Allis-Chalmers Manufacturing Co. v. Curtis Electrical Co.
Allis-Chalmers Manufacturing Co. v. Curtis Electrical Co.
Opinion of the Court
delivered the opinion of the Court.
The parties will be identified as in the trial court. See 259 S.W. 2d 918 for opinion of the Court of Civil Appeals.
Plaintiff furnished electrical equipment used by the Curtis Electrical Company (a corporation) as electrical subcontractor in the construction of dormitories upon the campus of the Agri
Plaintiff contends that the bond is not within Art. 5160 because the building was financed by the sale of revenue bonds under Ch. 5, Acts of the Second Called Session of the 43rd Legislature; Ch. 204, Acts of the Regular Session, 44th Legislature ; and Ch. 459, Acts of the Second Called Session of the 44th Legislature. Vernon’s Am. Civ. Stat. Art. 2603c. The question is whether buildings constructed under these acts are the result of “a formal contract with this state or its counties or school districts or other subdivisions thereof or any muncipality therein for the construction of any public building.” Plaintiffs say that because the state is exempted from liability the Board of Directors of A. & M. College acts as a separate entity in issuing revenue bonds for the building of dormitories. We agree with the Court of Civil Appeals in overruling this contention and hold that the Board of Directors of A. & M. College is an agency of the State within the meaning of Art. 5160 in erecting a dormitory upon the campus of A. & M. College to be financed by revenue bonds issued under the statutes cited above. See cases cited and discussed by the Court of Civil Appeals and see also State of Arkansas v. State of Texas, 346 U.S. 368, 74 Sup. Ct. 109, 98 Law Ed. 71.
On September 19, 1939 plaintiff billed Curtis upon “Regular terms; Net cash 30 days payable in Milwaukee-Chicago-New York Exchange.” On September 25th Curtis wrote plaintiff that he would personally guarantee a 30-day trade acceptance due October 31, 1939, in the amount of $5,990.43. On October 4, 1939, plaintiff wrote Curtis asking for a check in the amount of $1,352.72 and execution of a trade acceptance due October 31st in the amount of $5,000.00, but by mistake sent a trade acceptance in the amount of $6,000.00. On October 9, 1939, Curtis wrote plaintiff returning the $6,000.00 trade acceptance and suggesting a 60-day trade acceptance in the amount of $5,000.00 due December 1, 1939. On November 3, 1939, plaintiff wrote Curtis a letter containing the following statement:
Curtis did not execute this trade acceptance.
The effect of this negotiation was that Curtis started off with a request that his payment be delayed for 30 days from September 25th. This delay was achieved as a result of the negotiation about mistakes in the account. Had Curtis’ first offer been accepted he would have had to pay this account on October 25th. On October 4th plaintiff wrote asking for a trade acceptance due October 31st. On October 9th Curtis suggested a 60-day trade acceptance due December 1st. Since the period was actually 51 days this amounted to an offer to predate the instrument. Plaintiff’s reply to this was its trade acceptance dated October 30th and due November 30th. This amounts to a substantial meeting of the minds. In the ordinary course of business this account should have been paid by October 19th. A difference of one day in the maturity is not substantial since Curtis did gain the delay he was seeking. There is no proof that the one day difference materially affected the parties or adversely affected Curtis in any manner. This cause of action is not upon the acceptance itself but upon Curtis’ promise to endorse it personally.
The judgment of the Court of Civil Appeals is reversed to the extent that it denies a recovery against Curtis personally in the amount of $5,000.00 and judgment is here so rendered. Costs are taxed against Chas. E. Curtis.
Opinion delivered February 10, 1954.
Dissenting Opinion
joined by Justice Calvert, dissenting.
I am in agreement with the majority opinion insofar as it holds that the building contract and bond fall within the provisions of Article 5160, Vernon’s Annotated Civil Statutes; and the petitioner, not having compiled with the requirement of Article 5160, cannot recover.
I cannot agree that C. E. Curtis is individually liable to petitioner. For him to be liable there must have been a contract — a meeting of the minds — between petitioner and Curtis that Curtis should be liable. Curtis’ liability is predicated solely upon an exchange of letters between the parties.
As I understand the law of contracts, it has long been settled that before a contract can be made between parties there must be a meeting of the minds of the parties upon identical terms of the contract. The acceptance must be unqualified and unconditional, and in the exact terms of the offer. 10 Texas Jur. 42, Contracts, Sec. 23; 12 Am. Jur. 543, Contracts, Sec. 53; 17 C.J.S. p. 378, Contracts, Sec. 42. One of the most recent statements of this rule is found in the case of Garrett v. International Milling Co., Texas Civ. App., 223 S.W. 2d 67, 72 (1-6), no writ history, wherein it is said:
“In Summers v. Mills et al, 21 Texas 77, the Supreme Court said: ‘It does not matter that the difference of terms between the parties may not seem to be very material. If a diversity exists, that fact is enough. To make a contract there must be a mutual assent. “The assent must comprehend the whole of the proposition ; it must be exactly equal to its extent and provisions, and it must not qualify them by any new matter.” If the answer, “either in words or effect, departs from the proposition, or varies the terms of the offer, or substitutes for the contract tendered one more satisfactory to the respondent,” there is no assent and no contract. Pars. Con. 400. “If a proposition be accompanied with certain conditions or limitations, the acceptance must correspond to it exactly, for if any alteration be suggested, or any exception be made to its exact terms, the provisional acceptance becomes merely a new proposition, which also requires an acceptance.” ’
“The following additional authorities support the above propositions: Browne Grain Co. v. Walker, Texas Civ. App., 206 S.W. 859; Whitaker v. Zeihme et al, Texas Civ. App.,61 S.W. 499; Womack v. Dalton Adding Machine Sales Co., Texas Civ. App., 285 S.W. 680; Great West Grain & Seed Co. v. Ray, Texas Civ. App., 204 S.W. 2d 26, writ refused, no reversible error; Moore Bros. v. Kirkpatrick, Texas Civ. App., 172 S.W. 2d 135.” 1st. col., p. 72, 2nd par.
I would hold that Curtis is not individually liable.
Dissenting Opinion
also dissenting.
I cannot agree with the majority opinion wherein it denies the petitioner a recovery against the respondent, American Indemnity Company.
The petitioner filed this suit against respondents, Curtis Electrical Company, Charles E. Curtis, and American Indemnity Company to recover against them a balance due on a contract between Curtis Electrical Company and the petitioner. Judgment was entered in the trial court against Curtis Electrical Company for the balance due under the contract. This part of the judgment has become final and is not before this Court. The trial court denied petitioner a recovery against Charles E. Curtis and the American Indemnity Company. The Court of Civil Appeals
Petitioner contends that the performance bond executed by the American Indemnity Company was not required by Article 5160, Vernon’s Annotated Civil Statutes, but was given independently of any statutory requirement. I think the terms and conditions of the contract involved have an important bearing on the question of whether or not the statutory requirements apply. The terms of this contract are identical with those of the general contract between W. S. Bellows Construction Company and The Board of Directors of The Agricultural and Mechanical College of Texas.
Paragraph 13 of the contract reads as follows:
“13th. And it is hereby mutually agreed between the parties hereto that the sum to be paid by the Owner to the Contractor for said work and materials shall be Seventy Five Thousand Eight Hundred Thirty and 00/100 Dollars ($75,830.00) subject to the additions or deductions on account of alterations herein-before provided, and that such sum shall be paid in current funds by the Owner to the Contractor in installments as follows: Eighty-five per cent (85%) of the value of work and materials incorporated in the building or buildings and fifty per cent (50%) of the value of acceptable materials stored upon the site for use in the buildings, upon estimate issued by the Architect once every thirty days, if required, and the balance after the entire completion and acceptance of the work.
“It being understood that the final payment shall be made within ten days after this contract is completely finished, with the exception of ten per centum of total contract price which (at option of Owner) shall be held for 30 days, for protection of labor, as provided by law; provided, that in each of the said cases the Architect shall certify that all the work upon the performance of which the payment is to become due has been done to their satisfaction; provided, further, that before each payment, if required, the Contractor shall give the Architect good and sufficient evidence that the premises are free from all liens and claims chargeable to the said Contractor, and, further, that if at any time there shall be any lien or claim for which, if established, the Owner or the said premises might be made liable, and which would be chargeable to the said Contractor, the Owner shall have the right to retain out of any payment then due or thereafter to become due, an amount sufficient to completely indemnify it against such lien or claim, until the claim
The majority has affirmed the judgment of the Court of Civil Appeals holding, that the contract here involved, which was between respondent, Curtis Electrical Company and the Board of Directors of A. & M. College, was a contract with the State. The opinion cites the case of Fidelity & Deposit Company of Maryland v. Big Three Welding Equipment Co., Inc., 151 Texas 278, 249 S.W. 2d 183 as authority for the holding that the bond falls within Article 5160, Vernon’s Annotated Civil Statutes, and, therefore, the petitioner cannot recover because of its failure to comply with the provisions of the statute. The petitioner contends that the question here involved has never been before the courts of this or any other jurisdiction and is one of first impression. I agree with this position. The cases cited by the Court of Civil Appeals and the majority opinion have no application here. The Big Three Welding Company case, supra, involved a contract between the City of Houston and Shannon Company, Incorporated. The performance bond was executed by Shannon Company, Inc., as principal, and the Fidelity & Deposit Company of Maryland, as surety. The contract did not contain provisions we find in paragraph 13 and other provisions of the contract here under consideration. The case of Employers’ Liability Assur. Corporation, Limited, v. Young County Lumber Co., 122 Texas 647, 64 S.W. 2d 339, has no application in the case at bar. It reached this Court by way of certified question from the Court of Civil Appeals. The certificate recites that John T. Abies entered into a contract with Archer County, and that “ ‘ * * * to insure the faithful performance of the contract Abies executed a bond with the Employers’ Liability Assurance Corporation, Limited, as surety, in accordance with the requirements of article 5160, Rev. Civ. Statutes, as amended by the 41st Legisla
The certificate further recites that on January 27, 1930, John T. Abies with the same surety executed another bond in favor of certain other persons who had furnished service and labor. “ * * The principal and surety bound themselves to pay to the claimants or their assigns the “amounts of their respective claims, or such portion or portions thereof as may be proved to have been levied under the terms of chapter 17, General Laws of the State of Texas, * * * (Vernon’s Ann. Civ. St. arts. 5472a, 5472b) * * *” ’ ” “ The bond further recites that Abies was executing and filing the same because he desired to file with Archer County, Texas, a bond pursuant to and conditioned as provided, * * * by Article 5472b-l, Rev. Civ. Statutes, 1925.’ ” Again, in this case, as in the Big Three Welding Company case, supra, we have a clear demonstration that the contract and contractor’s bond were executed in strict compliance with the terms of Article 5160, and the two other bonds were executed in accord with other articles of the statute. The provisions were read into the contract's and bonds and considered as a part of such instruments. There was no material difference between the conditions in the bonds and the conditions in the statute. The provisions of the contract and the condition of the bond when considered together, as they properly should be considered, clearly demonstrate that the bond is not a statutory bond. For example, Article 5160, supra, provides that after completion and acceptance of a project all moneys due contractor shall be held by the State or its counties or school districts or other subdivisions thereof or any municipality until such time that satisfactory evidence is submitted and affidavits made by the contractor that all just bills for labor and material under the contract have been paid by the contractor.
Article 5160, supra, provides that “* * * all claims for labor and material furnished to any contractor shall be itemized and sworn to as required by Statutes as to mechanic’s lien claims, and such claims shall be filed with the County Clerk * * And, Article 5472a, Vernon’s Annotated Civil Statutes, provides: “That any person, * * * furnishing any material, apparatus, fixtures, machinery or labor to any contractor for any public improvements in this State, shall have a lien on the moneys, or bonds, or warrants, due or to become due to such contractors for such improvements; provided, such person * * *, shall, before any payment is made to such contractor, notify in writing the officials of the State * * * whose duty it is to pay such contractor of his claim.” How can it be successfully argued that these articles shall be considered as a part of a contract and bond when the instruments contain provisions wholly repugnant thereto? The contract under consideration contains the following provision : “And it is further understood and agreed that the Contractor shall and will pay off and satisfy all claims of sub-contractors or others for labor or material furnished upon said building, and which may be found to be justly due and owing, whether or not the same can be established as a lien against said property for which said property or the Owner would be liable; it being the true intent and meaning hereof that the Contractor shall pay off and satisfy all bills incurred for labor and material in the erection of said building and found to be justly due and owing, whether established as liens or not.” (Emphasis added.)
There is nothing unlawful or in violation of public policy contained in this contract, and it is not so claimed. The contract was entered into pursuant to Chapter 5,' Acts of the Second Called Session of the 43rd Legislature; Chapter 204, Acts of the Regular Session, 44th Legislature; and Chapter 459, Acts of the Second Called Session of the 44th Legislature. The bond guaranteed the performance of the contract regardless of whether liens were established or not. I have been unable to find any case wherein the contract contained such provisions as found in the contract under discussion. The respondent, American Indemnity Company, assumed obligations by executing the performance
The debt claimed by petitioner has been established by judgment of the court and has not been satisfied. The bond was “made for the use and benefit of all persons, firms and corporations who may furnish any material or perform any labor for or on account of said work, building or improvement, and they, and each of them are hereby made obligees hereunder, the same as though their own proper names were written herein as such, and they and each of them may sue hereon, and no change of, or deviation from, the time, manner or amount of payments to the Contractor * * * shall affect or in any manner release the liability of the surety on this bond.” The performance bond was in favor of A. & M. College and not to the State of Texas. The contracts involved were not entered into “with this state or its counties or school districts or other subdivisions thereof or any municipality therein for the construction of any public building, or the prosecution and completion of any public work” in the sense that the State of Texas would in any manner be deemed liable. But, on the contrary, the statutes, supra, expressly provide that all undertakings under the contract between the Board of Directors of A. & M. College and the contractor shall be “without cost to the State of Texas.” The American Indemnity Company, one of the respondents herein, was charged with knowledge of this fact, and the further fact that the members of the Board could not and would not be held individually liable. To release the surety company from liability in this case will work an injury to the laborer and the materialman. The respondents in this case guaranteed performance independently of any statutory requirement. The majority opinion requires the petitioner to perform a useless act for its protection. Under the record in this case it had protection without the necessity of establishing a lien. The Big Three Welding Company case, supra, holds that in order to recover the materialman must show that he has established a lien as required by statute, and the majority opinion in this case recognizes such holding was erroneous. However, I am of the opinion there exists a distinct difference between the provisions of the two bonds and contracts.
Petitioner’s point that the respondent, Charles E. Curtis, under the evidence, is liable for the debt of the Curtis Corporation should be sustained. I, therefore, concur with the majority on this point for the following reasons: On September 25, 1939, Charles E. Curtis, President of Curtis Electrical Company, in a letter addressed to petitioner, admitted that the corporation was
On October 9, 1939, Charles E. Curtis, in behalf of the Curtis Electrical Company, addressed another letter to petitioner wherein it was stated that the balance due was the sum of $5,886.53. The last paragraph of the letter reads: “We are also returning your trade acceptance as you will note that it is made out for $6,000 whereas your letter states $5,000 is the amount, which is no doubt an error. We suggest that you remake the trade acceptance for 60 days being due Dec. 1, 1939 for $5,000 and we will send you our check for $886.53 immediately; and in the meantime you issue us a credit memorandum for $66.19 or correct your invoice F-60,671 of 8/15/39 to $7,000 less $466.19, or $6,533.81 and everything will be straight again.” On November 3, 1939, in a letter addressed to Curtis Electrical Company, petitioner agreed that the balance due was $5,886.53, and attached a new trade acceptance for $5,000 dated October 30, 1939 due Nov. 30, 1939. The letter suggested the execution and return of the trade acceptance “along with your check for $866.53.”
Mr. Curtis voluntarily offered to personally guarantee and, if necessary, sign the trade acceptance. Apparently his company was involved financially when he made the offer to personally guarantee and sign the trade acceptance. The offer was accepted
I would reverse and render the judgments of the trial court and the Court of Civil Appeals.
Opinion delivered February 10, 1954.
Reference
- Full Case Name
- Allis-Chalmers Manufacturing Company v. Curtis Electrical Company Et Al
- Cited By
- 19 cases
- Status
- Published