and th'e bondsmen for defective work and material claimed to have gone into the building, and in the alternative against Watson for such damages as might b.e shown to have resulted from any defects in plans and specifications furnished her by him.
The cause having been submitted to, and findings returned by, a jury, judgment was rendered tbereon in favor of Wright & Hearne for $1,665.71, and in favor of Oraw-ford & Hogue for $294.26, respectively, against Mrs. Rouser, and in her favor against the architect, A. O. Watson, for $1,561.98; but, as already stated, by oversight and mutual mistake of all parties, including the court, no disposition was made in the judgment of the cross-action pleaded by Crawford & Hogue against Watson, upon which they had offered no proof.
Mrs. Rouser alone appealed from the judgment originally entered, but th'e Court of Civil Appeals at El Paso dismissed her appeal, on the ground that no final judgment below had been rendered because of tbe trial court’s failure to dispose of this cross-action of the contractors against the architects. Subsequently, and at a different term, upon a hearing - had on the motion of appellees Wright & Hearne, at which all the parties in interest, including Mrs. Rouser, appeared for trial, she having specially answered the motion upon the facts, the trial court entered a corrected and final judgment in the cause, disposing of the cross-action of Orawford & Hogue against Watson, but in no other re *850 spect changing or amending it, thus leaving the original recoveries against Mrs. Rouser unaffected. Of that judgment, as so finally-entered, she alone complains through her appeal now before this court, having named all the other parties to the suit as appellees.
Considering, first, the.question raised as to the right of the trial court to so amend and thereby make final its judgment at a later term, we are not prepared to hold that authority wanting, under the conditions here shown. It is not contended that the correction or amendment made failed to reflect the true state of the record, or that it determined any issue not litigated at the original trial, but simply that the court was without power to enter it at a subsequent term.
In Young v. Pfeiffer, 30 S. W. 94, it is said:
“The judgment originally entered failed to dispose of the case as to one of the defendants, and therefore no appeal could be taken from it. The court clearly had power at a later term to enter a judgment that disposed of all the parties, which was done, and from the judgment so rendered the appeal was properly taken. Johnson v. Smith, 14 Tex. 412.”
Through appellant’s first assignment complaint is made of the overruling of her general demurrer to the trial petition of appel-lees Wright & Hearne; but, after an examination of the pleadings, we conclude there were at least two respects in which they alleged a cause of action: First, that there was a balance properly due them under their relation to the original contract upon the agreed cost therein fixed for the building; second, that after they, Wright & Hearne, came into the matter, a new agreement entirely had been finally made by all parties interested, under which they were to tear down the old roof, construct another one, and complete the building in other details, upon such arrangement as to the extra cost over the original contract price as might be arranged between them and appellant’s architect, Watson; that accordingly they did in fact take down the first roof, build a new one, and otherwise do further work upon the building, at the extra cost and of the reasonable value of $1,566.98 over the sum named in the original contract, which was all done under the architect’s direction, not . only at the instance and with the full knowledge and approval of Mrs. Rouser and her named architect, Watson, but, after being so done, was received and accepted by both. These allegations having stated a cause of action, it was not error to overrule the general demurrer.
Under the third assignment the action of the court in refusing to peremptorily instruct the jury to return a verdict for appellant is assailed upon the claim that the great preponderance of the evidence showed not only no obligation nor promise on her part to pay anything above the contract price, except a small excess in the foundation, but that she was entitled to $500 damages over against both the contractors and their bondsmen. It has been uniformly held that an assignment of this character presents nothing for review and cannot be considered. Speights v. Speights, 176 S. W. 641; Alexander v. Lumber Co., 154 S. W. 236; M., K. & T. Ry. Co. v. W. R. Patterson, 204 S. W. 1026, recently decided by this court, but not yet officially reported. If the assignment were considered, however, we should be compelled to find' that there was sufficient evidence in the record to support a verdict against appellant, which conclusion would necessitate the overruling of the assignment.
The fourth assignment is not in effect different from the first and third considered together, its specification being that the court erred in refusing appellant’s request for a peremptory instruction, on the alleged ground that there was, because of the contractual relation existing between her and the appel-lees, neither pleading nor evidence upon which a verdict or judgment against her could be based. Our preceding findings that, independent of the original contract between all the parties, which is the relation referred to in this assignment, a cause of action was alleged in appellees Wright & Hearne, and supported by their testimony that Mrs. Rouser authorized them to do as her architect, Watson, directed, thereby putting him in her place, meet the question here raised also, and require the overruling of the assignment.
The fifth and sixth assignments charge er *851 ror in the court’s refusal of appellant’s motion to enter judgment for her, because it is said, there was no evidence that she knew additional pay over the original contract price for rebuilding the roof was expected by appellees Wright & Hearne, nor any to support the jury’s finding that she had such knowledge, and none that she ever promised to pay them anything extra for such work. In further development of the idea thus presented it is then, in the seventh assignment, insisted the motion should have been granted, because no express agreement upon appellant’s part to pay extra for the reconstructed roof was either pleaded or proved, and on account of the contract then existing •between her and Wright & Hearne as bondsmen for the original contractors, Crawford & Hogue, obligating the bondsmen to place a good and sufficient roof on the building anyway, no implied contract to pay anything additional for the new roof could arise.
We are unable to agree to this contention, and overrule the .assignment urging it. In the state of case presented by this record we think there was nothing to forbid an implied promise upon Mrs. Rouser’s part to -pay for extras or for new work done upon changed plans and specifications. To what has been before recited, it may be added the jury found, upon what we deem sufficient evidence, the following facts:
(1) The roof put on the building by Crawford & Hogue under the original contract, after being braced with some iron truss rods, was in accord with the plans and specifications of appellant’s architect, Watson, and was accepted by him before they quit work upon the building.
(2) Although Mrs. Rouser herself refused to accept the roof as originally built by Crawford & Hogue, and objected to a change being made in it, afterwards appellees Wright & Hearne, under the direction of her architect, Watson, and with her own knowledge, consent, and approval, built to the satisfaction of herself and the architect, both in advance knowing that extra pay was expected for it, a comb or ridge roof upon the building, different from that called for in the original plans and specifications, and of the reasonable value of $1,566.98, which was duly accepted.
(3) Aside from so changing the roof, Wright & Hearne put further necessary work and material of the reasonable value of $988.50 into the completion of the building, substantially in accord with the plans and specifications and to the satisfaction of Mrs. Rouser and the architect, the latter knowing that pay outside of the original contract amount with Crawford & Hogue was expected therefor.
(4) The work done, by Crawford & Hogue prior to quitting the contract, including the roof they put on the building, was done in substantial accord with the plans and specifications furnished them by the architect, and there was left unpaid a difference of $279.14 between what had been paid to and assumed for them'by Mrs. Rouser and the contract price, as well as $294.26 more for extra work and material furnished by them. While this balance of $279.14 due Crawford & Hogue upon -their original contract might have been substantially reduced by further payments by Mrs. Rouser in completing the building of items which should properly be chargeable against them, still it was not entirely extinguished, unless the $500 damages found by the jury in Mrs. Rouser’s favor for defective plans and specifications could also be construed as applying against them. Upon considerations hereinafter stated, however, we do not think it could. So that, leaving that item out of consideration for the present, under the results thus otherwise disclosed, there was at least some balance due by Mrs. Rouser within the terms of the original contract, and independent of extras, no matter by whom furnished. That being true, even though no recovery could be had outside the terms of the contract here for extra work, except upon express promise to pay for it, as appellant so ably contends, her motion to have judgment generally entered for her could not prevail.
What has been already said disposes of the issues raised under the seventh and eighth assignments, and separate detailed discussion becomes unnecessary. In answer, however, to the insistence made in the eighth assignment that the measure of damages could not exceed the difference between the cost of reconstructing a safe and substantial roof -under the plans and specifications and that of the roof as actually constructed, in addition to the findings and conclusions previously stated, it may be added that the proof showed that no such roof could be built. . .
Under the, ninth and thirteenth assign- *852 merits it is claimed Mrs. Rouser was entitled to have the $500 the jury awarded her because of defects in the plans and specifications charged against the contractors, Crawford & Hogue, and their bondsmen, Wright & Hearne, and when that is done the balance of accounts would he in her favor. We do not so interpret the jury’s meaning. They had already repeatedly acquitted Crawford & Hogue of any failure to substantially comply with the plans and specifications furnished them by the architect, and, when the finding as to this $500 is compared with the others made, its manifest effect is, we think, that while Mrs. Rouser was damaged to the extent of the sum named it was because of the architect’s dereliction in furnishing defective plans and specifications, and not because of the failure of Crawford & Hogue to erect and complete the building in accordance therewith.
There are other assignments, but, after carefully considering them all, we conclude that none of them are well taken, and that those specifically discussed present the controlling questions in the case. Finding no reversible error, it has been ordered that the judgment be affirmed.
Affirmed.
©=oFor other cases see same topic and KEY-NUMBER in all Key-Numbered Digests.and Indexes
Reference
- Full Case Name
- ROUSER v. WRIGHT Et Al.
- Cited By
- 1 case
- Status
- Published