Pool v. Sanford
Pool v. Sanford
Opinion of the Court
It is contended by appellantPool that appellees Moore & Co. and Wedemeyer & Schulte had no right to intervene in this case.
In 2 Chitty’s General Practice, 492, it is stated that “ if any third person consider that his interest will be affected by a cause which is pending, he is not bound to leave the care of his interest to either of the litigants, but has a right to intervene or be made a party to the cause, and to take on himself the defense of his own rights, provided he does not disturb the order of the proceedings.”
In Brown v. Saul, 4 Mart., N. S., La.,) 434, decided in the Supreme Court of Louisiana, to which State we can very appropriately look for light upon this question, it was held, that to give this right the intervenor should have with one of the original parties a union of interest in relation to the subject-matter in dispute, and that this interest should be founded on some right, claim, or lien, either conventional or legal, directly and closely connected with this subject-matter.
Mr. Pomeroy, in his work on Remedies and Remedial Rights, sec. 430, after a review of the decisions in Iowa, California, and Louisiana, sums up the doctrine of intervention in the following language:
“ The intervenor’s interest must be such, that if the original action had never been commenced, and he had first brought it as the sole plaintiff*, he would have been entitled to recover in his own name to the extent at least of a part of the relief sought; or if the action had first been brought against him as a defendant, he would have been able to defeat the recovery, in part at least. His interest may be either legal or equitable.”
It is believed that our practice substantially conforms to these principles, and permits intervention in suits for real or personal
Upon the issues as presented by the pleadings, we are of opinion that the claims of the original plaintiff, Sanford, and of the intervenors were so intimately connected, and so dependent the one upon the other, as to present a proper case and subject-matter for intervention, so that the respective rights and interests of all the parties, including the plaintiff himself, could be adjusted and protected. (Phil. on Mech. Liens, sec. 205; Loonie v. Hogan, 5 Seld., (9 N. Y.,) 440.)
To hold otherwise might, subject the property to the very liability suggested by appellant—the enforcement of two or more liens for the same indebtedness. (Waldroff v. Scott, 46 Tex., 1.)
The demurrer of appellant Pool, defendant below, to the pleadings of Sanford, the original plaintiff’, so far as he sought to enforce his alleged mechanic’s lien, should have been sustained. The right to such lien depends upon a substantial compliance with the statute giving the same.
The requisites of the statute are necessarily descriptive of the lien, and if omitted in the pleadings should subject them to demurrer. (Tinsley v. Boykin, 46 Tex., 599; Sutherland v. Ryerson, 24 Ill., 517; Shaw v. Allen, 24 Wis., 564.)
The only allegation in the petition, in regard to the lien, was that plaintiff claimed “that the work and materials furnished by him in his business as a mechanic gave him a lien upon the said dwelling and lots.”
If, however, the pleadings of plaintiff had been sufficient on general demurrer, they were clearly insufficient when tested by the special demurrers of defendant, and these should have been sustained.
The same objection applied to the petition of intervenors Moore & Co., so far as they sought a lien, either as principal
Rule 19 of this court, for the government of the District Courts, (47 Tex., 620,) provides that exhibits may be attached to a pleading, and referred to as such, in aid and explanation of the allegations therein; but this will not relieve the pleader from making the proper allegations, of which the exhibits maybe the evidence, in whole or in part.
This is but declaratory of what the proper practice was before the adoption of the rules, and tested by it, the demurrer to so much of the pleadings of Moore & Co. as claimed a lien should have been sustained. These iutervcnors did not, by-proper and appropriate allegations, show that either the original plaintiff, Sanford, or they themselves were entitled to a mechanic’s lien.
The petition of Wedemeyer & Schulte did not show that Sanford was entitled to the mechanic’s lien, but it was sufficient to entitle them, if sustained by the evidence, to such lien as principal contractors themselves. There is no statement of facts in the record, hut there were certain special verdicts in response to issues made up under the direction of the court, and which, under the statute, are “ conclusive between the parties as to the facts found.” (Paschal’s Dig., art. 1469; Rev.Stats., art. 1332.)
' Although there seems .to be some inconsistency in these special verdicts, yet, in our opinion, their legal effect, as presented to us, is, that the contracts with both Moore & Co. and Wedenmyer & Schulte were made with Sanford, tho original contractor, and not with appellant Pool, the owner. If this were so, it would make them sub-contractors under Sanford,
For the error of the court in overruling the exceptions of appellant Pool to the original petition of plaintiff, Sanford, and to the petition for intervention of Moore & Co., in so far as the same claimed the mechanic’s lien, and the further error in rendering judgment on the special issues in favor of both intervenors for the enforcement of such lien, the judgment must be reversed.
As the cause will be remanded, it is proper that we indicate our opinion upon certain questions which are presented in the record, and which may arise on another trial.
1. To authorize the court to decree to either the original plaintiff or the intervenors a judgment for the enforcement of the mechanic’s lien as original contractors, they must, by appropriate allegations and proof, show that they are entitled to the same. In our opinion, the intervenors Moore & Co. come under the designation, “ any person or firm,” used in the statuto, and are within both its letter and spirit. (Paschal’s Dig., art. 7112.)
2. As heretofore decided by this court, the mere fact that the intervenors were sub-contractors, would not, as such, entitle them to the statutory mechanic’s lien. (Shields v. Morrow, 51 Tex., 393; Horan v. Frank, 51 Tex., 401; Loonie v. Frank, 51 Tex., 406.)
If, however, under appropriate allegations, the testimony should showr that they, or cither of them, were sub-contractors under Sanford, and that they availed themselves of the special provisions of the statute in the nature of a garnishment, and thereby adjusted the “true sum due” them by Sanford as original contractor, and fixed liability upon Pool, the owner,
3. Pool, as owner, could not be compelled to pay, including all prior voluntary payments made in good faith, according to the terms of his contract as originally or subsequently made, and for which a lien was fixed and secured under the statute, any greater amount than the contract price. (Paschal’s Dig., art. 4598; Laws 15th Leg., sec. 6, p. 92; Rev. Stats., art. 3176; Doughty v. Devlin, 1 E. D. Smith, (N. Y.,) 634; Russell v. Bell, 8 Wright, (Penn.,) 53; Horan v. Frank, 51 Tex., 401; Phil, on Mech. Liens, secs. 206-213, and authorities cited)
4. To entitle the intervenors to be subrogated to the rights of the principal contractor, the statutory notice in the nature of a garnishment, by service of “an attested account of the amount and value of the work and labor thus performed or materials furnished and remaining unpaid,” must have been given. (Paschal’s Dig., art. 4595.) Mere ordinary notice, information, or knowledge, on the part of the owner, that the principal contractor was indebted to them, would not, of itself, be sufficient to bind the owner.
5. If the testimony should show that the intervenors, as subcontractors, were about to abandon the work because they were apprehensive that the principal contractor would not pay them, or for other good and sufficient reason, and that to prevent this they were induced by the owner, Pool, to continue and complete their part of the work in consideration that he would pay them therefor, this would be a sufficient original understanding to take the contract without the statute of frauds and to bind Pool, and the intervenors could, in any event, recover against him a personal judgment, or a judgment enforcing the mechanic’s lien in their favor as original
The judgment below is reversed and the cause remanded for further proceedings in accordance with this opinion.
BeVERSED • AND REMANDED.
Reference
- Full Case Name
- William Pool v. John H. Sanford
- Cited By
- 38 cases
- Status
- Published
- Syllabus
- 1. Intervention.—To entitle a party to intervene in a suit pending, his interest, legal or equitable, must be such, that had the original action never been commenced, and the intervenov had brought the suit in his own name as sole plaintiff, lie would have been entitled to recover in his own name to tlie extent at least of a part of the relief sought; or had the action been first brought against him, as a defendant lie would have been able to defeat the recovery, in part at least. 2. Tact cases.—See statement of case for causes for action justifying intervention. 3. Mechanic’s lien.—The right- to a mechanic’s lien depends on a substantial compliance with the statute which confers it. 4. Mechanic’s lien—Pleading. —The requisites of the statute conferring a mechanic’s lien are necessarily descriptive thereof, and if omitted in the pleading claiming the enforcement of such lien, will subject it to demurrer. 5. Case APPROVED.—Tinsley v. Boykin, 46 Tex., 599, approved. 6. Exhibit—Pleading.—An exhibit attached to a petition claiming it mechanic’s lien, which exhibit upon its face shows that it was recorded, and that a copy thereof was served upon defendant as required to fix tlie lien, will not relieve the pleader from the necessity of ax-erring those facts. 7. Exhibits—Pleading.—An exhibit filed with a plea can only, under rule 19, for the government of tlie District Courts, be looked to in aid and explanation of specific allegations made in the plea. S. Practice—Special verdict.—In the absence of a statement of facts, special findings of the jury trying the cause beloxv, in response to issues submitted, will be regarded as conclusive between tlie parties as to tlie facts found. 9. Pleading—Lien—Contractor.—See case for pleading and verdict, under which it xx-as held error to render judgment for an iutervenor enforcing a lien as an original contractor. 10. Mechanic’s lien.—Under article 7112 of Paschal’s Digest, one furnishing material used in the construction of the house, xvho complies with the requisites of the law to fix the lien conferred by tlie statute, is entitled to its provisions without alleging or proving his vocation as an artisan or mechanic. 11. Sub-contractor—Garnishment—Equity—Lien.—A sub-contractor xvlio xvill ax-ail himself of the special provisions of the statute in the nature of a garnishment, and thereby adjust the “true sum due” him from the original contractor, and fix tlie liability of tlie owner of tlie property for its payment, may afterwards, in a proper case, upon sufficient allegations and proof of collusion between the owner and the original contractor, or fraud or insolvency of the parties, he subrogated to the rights of the principal contractor, both as to the amount due as thus adjusted and also as to the mechanic's lien to secure the same. 12. Mechanic's lien.—The owner of property who contracts for the construction of a building thereon, cannot be compelled to pay any greater amount under his contract than the contract price, including-all prior voluntary payments made in good faith, according to the terms of his contract, for winch a lien was fixed and secured for the benefit of the principal contractor under the statute. 13. Sub-contractor—Subrogation.—To entitle a sub-contractor, or one who has furnished materials, to be subrogated to the rights of a principal contractor, the statutory notice in the nature of a garnishment, by service of an attested account of the amount and value of the work and labor performed or materials furnished and remaining unpaid, must have been given. Mere ordinary notice, information, or knowledge on the part of the owner, that the principal contractor was indebted to the sub-contractor, would not, of itself, be sufficient to bind the owner. 34. Same—Statute of frauds—Lien.— See concluding portion of opinion for facts which would take a verbal contract by a sub-contractor but of the statute of frauds, and would entitle him, on complying with the statute regulating liens, to the rights of an original contractor.