Frost v. Thomas
Frost v. Thomas
Opinion of the Court
This suit was brought by appellants against J. M. Thomas, E. O. Dreyer, and Ed. Dupree to cancel an oil and gas lease, upon the grounds of fraudulent misrepresentations in obtaining its execution.
For cause of action plaintiffs alleged, as contained in appellants’ brief:
“That they are the owners in fee simple of 640 acres of land known as section 29, block 29, township 1 north, Texas & .Pacific Railway Company Survey in Mitchell and Howard counties, Tex., and appellants about said date entered into an agreement with defendants Dreyer and Dupree, who claimed to represent other parties, who were desirous of drilling a deep test well on said section, and in order to get a drilling contract it was absolutely essential that appellants’ land should be obtained, and the sole and only purpose of obtaining the said section was for the purpose of development, and in event drilling was n.ot done any lease on said' land was to be null and void and of no effect. It was a condition of the trade that drilling was to begin within 90 days from the date of the lease and be pursued with due diligence, and the lease was to be held in escrow by said Dupree, with similar leases of his own, not to be delivered to. the company until actual operations were begun. Relying upon these representations, an oil and gas lease was executed by appellants, upon no consideration paid at the time, the real consideration being the drilling of a well within 90 days, to J. M. Thomas, for the benefit of an Arizona Oil Company, all of which representations were false, as the section was not obtained for the purposes set forth in appellees’ representations, and was not by Dupree turned over to a company to drill a deep test well; but, on the contrary, was by said Thomas assigned and transferred to E. O. Dreyer, who paid no consideration for the same. No well was commenced within the time specified in the said contract. The escrow agreement was violated and the lease placed of record by said Dreyer. While Dupree obtained a release of his own acreage from the lease executed by him.”
Defendants Thomas and Dupree filed disclaimers, and Dreyer genera! demurrer, and general denial.
Tried without jury, and judgment entered that plaintiff take nothing, from which an appeal is perfected.
There are ten assignments of error and many propositions attacking, all but two, the findings of fact and conclusions of law. We will therefore pass upon the merits of the questions presented in a general way without specifically taking up each assignment and proposition.
“In the latter case, however, an exception to the general rule was recognized. That case was one where the grantor in a conveyance to a right of way sought to cancel the conveyance on the ground of an unfulfilled promise to locate depot grounds, etc., on the plaintiff’s lands. In disposing of the case our Supreme Court said:
“ ‘To the above rule (the general rule above noted), however, we think that there is a well founded exception, though there is a conflict in the authorities upon the question. It has been distinctly recognized and announced by the Supreme Court, however, in this state. The exception may be stated as follows, and in reference to the case in hand: If the railway company, at the time it made the representations and promises before mentioned to the plaintiffs, did so with the design of cheating and deceiving the plaintiffs, and had no intention at the time of performing the promises, but used them merely as false pretenses to induce the plaintiffs to execute the deed, and' if its conduct did have that effect, then we think that such acts and declarations, coupled with its subsequent utter failure and refusal to perform the promises or assurances, would amount to such actual fraud as would authorize the plaintiffs to have the contract rescinded and the land restored to them. But, upon the other hand, if the promises and representations were made in good faith at the time of the contract, and the defendant subsequently changed its mind and failed or refused to perform the promises, then such conduct of the company, originally or subsequently, would not. * * * justify the rescission, of the contract or the cancellation of the deed.’ ”
Burehill v. Hermsmeyer (Tex. Civ. App.) 212 S. W. 767.
For the plaintiffs to maintain this action, therefore, the burden was upon them to show that Dreyer and Dupree, at the time they made the oral statements, if they did so at all, did not intend to fulfill them, but intended to thereby deceitfully induce the plaintiffs to execute the lease. There may be some evidence in this record that the parties did not intend to perform, but there is sufficient evidence to support the findings, by thd court:
“That the lease contract was executed under circumstances free from fraud, that all the par *307 ties signed it with a fair understanding of its provisions.”
The logical effect of this finding is that the representations alleged to have been made as an inducement to the execution of the contract were not in fact made.
Conceding this to be a valid objection and that it was incompetent evidence, there is nothing in this case to indicáte that the court considered it in arriving at the finding that there was no fraud. Therefore, is not reversible error. Melton v. Cobb, 21 Tex. 539; Orient Land Co. v. Reeder (Tex. Civ. App.) 173 S. W. 939.
The next is:
“The court erred in admitting the testimony of Dreyer to the effect that he was holding the section in question for the Southwestern Oil & Leasing Company, a New Mexico corporation, without a permit to do business in Texas, because there is no pleading to support it.”
Finding no reversible error, the cause is affirmed.
tf&ssFor-other oases see same topic and KEY-NUMBER in all Key-Numbered Digests and Tndexes
Reference
- Full Case Name
- FROST Et Al. v. THOMAS Et Al.
- Cited By
- 5 cases
- Status
- Published