City of Corpus Christi v. Public Utility Commission of Texas
City of Corpus Christi v. Public Utility Commission of Texas
Opinion of the Court
In 1999, the Legislature substantially revised the Public Utility Regulatory Act (PURA) to bring about a major restructuring of the electric power industry in Texas to allow retail electric rates to be determined by competition. As part of that restructuring, the PURA permits existing utilities to recover “regulatory assets” and “stranded costs” through securitization financing. Securitization is accomplished through a financing order issued by the Public Utility Commission that authorizes a utility to issue a transition bond. The transition bond is repaid or secured by transition charges to electric power consumers in a utility’s service area. Central Power and Light Company, an existing utility, applied for and the Commission approved a financing order that assures that CPL will recover certain of its regulatory assets through securitization. Two separate proceedings were brought in a Travis County district court seeking review of that order on different grounds. Final judgments were rendered in both proceedings affirming the Commission’s order. We granted direct appeals from those judgments pursuant to section 39.303(f) of the PURA and consolidated the two proceedings.
Power Choice, Inc., the appellant in one of the appeals, contends that the securiti-zation provisions of the PURA are facially unconstitutional under the Texas Constitu
In the appeal by numerous cities including the City of Corpus Christi, and by Texas Industrial Energy Consumers and the Office of Public Utility Counsel, we also affirm the trial court’s judgment. We hold that: 1) regulatory assets known as “SFAS 109 assets” may be securitized even though they currently earn no return and have no carrying costs; 2) the Commission properly treated investment tax credits; 3) the Commission did not err in securitizing regulatory assets reflected in CPL’s SEC Form 10-K rather than the balance of those assets as of December 31, 2001; 4) the PURA authorizes the Commission to prescribe what it calls a “nonstandard true-up”; 5) the Commission did not err in declining to adjust the allocation factors for industrial customer classes to reflect load loss; 6) the Commission did not err in its allocation of transition charges to non-firm industrial customer classes; and 7) the Cities were not denied due process in the proceedings before the Commission. Accordingly, we affirm the trial court’s judgment. Justice Owen’s concurring opinion is the opinion of the Court with respect to the issues that it addresses, and Justice Hecht’s concurring opinion is the opinion of the Court with respect to the issue that it addresses.
Justice HECHT filed a concurring opinion, in which Chief Justice PHILLIPS, Justice ABBOTT, Justice HANKINSON, and Justice JEFFERSON joined.
Justice OWEN filed a dissenting opinion, in which Justice ENOCH and Justice BAKER joined.
Concurring Opinion
joined by Chief Justice PHILLIPS, Justice HECHT, Justice ENOCH, Justice BAKER, Justice ABBOTT, Justice HANKINSON, and Justice JEFFERSON, concurring.
I
The Public Utility Regulatory Act (PURA) first came into being in 1975. At that time, the Legislature established a comprehensive regulatory system for electric utilities.
In 1999, the Legislature decided to chart a new course for the provision of electric service in Texas. In the years intervening since 1975, partial deregulation at the federal level and deregulation in other states had wrought significant changes in the electric industry on a national level. The Legislature concluded that it was in the public interest to establish a “fully competitive electric power industry” in Texas.
In order to achieve competition in the retail market for electricity, the amendments to the PURA require existing utilities to “unbundle” the services that they provide.
Underpinning the Legislature’s decision to restructure the electric power industry was its finding that regulation was no longer warranted, except for regulation of transmission and distribution services and regulation of the recovery of stranded costs:
The legislature finds that the production and sale of electricity is not a monopoly warranting regulation of rates, operations, and services and that the public interest in competitive electric markets requires that, except for transmission and distribution services and for the recovery of stranded costs, electric services and their prices should be determined by customer choices and the normal forces of competition.11 Stranded costs have a precise, technical definition under chapter 39 of the PURA:
“Stranded cost” means the positive excess of the net book value of generation assets over the market value of the assets, taking into account all of the electric utility’s generation assets, any above market purchased power costs, and any deferred debit related to a utility’s discontinuance of the application of Statement of Financial Accounting Standards No. 71 (“Accounting for the Effects of Certain Types of Regulation”) for generation-related assets if required by the provisions of this chapter. For purposes of Section 39.262 [true-up proceeding], book value shall be established as of December 31, 2001, or the date a market value is established through a market valuation method under Section 39.262(h), whichever is earlier, and shall include stranded costs incurred under Section 39.263 [stranded cost recovery of environmental cleanup costs].12
Stranded costs can more generally be described as the portion of the book value of a utility’s generation assets that is project
The Legislature determined that it is in the public interest for existing utilities to recover certain stranded costs in charges that are “nonbypassable.”
The Legislature similarly concluded that “regulatory assets” should be recoverable through nonbypassable charges.
“Regulatory assets” means the generation-related portion of the Texas jurisdictional portion of the amount reported by the electric utility in its 1998 annual report on Securities and Exchange Commission Form 10-K as regulatory assets and liabilities, offset by the applicable portion of generation-related investment tax credits permitted under the Internal Revenue Code of 1986.16
Regulatory assets are a subset of generation-related costs reasonably incurred by a utility that the Commission has determined in prior rate cases could be included in rates and recovered over a period of years instead of at the time the expenditure was made. They differ from “stranded costs,” as defined above, because stranded costs are investments in or the cost of tangible assets. Regulatory assets are essentially bookkeeping entries that reflect a charge to be included in a utility’s future rates. In the Commission’s reports to the Legislature about major issues that would arise if the electric power industry were deregulated, the Commission projected that all of a utility’s regulatory assets would be stranded if competition in retail sales occurred and no provision was included to address them. That is because regulatory assets have no market value absent a regulatory scheme that assures their recovery.
In deciding to proceed with deregulation of retail rates, the Legislature concluded that incumbent utilities should be allowed
The Legislature also established an alternative method by which a utility could recover certain stranded costs and regulatory assets, which is through securitization financing under subchapter G of chapter 39 of the PURA. The Legislature authorized the Commission to adopt financing orders that permit an electric utility to issue transition bonds or other evidences of indebtedness.
The Commission is directed by section 39.301 of the PURA to ensure that securi-tization of costs by a utility results in benefits to consumers. Section 39.301 provides:
The commission shall ensure that securi-tization provides tangible and quantifiable benefits to ratepayers, greater than would have been achieved absent the issuance of transition bonds.... The amount securitized may not exceed the present value of the revenue requirement over the life of the proposed transition bond associated with the regulatory assets or stranded costs sought to be securitized.22
A securitization financing order establishes “transition charges” to be paid by retail customers in a utility’s service area that allow recovery of “qualified costs.”
The PURA sets forth a “true-up” mechanism that is intended to ensure that no utility overrecovers stranded costs through competition transition charges.
The financing order at issue in this case authorizes CPL to obtain securitization financing for the net amount of $763,734,489 in regulatory assets. The financing order establishes transition charges to ensure payment of the transition bonds. None of CPL’s stranded generating plant costs are included in the financing order. Stranded generating plant costs are to be estimated in a proceeding that was pending before the Commission at the time this case was submitted. That proceeding is not part of these appeals. Nevertheless, the appeal by Power Choice broadly challenges the constitutionality of transition charges, irrespective of whether the underlying transition bonds securitize regulatory assets or stranded costs. Because Power Choice’s principal challenges would moot the appeal by the City of Corpus Christi and others, we turn first to Power Choice’s appeal.
II
Power Choice hopes to compete with CPL in the geographic area in which CPL is currently authorized by the Commission to provide service. The financing order under consideration establishes transition charges and directs all retail electric suppliers in CPL’s service area, which would include Power Choice, to collect those transition charges and pass them on to CPL.
Power Choice contends that the entire securitization scheme under the PURA is unconstitutional on several grounds. Power Choice argues that the nonbypassable charges are not rates because, it contends, they are unrelated to the cost of electricity that is actually used by retail customers. Power Choice also contends that transition charges are not rates because they are unrelated to any service provided to customers if they choose to purchase electricity from retail providers other than an incumbent utility. Power Choice further asserts that transition charges have no underlying public purpose because they are only a transfer of money from one private party to another. The result, Power Choice contends, is that the securitization provisions violate “the protections of the tax, taking, and appropriation and grant clauses of the Texas Constitution.” Power Choice relies on Article VIII, Section 3; Article I, Section 17; Article XVI, Section 6, and Article III, Section 51 of the Texas Constitution.
In approving CPL’s financing order, the Commission did not specifically address Power Choice’s constitutional arguments, apparently concluding that it lacked the power to rule on them. Power Choice appealed to a Travis County district court in accordance with section 39.303(f) of the PURA. That court rejected all of Power Choice’s arguments, holding that the secu-ritization provisions of the PURA did not violate any of the sections of the Texas Constitution on which Power Choice relied.
In this Court, as in the district court, Power Choice primarily mounts a facial challenge to the constitutionality of the securitization provisions of the PURA. In Texas Workers’ Compensation Commission v. Garcia we explained the difference between a facial challenge and an “as applied” challenge.
Ill
Power Choice asserts that transition charges constitute a taking of money from consumers of electricity that is uncompensated because the charges are unrelated to the current provision of electric service in a competitive market. Power Choice contends that for customers of an incumbent utility, the transition charges bear no relation to the current market value of the electricity received, and that customers of a new provider will receive nothing at all in return for their payment of transition charges. We are unpersuaded that transition charges are a taking without adequate compensation in violation of Article I, Section 17 of our Texas Constitution.
A
The first question that we must resolve is what analytical framework applies in determining whether charges by a utility amount to an unconstitutional taking. Historically, states have regulated utilities and utility rates under the police power. The United States Supreme Court has said that “the regulation of utilities is one of the most important of the functions traditionally associated with the police power of the States.”
The reasoning in decisions of the United States Supreme Court that have arisen in the context of complaints by consumers that a utility’s rates are unjust and unreasonable is instructive.
In Federal Power Commission v. Hope Natural Gas Co.,
Accordingly, there can be no constitutional objection if the [Federal Power] Commission, in its calculation of rates, takes fully into account the various interests which Congress has required it to reconcile. We do not suggest that maximum rates computed for a group or geographical area can never be confiscatory; we hold only that any such rates,*243 determined in conformity with the Natural Gas Act, and intended to “balanc[e] ... the investor and the consumer interests,” are constitutionally permissible.45
Rates may be substantially higher than the lowest reasonable rate that is not confiscatory to a utility and yet not be excessive when charged to a consumer.
Recently, the Supreme Court of New Hampshire utilized the “zone of reasonableness” principles when it was called upon to review legislation that deregulated certain aspects of that state’s electric power industry.
Armed with these basic principles, we consider Power Choice’s arguments.
B
Power Choice contends that consumers should not be burdened with obligations that an incumbent utility incurred in the past to provide service or build facilities because those costs are unrelated to the current provision of electric sendee. The first question that we must decide, then, is whether, “during the transition to and in the establishment of a fully competitive electric power industry,”
We have held that it is not unjust or unreasonable to permit a utility to recover past costs over a future period through rates.
The transition charges that are established under the 1999 amendments to the PURA are essentially a conversion from one form of rate recovery to another. Through transition bonds, the costs that a utility would otherwise have had the opportunity to recover in rates are to be refinanced. At least one court has characterized transition charges like those at issue here as “nothing more than a different manifestation of the previously regulated rates.”
Had Pennsylvania continued the system in effect prior to the Competition Act, PUC would have allowed PECO to recover these costs through the rates it charged for its “bundled” services without labeling them transition charges. The stranded-cost provisions are simply a novel way to accommodate the need for recovery of these costs consistent with traditional state regulation.57
Spreading the recovery of costs incurred in the past over a period of years is not a concept unique to regulation of utilities in Texas. Recently, the United States Court of Appeals for the District of Columbia Circuit had occasion to review orders of the Federal Energy Regulatory Commission that partially deregulated the interstate electric industry and provided for recovery of stranded costs, including regulatory assets.
Implicit, if not explicit, in these fundamental ratemaking principles is the recognition that even though a particular consumer does not derive a direct benefit from the use of particular assets, that does not render rates that include costs associated with those assets unjust or unreasonable. We considered a similar proposition in Cities for Fair Utility Rates v. Public Utility Commission,
While it is not fair to charge present ratepayers with the cost of future service, neither is it fair to burden future ratepayers with unnecessarily high acquisition costs because a utility was discouraged from making prudent long-term plans. PHFU expenses are used and useful because they are a necessary part of planned investments. Most states include PHFU in rate base in some circumstances.65
We accordingly held that a utility could include approximately $93 million of costs incurred in connection with a generating plant that it planned to build in ten years.
Under the PURA, a utility’s recovery of regulatory assets through rates has, by definition, been determined in previous rate cases to be within the zone of reasonableness as between a utility and the customers who would pay its rates. And by definition, stranded costs were incurred in providing electric power service. Under the 1999 amendments to the PURA, a utility may recover only “net, verifiable, nonmitigable stranded costs incurred in purchasing power and providing electric generation service.”
Were it otherwise, no residential rates could pass constitutional muster. Residential customers continually move in and out of a utility’s service area. Rates are not adjusted so that each consumer pays only for costs incurred by the utility when that consumer actually lived in the area and was served by the utility. It would be utterly impracticable to set and then continually adjust rates on such a basis.
Another ground on which Power Choice bases it takings argument is that unless a utility has the constitutional right to recover stranded costs and regulatory assets, it would be unconstitutional for the Legislature to allow recovery of those costs and assets. We need not and do not decide whether an incumbent utility’s constitutional rights would be abridged if it were not permitted to recover stranded costs. As we have seen from some of the decisions discussed above, a regulator may lawfully allow a utility to recover certain costs even though a denial of recovery of those costs would not amount to confiscation from a utility.
In sum, a regulatory authority, and certainly the Legislature, may conclude that it is appropriate to spread recovery of a utility’s costs over time. The fact that a particular consumer does not derive a direct benefit from the past use of particular
C
Power Choice argues that the PURA’s securitization provisions result in a taking as to new customers moving into a utility’s service area and a utility’s existing customers, at least if these new and existing customers choose to purchase power from a new supplier. Those consumers, Power Choice contends, receive no benefit at all from a utility’s past investments or costs. This is an as-applied constitutional challenge, rather than a facial challenge.
For many of the reasons that we discussed in section IIIB above, we reject Power Choice’s argument that transition charges are confiscatory as to new and existing consumers who will buy electricity from suppliers other than CPL. If the Legislature had not enacted the 1999 amendments to the PURA, many new and existing consumers who will now want to buy power from a new supplier would have been served by an incumbent utility. As explained above, many customers would not have had the option under the previous regulatory regime to seek another supplier because there would have been no other supplier. Those consumers would have been required to pay rates that allowed the incumbent utility to recover costs associated with obligations incurred in the past, even though those particular consumers may not have been customers of the utility when it incurred the costs or obligations.
It is not unjust or unreasonable to require consumers for whose benefit an electric power generation infrastructure was constructed to share in some of the costs of that infrastructure, even though they may not directly benefit from it under the new regulatory scheme. Under the regulatory scheme in which regulatory assets were created and stranded costs were incurred, an electric utility had a public-service obligation to render service to all those in its service area at regulated rates.
Regulatory assets were created and stranded costs were incurred as part of prudent planning not only for customers the utility was then serving but for anticipated future customers as well. It is not unjust or unreasonable, and therefore it is not confiscatory, to charge rates to present and future retail consumers in a utility’s service area that will allow a utility to recoup regulatory assets and stranded costs associated with these outlays of capital. This is so even if the consumers do
Although it is not critical to our takings analysis, we note that retail customers who otherwise would have been served by an existing utility but who will choose another provider in the new era of competition may have their electricity generated by facilities built by the existing utility in their service area. Under the PURA, an existing utility must sell at auction at least fifteen percent of its generation capacity.
In the interim between September 1, 1999 and January 1, 2002, an electric utility’s rates are frozen at the September 1, 1999 level, with certain exceptions.
Residential and small commercial customers will also have the right to continue to purchase electricity from an incumbent utility or its affiliated retail electric provider at a frozen “price to beat” for a period of time up to January 1, 2007.
The foregoing scheme indicates that the Legislature intended that the overall structure and impact of the securitization provisions and the move to partial deregulation would benefit most consumers. There are tangible services that are likely to be provided to many existing customers as well as many new consumers who enter an incumbent utility’s service area after its regulatory assets were created and its stranded costs were incurred, particularly if those consumers would have been served by the incumbent utility had the former scheme of regulation remained in place. The Legislature’s scheme does not result in an unconstitutional taking as to these
We do not decide whether the securitization provisions of the PURA would result in an unconstitutional taking as applied to a new consumer if that consumer could demonstrate that its electric service would not have been provided by an incumbent utility if regulation had been continued and that no part of the electric service that the consumer has or will receive is generated by an incumbent, its affiliate or a purchaser of its assets, or is transmitted or distributed over or through facilities that were owned or constructed by an incumbent utility or its affiliate. A challenge mounted on that basis would be a particularized “as applied” challenge that Power Choice does not make in this case. For the reasons considered above, we conclude that the district court did not err in rejecting Power Choice’s constitutional challenges to transition charges.
IV
Power Choice contends that the nonbypassable transition charges contemplated by the PURA are a tax, not a rate or a regulatory fee. With limited exceptions, transition charges will be paid by all electric power consumers in CPL’s geographic service area regardless of whether those consumers buy electricity from CPL or some other supplier.
A
In determining whether transition charges are a tax rather than a utility rate, it is important to consider who is to pay those charges under the PURA’s regulatory scheme and what the charges represent. When the Legislature implemented the securitization provisions of the PURA, it made a conscious decision about who is to bear certain costs associated with the transition from regulated electric retail rates to market-based retail rates. The Legislature determined that with limited exceptions, certain costs of the transition should be borne by all consumers of electricity in an incumbent utility’s service area rather than by that utility’s shareholders. The Legislature’s decision was consistent with how those same costs would have been allocated if the former regulatory scheme had been left in place. As we discussed above, incumbent utilities had an obligation to prudently plan to serve future consumers. Consumers of electricity for the most part would have purchased power from an incumbent utility and would have paid through rates, not taxes, costs that the incumbent utility incurred in the past
Many of the costs that are to be securi-tized and recovered through transition charges are costs that the Commission determined in prior rate cases should be recovered directly by a utility through its rates because those costs were prudently incurred in connection with providing electric service.
B
In arguing that transition charges cannot be lawful rates and therefore must be considered a tax, Power Choice asserts that transition charges are not “related to any service, product, or commodity” and thus do not satisfy the “used and useful” test. Power Choice also asserts that transition charges amount to retroactive rate-making in violation of the filed rate doctrine.
In support of its “used and useful” argument, Power Choice cites this Court’s decision in Cities for Fair Utility Rates v. Public Utility Commission.
Stranded costs include so-called bricks and mortar capital expenditures for generating facilities.
Power Choice relies on our decision in State v. Public Utility Commission
Moreover, the filed rate doctrine does not prohibit a regulatory authority from finding that an existing rate is unreasonable and determining the just and reasonable rate to be charged thereafter.
C
Power Choice cites this Court’s decision in Conlen Grain,
In Conlen Grain, agricultural producers voted under the Texas Commodity Referendum Act
[The assessments on producers] are levied periodically to provide a fairly constant source of revenue that is expended by an agency of the state as it considers proper for the support of programs calculated to increase the production and use of particular agricultural commodities. These programs doubtless promote the economic welfare of many who are engaged in producing the commodities, but the assessment paid by any particular person is not necessarily related to the benefits that will be received by that person through the Board’s expenditure of the money he paid. The levy is not a special assessment.102
We then said that because the power of the state was used to deprive commodity producers of money or at least the use of money until the assessment was refunded, and because the primary purpose of the assessment was to raise revenues, it was a tax.
The transition charges imposed by the PURA are different from the assessments in Conlen Grain in at least one important respect. Transition charges are not used by an agency of the state. Transition charges are used by an electric utility to retire debt or equity associated with its stranded costs and regulatory assets related to the generation of electric power. Transition charges are analogous to an allocation of costs between intrastate and interstate telephone service providers that was held not to be a tax by the United States Court of Appeals for the District of Columbia Circuit in Rural Telephone Coalition.
It is beyond dispute that in the prior, regulated environment, the Legislature had the authority to require retail electric customers to pay the costs represented by a utility’s regulatory assets through utility rates. That authority still exists even though the Legislature has decided to partially deregulate the electric power industry. The fact that the Legislature has chosen to continue to require consumers to pay the costs represented by a utility’s regulatory assets under a different mechanism than it did under the prior regulated regime does not transform what were undeniably utility rates into taxes. The secu-ritization provisions of the PURA do not constitute a tax and do not violate Article VIII, Section 3 of the Texas Constitution.
Power Choice’s alternative argument is that if transition charges are truly in the public interest, then the general public, not just energy consumers in particular incumbent utilities’ service areas, should pay those costs in the form of a tax. This would, of course, breathe life into another of Power Choice’s constitutional challenges, which is that tax dollars cannot be paid to private corporations because to do so would violate Article III, Section 51 of the Texas Constitution. (We consider that constitutional challenge in the next section.) But the Legislature has the unquestioned police power, as we have seen, to regulate utility rates.
V
Power Choice contends that transition charges are a grant of public money to private corporations in violation of Article III, Section 51 of the Texas Constitution.
This Court held in State v. City of Austin that the purpose of Article III, Section 51 and of Article XVI, Section 6 of the Texas Constitution “is to prevent the application of public funds to private purposes; in other words, to prevent the gratuitous grant of such funds to any individual or corporation whatsoever.”
For the same reason, this Court’s decision in Road District No. ⅛, Shelby County v. Allred is inapposite.
For the reasons considered above, we conclude that Power Choice’s appeal is without merit. We now turn to the issues raised in the appeal by numerous cities served by CPL, the Office of Public Utility Counsel, Texas Industrial Energy Consumers, and the Texas Retailers Association.
VI
The financing order at issue allows CPL to securitize regulatory assets that include what are known as “SFAS 109 assets.” “SFAS 109” refers to Statement of Financial Accounting Standard 109. An SFAS 109 regulatory asset is essentially a receivable from a utility’s customers for the future payment of federal income taxes. Of the total amount of $763,734,489 of regulatory assets that the financing order at issue in this case allows to be securi-tized, SFAS 109 assets account for $139,182,000.
The Cities contend that it was improper for the Commission to include SFAS 109 assets in the amount to be securitized because these regulatory assets earn no return and have no carrying costs. The Cities argue that the PURA requires that each regulatory asset be analyzed on a stand-alone basis to determine whether securitization will lower that asset’s carrying costs “relative to the costs that would be incurred using conventional utility financing methods.”
Resolution of the Cities’ challenge to this aspect of the financing order lies in the provisions of the PURA. Those provisions make it clear that, contrary to the Cities’ position, the Commission is not permitted to decide what types or categories of regulatory assets may be securitized. The PURA says that all regulatory assets are to be securitized on application of a utility, subject to the requirement that “the total amount of revenues to be collected under the financing order” meets the requirements of sections 39.301 and 39.303(a).
The PURA provides that an electric utility may “securitize 100 percent of its regulatory assets as defined by section 39.302.”
“Regulatory assets” means the generation-related portion of the Texas jurisdictional portion of the amount reported by the electric utility in its 1998 annual report on Securities and Exchange Commission Form 10-K as regulatory assets and liabilities, offset by the applicable portion of generation-related investment tax credits permitted under the Internal Revenue Code of 1986.116
Each utility’s “regulatory assets” were fixed and ascertainable from 1998 Form 10-K’s at the time that the securitization provisions were enacted in the 1999 amendments to the PURA.
Sections 39.302(4), 39.302(7), and 39.303(a) of the PURA reiterate that “100 percent of an electric utility’s regulatory assets” are “qualified costs” that can be recovered through transition charges imposed under a financing order upon application by a utility, subject to the requirements of sections 39.301 and 39.303(a). The PURA does not give the Commission discretion to single out certain types of regulatory assets from “100 percent of an electric utility’s regulatory assets” and declare that those particular types of regulatory assets are not “qualified costs.”
The Commission did not err in allowing CPL to securitize SFAS 109 assets.
VII
The Cities contend that the Commission erred by fading to offset the regulatory assets that CPL sought to securitize with all of CPL’s investment tax credits. The PURA’s definition of “regulatory assets” that may be securitized provides that regulatory assets are to be “offset by the applicable portion of generation-related investment tax credits permitted under the Internal Revenue Code of 1986.”
The operative qualifier in section 39.302(5)’s offset provision is “applicable.” Section 39.302(5) does not require that CPL offset all its tax credits against its regulatory assets. It only requires an offset of applicable credits. Witnesses for CPL and the Commission testified that none of the investment tax credits that the Cities identified were applicable to the regulatory assets in question. Moreover, the Cities’ expert witness conceded that if the offset the Cities sought were required by the Commission, a normalization violation might occur, which would obligate CPL to pay to the IRS all its current tax credits, not just those associated with its investments in transmission and distribution facilities.
The financing order’s treatment of investment tax credits “conforms to the [PURA]” and is “within the authority of the commission” under chapter 39 of the PURA.
VIII
The Cities assert that because the Commission used CPL’s 1998 SEC Form 10-K to identify the amount of certain regulatory assets to be securitized, rather than the balance of those assets as of December 31, 2001, CPL will over-recover. This occurs, the Cities contend, because CPL’s regulatory assets are in its existing rate base, and its rates provide for recovery of and a return on those assets. The actual balance of the regulatory assets will decline, the Cities contend, from the balance shown in CPL’s 1998 10-K because rate recovery will reduce that balance
Once again, the express provisions of the PURA are dispositive. Section 39.302(5) defines “regulatory assets” as the amount reported in CPL’s 1998 SEC Form 10 K.
We note that the Commission and CPL contend that certain sections of the financing order and provisions of the PURA should mitigate or eliminate any over-recovery by CPL. They point to the final true-up provision of the financing order and sections 39.254 and 39.257 through 39.261 of the PURA. We need not decide whether any of those provisions will actually eliminate or ameliorate any over-recovery. That question may be raised in future proceedings. The financing order at issue in this case complied with section 39.302(5) in using the 1998 Form 10-K amount of regulatory assets. The Cities do not attack the validity of section 39.302(5). They say only that its express directive should not have been applied. Because the PURA does not authorize the Commission to use the balance as of December 31, 2001, in determining the amount of regulatory assets that may be securitized, our inquiry in this case is at an end.
IX
Another point of dispute is how section 39.253 of the PURA, which allocates transition charges among classes of customers, should be interpreted.
The allocation of stranded costs, including regulatory assets, has two basic components. One is determined by applying the same methodology used to allocate costs of the underlying assets in the electric utility’s most recent commission order addressing rate design.
CPL’s last rate design case was in 1997. In allocating transition charges among classes of CPL’s customers, the Commission applied the methodology used in that rate case to the power consumption data developed in that same case. This resulted in allocation factors, expressed as percentages, for each class of customers. The Commission used those allocation factors to allocate transition costs.
Texas Industrial Energy Consumers is a voluntary association of companies that operates small and large industrial facilities in CPL’s service area. It contends that in initially determining the allocation factor for each customer class, the Commission should have adjusted the historical data that reflected usage by the industrial classes to account for industrial customers that have since left or will leave CPL’s
To the extent a customer’s load is served by a qualifying cogeneration facility before a certain date, or by an on-site power facility that has a capacity of ten megawatts or less, that customer is exempt from paying transition charges under section 39.262(k).
TIEC first asserts that this is required by section 39.253(f), which says that “[e]xcept as provided by Section 39.262(k), no customer or customer class may avoid the obligation to pay the amount of stranded costs allocated to that customer class.”
Moreover, to give effect to TIEC’s position, we would have to construe section 39.253 as directing the Commission to establish allocation factors based on data obtained at the end of each year over the life of the transition bonds rather than the data used in the utility’s most recent rate design case. As noted above, section 39.253 says that one component of how transition costs are allocated among all other customer classes is “the methodology used to allocate the costs of the underlying assets in the electric utility’s most recent commission order addressing rate design.”
In light of the Commission’s and our interpretation of section 39.253(c)-(i), the Commission did not err in declining to use customer load data other than the data in CPL’s last rate case and the energy consumption data as of May 1, 1999, adjusted for normal weather conditions, in determining how transition charges are to be allocated among CPL’s customer classes.
X
Another disagreement is how section 39.253 allocates transition costs to non-firm industrial customers. A utility may interrupt service to non-firm customers for specified reasons, typically during periods of high demand from other customers on that utility’s system. Nucor Steel, one of CPL’s non-firm industrial customers, and TIEC insist that the literal terms of the PURA require that after the amount to be allocated to residential customers has been determined, section 39.253 directs that that amount is to be subtracted from the total amount of transition charges before an allocation is made to non-firm industrial customers. The Commission did not make that subtraction. It based the percentage of transition costs to be borne by non-firm industrial customers on the entire amount of the transition charges.
Section 39.253 is complex and, we conclude, unclear in this regard. It says:
(c) The allocation to the residential class shall be determined by allocating to all customer classes 50 percent of the stranded costs in accordance with the methodology used to allocate the costs of the underlying assets in the electric utility’s most recent commission order addressing rate design and allocating the remainder of the stranded costs on the basis of the energy consumption of the classes.
(d) After the allocation to the residential class required by Subsection (c) has been calculated, the remaining stranded costs shall be allocated to the remaining customer classes in accordance with the methodology used to allocate the costs of the underlying assets in the electric utility’s most recent commission order addressing rate design. Non-firm industrial customers shall be allocated stranded costs equal to 150 percent of the amount allocated to that class.
(e) After the allocation to the residential class required by Subsection (c) and the allocation to the nonfirm industrial class required by Subsection (d) have been calculated, the remaining stranded*260 costs shall be allocated to the remaining customer classes in accordance with the methodology used to allocate the costs of the underlying assets in the electric utility’s most recent commission order addressing rate design.140
There is tension between paragraph (c) on the one hand, and paragraphs (d) and (e) on the other, partly because of the use of the word “remaining” in the latter two paragraphs. There is also ambiguity because paragraph (c) seems to contemplate an allocation of all costs to all classes based fifty percent on demand allocation factors and fifty percent on energy consumption. . Paragraph (c) says that fifty percent of stranded costs (which also means transition charges for regulatory assets
TIEC offers an example to demonstrate the difference between its application of section 39.253 and the Commission’s. In that example, the transition charges total $100. Residential customers are allocated forty percent of those costs. The example further assumes that based on the last rate case, the non-firm industrial customers’ demand allocation factor is ten percent and the demand allocation factor for all other classes totals fifty percent. Because paragraph (d) requires non-firm industrial customers to bear 150 percent of the amount allocated to that class, the demand allocation factor for that class becomes fifteen percent. Both TIEC’s and the Commission’s application of section 39.253 to this example allocates $40 of the $100 of transition charges to the residential class. TIEC and the Commission diverge on what happens next.
TIEC would subtract the residential class’s $40 share of costs from the $100 total, and then apply the fifteen percent demand allocation for non-firm industrial customers to the remaining $60 of costs. That results in an allocation of $9 to that class. TIEC would then spread the remaining costs of $51 among the firm nonresidential classes based on their proportionate demand allocation factors, rather than applying the demand allocation factors which total fifty percent for those classes. TIEC refers to this latter step as “grossing up” the allocation factors for the firm non-residential classes, which is not in conformity with the literal terms of paragraph (e). TIEC argues that “grossing up” the firm non-residential class’s demand allocation factor is nonetheless necessary under its interpretation of section 39.253 because otherwise, there would be an undercollection of transition charges.
Using the Commission’s application of section 39.253, the fifteen percent demand allocation factor for the non-firm industrial customers is applied to the total $100 in transition costs. The non-firm industrial customers would pay $15, rather than $9 in TIEC’s example. The Commission’s application of section 39.253 then allocates the remaining $45 of costs among the firm non-residential classes. As Nucor Steel
TIEC’s construction of section 39.253 results in an undercollection of transition charges. The Commission’s construction, if carried to its logical conclusion, would result in an overcollection. No one suggests a construction that allows recovery of 100 percent of the transition charges, but no more. As we explained above and as we explain today in TXU,
XI
Finally, the Cities argue that the Commission denied them due process by: (1) not allowing adequate time to prepare for the contested case hearing on the financing order; (2) unduly restricting the Cities’ opportunity to cross-examine witnesses; and (3) issuing a financing order that adopts a non-unanimous stipulation without first holding a separate hearing on that stipulation or making findings that it is reasonable, supported by the evidence, and in compliance with the PURA. We conclude that the Cities were not denied due process in this case.
A
The PURA contemplates that adoption of a financing order will be accomplished on an accelerated procedural schedule. The Legislature has directed that a financing order shall be issued within ninety days after a utility files a request for a financing order.
CPL filed its request for a financing order with the Commission on October 18, 1999. The Cities were among eighteen parties that intervened. Consistent with the PURA’s expedited procedures, the Commission established a briefing and hearing schedule. The Cities argue that this schedule allowed insufficient time for discovery. They were particularly aggrieved, they say, by the hearing schedule because they were afforded only “39 minutes of cross examination [of 36 witnesses] reduced by any time presenting an opening statement.” Accordingly, the Cities argue, their due process rights were violated in the first instance because they did not have a reasonable amount of time to prepare, citing Lowe v. City of Arlington,
This Court has held that in administrative proceedings, due process requires that parties be accorded a full and fair hearing on disputed fact issues.
While we recognize that an administrative agency is entitled to considerable procedural flexibility, the Commission has failed to offer an adequate explanation of why, in a case of such public importance, it so severely restricted the time for cross-examination of witnesses. Even within the confines of the ninety-day statutory deadline for concluding proceedings when a request for a financing order has been filed, the Commission could have devoted more time in the schedule to the actual hearing. Furthermore, CPL filed an amended application after the evidentiary hearing had concluded that gave the Commission an additional seventy-one days beyond the original ninety days it would otherwise have had to issue an order. Yet the Commission did not allow additional hearing time. We do not condone the truncated hearing schedule that was established in this case. Nevertheless, based on the record before us, the Cities have failed to demonstrate any harm flowing from the Commission’s actions.
Before the hearing on the merits, the parties joined issue by submitting written discovery and pre-filing direct testimony. CPL filed its direct testimony with its request for a financing order, and all of the intervenors were able to respond to this testimony. At the hearing, witnesses were grouped into panels by topic, and counsel shared or traded time allotted to allied counsel for the examination and cross-examination of witnesses. After the hearing, all parties submitted an initial brief and a reply brief. With only one exception, the Cities do not identify any instance in which, the Commission’s procedural schedule pre
In view of the entire record in this case, we are persuaded that the Cities were accorded due process, particularly since the dispositive issues in these appeals are legal ones involving constitutional provisions and statutory construction. The Cities have failed to identify any material disputed fact issue had they been given more time to prepare that might have been resolved differentlyfor the hearing, present evidence, or cross-examine witnesses. In spite of the shortness of the hearing and the limited time for cross-examination, the Cities have not shown that substantial rights were violated by the procedures afforded.
B
The Cities additionally contend that their due process rights were violated when the Commission ignored its own rule by adopting the non-unanimous stipulation without conducting an additional hearing on that stipulation. The Cities point to section 22.206 of the Commission’s rules.
We have recognized the importance of requiring an administrative agency to consider a non-unanimous stipulation on its merits.
Although the Commission did not provide the non-settling parties an evidentiary hearing following the non-unanimous stipulation, we conclude that the Cities have failed to show that the Commission’s procedure denied them due process. The Commission adopted the financing order incorporating in part the non-unanimous stipulation only after extensive briefing, open meetings, and comments on the proposed order. The parties continued to
Moreover, we have previously held that failure to follow procedural requirements of statutes or rules is not reversible error without a showing of harm.
.Former Tex.Rev.Civ. Stat. Ann. art. 1446c, Act of June 2, 1975, 64th Leg., R.S., ch. 721, § 1, 1975 Tex. Gen. Laws 2327 (.current version at Tex. Util.Code § 11.001, et seq.).
.Former Tex.Rev.Civ. Stat. Ann. art. 1446c § 2.
.Id.
. Tex. Util.Code § 31.001 (b), (c).
. Id. § 31.001(a).
. Id. § 39.001(a).
. Id.
. Id. § 39.051.
. M§ 39.051(b).
. Id. § 39.051(c).
. Id. § 39.001(a).
.Id. § 39.251(7).
. Id. §§ 39.201(i), 39.252, 39.302(7), 39.306.
. Id. § 39.252.
. Id. §§ 39.301, 39.302(4),(5), (7).
. Id. § 39.302(5).
. Id. §§ 39.201(f)-©, 39.252.
. Id. §§ 39.201 (i), (j), 39.253.
. Id. § 39.262(k).
. Id. §§ 39.301, 39.302, 39.303.
. Id. § 39.301.
. Id.
. Id. § 39.302(2).
. Id. § 39.302(4).
. Id. §§ 39.302(6), 39.304.
. Id. §§ 39.302(7), 39.303, 39.306.
. Id. § 39.262.
. Id. § 39.307.
. 893 S.W.2dat518n. 16.
. Id. (citing Texas Ass’n of Bus. v. Texas Air Control Bd„ 852 S.W.2d 440, 450 (Tex. 1993) and Nelson v. Krusen, 678 S.W.2d 918, 922 (Tex. 1984) (holding two-year medical limitations statute unconstitutional as applied to a plaintiff who could not discover the injury during the two-year period)).
. Barshop v. Medina County Underground Water Conservation Dist., 925 S.W.2d 618, 627 (Tex. 1996) (citing Texas Workers' Comp. Comm’n v. Garcia, 893 S.W.2d 504, 518 (Tex. 1995)); see also Appraisal Review Bd. of Galveston County v. Tex-Air Helicopters, Inc., 970 S.W.2d 530, 534 (Tex. 1998).
. The takings clause in the Texas Constitution provides:
No person’s property shall be taken, damaged or destroyed for or applied to public use without adequate compensation being made, unless by the consent of such person; and, when taken, except for the use of the State, such compensation shall be first made, or secured by a deposit of money; and no irrevocable or uncontrollable grant of special privileges or immunities, shall be made; but all privileges and franchises granted by the Legislature, or created under its authority shall be subject to the control thereof. Tex. Const, art. I, § 17.
. Arkansas Elec. Coop. Corp. v. Arkansas Pub. Serv. Comm’n, 461 U.S. 375, 377, 103 S.Ct. 1905, 76 L.Ed.2d 1 (1983) (citing Munn v. Illinois, 94 U.S. 113, 24 L.Ed. 77 (1876)).
. St. Joseph Stock Yards Co. v. United States, 298 U.S. 38, 51, 56 S.Ct. 720, 80 L.Ed. 1033 (1936) (explaining constitutional limits on a legislature’s ratemaking authority).
. Los Angeles Gas & Electric Corp. v. R.R. Comm’n of California, 289 U.S. 287, 304, 53 S.Ct. 637, 77 L.Ed. 1180 (1933).
. Id. at 305, 53 S.Ct. 637; see also St. Joseph Stock Yards, 298 U.S. at 53, 56 S.Ct. 720.
. Mayhew v. Town of Sunnyvale, 964 S.W.2d 922, 933 (Tex. 1998).
. 155 Tex. 502, 289 S.W.2d 559, 563 (1956).
. 320 U.S. 591, 594, 64 S.Ct. 281, 88 L.Ed. 333 (1944).
. Id. at 601, 64 S.Ct. 281 (quoting Federal Power Comm’n v. Natural Gas Pipeline Co., 315 U.S. 575, 582, 62 S.Ct. 736, 86 L.Ed. 1037 (1942)).
. 390 U.S. 747, 770, 88 S.Ct. 1344, 20 L.Ed.2d 312 (1968).
. 390 U.S. at 770, 88 S.Ct. 1344 (citing Hope Natural Gas, 320 U.S. at 603, 64 S.Ct. 281).
. Banton v. Belt Line Ry. Corp., 268 U.S. 413, 422-23, 45 S.Ct. 534, 69 L.Ed. 1020 (1925).
. Denver Union Stock Yard Co. v. United States, 304 U.S. 470, 483, 58 S.Ct. 990, 82 L.Ed. 1469 (1938).
. Campaign for Ratepayers Rights, 766 A.2d 702, 706 (N.H. 2001).
. Id. at 706 (quoting Pub. Serv. Co. of N.H., 130 N.H. 265, 539 A.2d 263, 268 (1988)).
. Tex. Util.Code § 39.001(a).
. Id. § 39.001(b)(2).
. State v. Pub. Util. Comm’n, 883 S.W.2d 190, 197-200 (Tex. 1994).
. Tex. Pub. Util. Comm'n, Application of Central Power & Light Company for Authority to Change Rates, Docket Nos. 8646, 9141, 9595 & 9561, 16 Tex. P.U.C. Bull. 1876, 1878, 1896 (Oct. 19, 1990); Tex. Pub. Util. Comm’n, Application of Central Power & Light Company for Rate Changes and Inquiiy into the Company's Prudence with Respect to South Texas Project Unit 2, Docket No. 9561, 17 Tex P.U.C. Bull. 157, 357, 368 (Dec. 19, 1990).
. State v. Pub. Util. Comm’n, 883 S.W.2d at 193-96.
. Indianapolis Power & Light Co. v. Pennsylvania Pub. Util. Comm’n, 711 A.2d 1071, 1079 (Pa.Commw.Ct. 1998); cert, denied, 526 U.S. 1005, 119 S.Cl. 1143, 143 L.Ed.2d 210 (1999).
. Id.
. Transmission Access Policy Study Group v. Federal Energy Regulatory Comm’n, 225 F.3d 667 (D.C.Cir. 2000).
. Id. at 699.
. Office of Consumer Counsel v. Dep’t of Pub. Util. Control, 252 Conn. 115, 742 A.2d 1257, 1263 (2000).
. Campaign for Ratepayers Rights, 766 A.2d at 706.
. Id. (quoting Transmission Access Policy Study Group, 225 F.3d at 708).
. 924 S.W.2d 933 (Tex. 1996).
. Mat 937.
. Id. at 941.
. See Former Xex.Rev.Civ. Stat. Ann. art. 1446c §§ 37, 58; Former Tex.Rev.Civ. Stat. Ann. art. 1119, Act of Apr. 2, 1937, 45th Leg., R.S., ch. 144, § 1, 1937 Tex. Gen. Laws 274, 274—75 (current version at Tex. Util.Code §§ 11.001, et seq.); Former Tex.Rev.Civ. Stat. Ann. art. 1175(12), amended by Act of May 10, 1999, 76th Leg., R.S., ch. 227, § 27, 1999 Tex. Gen. Laws 721, 1055 (current version at Tex.Rev.Civ. Stat. Ann. art. 1175(1)).
. Indianapolis Power & Light Co., 711 A.2d at 1074.
. Id.
. 571 S.W.2d 503, 516 (Tex. 1978).
. Tex. Util.Code § 39.252(a) (emphasis added).
. Permian Basin, 390 U.S. at 770, 88 S.Ct. 1344 (holding that "any rate selected by the Commission from the broad zone of reasonableness permitted by the Act cannot properly be attacked as confiscatory”).
. Denver Union Stock Yard Co., 304 U.S. at 483, 58 S.Ct. 990.
. Tex Util.Code § 39.153(a).
. Id. § 39.153(b).
. Id. § 39.052.
.Id. § 39.202(a).
.Id.
. Id. §§ 39.201(i), (j), 39.253.
. The Texas Constitution provides under the heading of "General laws; public purposes” that: "Taxes shall be levied and collected by general laws and for public purposes only.” Tex. Const, art. VIII, § 3.
. See Tex. Util.Code §§ 39.259(c) (providing that for purposes of determining stranded costs "items in invested capital [other than those in (a) and (b) ] shall be as approved in the electric utility's last rate proceeding before the commission”), 39.302(5) (defining regulatory assets).
. 924 S.W.2d 933 (Tex. 1996).
. Id. at 935.
. Tex. Util.Code § 39.251(3), (7).
. See State v. Pub. Util. Comm'n, 883 S.W.2d at 193-96, 202; Transmission Access Policy Study Group, 225 F.3d at 699; Office of Consumer Counsel, 742 A.2d at 1263.
. Tex Util.Code § 39.302(5).
. Campaign for Ratepayers Rights, 766 A.2d at 706.
. Id.
. 838 F.2d 1307 (D.C.Cir. 1988).
. Id. at 1316 (citing Jersey Cent. Power & Light Co. v. PERC, 810 F.2d 1168, 1175 (D.C.Cir. 1987)).
. 453 U.S. 571, 578, 101 S.Ct. 2925, 69 L.Ed.2d 856 (1981).
. Id.
. Tex. UtiiXode § 39.001(a), (b)(2).
. Arkansas Louisiana Gas Co., 453 U.S. at 578, 101 S.Ct. 2925.
. Id.
. Conlen Grain and Mercantile, Inc. v. Texas Grain Sorghum Producers Bd., 519 S.W.2d 620 (Tex. 1975).
. Former Tex.Rev.Civ. Stat. Ann. art. 55c, Act of May 25, 1967, 60th Leg., R.S., ch. 462, 1967 Tex. Gen. Laws 1052, repealed by Act of May 22, 1981, 67th Leg., R.S., ch. 388, § 4(1), 1981 Tex. Gen. Laws 1012, 1487 (current version at Tex. Agric. Code §§ 41.001, et seq.).
. Conlen Grain, 519 S.W.2d at 624.
. Id. at 623.
. Id.
. 838 F.2d at 1314.
. Id. at 1310-11.
. Id. at 1314.
. Arkansas Elec. Coop. Corp., 461 U.S. at 377, 103 S.Ct. 1905 (citing Munn v. Illinois, 94 U.S. 113, 24 L.Ed. 77 (1876)).
. The Texas Constitution provides:
§ 51. Grants of public money prohibited; exceptions.
Sec. 51. The Legislature shall have no power to make any grant or authorize the making of any grant of public moneys to any individual, association of individuals, municipal or other corporations whatsoever; provided that the provisions of this Section shall not be construed so as to prevent the grant of aid in cases of public calamity. Tex. Const, art. Ill, § 51.
. 160 Tex. 348, 331 S.W.2d 737, 742 (1960) (citing Byrd v. City of Dallas, 118 Tex. 28, 6 S.W.2d 738, 740 (1928)).
. City of Austin, 331 S.W.2d at 740.
. 123 Tex. 77, 68 S.W.2d 164 (1934).
. Id. at 169-70
. Tex. Util.Code § 39.301.
. Id. §§ 39.201(i)(l), 39.301, 39.303(a).
. Id. § 39.201(0(1).
. Id. § 39.302(5).
. 17 C.F.R. § 249.310 (providing that Securities and Exchange Commission Form 10 K must be filed within 90 days after the end of the fiscal year).
. Tex Util.Code § 39.262(f).
. Id. § 39.302(5).
. Id. § 39.302(4).
. Id. § 39.303(a).
. 51 S.W.3d 275 (Tex. 2001).
. Tex. UtiiXode § 39.301 (directing that "[t]he amount securitized may not exceed the present value of the revenue requirement over the life of the proposed transition bond asso-dated with the regulatory assets or stranded costs sought to be securitized”).
. Id. § 39.302(5).
. Id. § 39.303(f).
. Id. § 39.302(5).
. Id §§ 39.201(0(1), 39.301, 39.303(a)
. See id. §§ 39.253; 39.303(c) (directing that transition charges are to be "allocated among customers in the same manner as competition transition charges under Section 39.201”); 39.20KJ) (directing that "[a]ny competition transition charge shall be allocated among retail customer classes according to Section 39.253”).
. Id. § 39.253(c)-(e).
. Id. § 39.253(c).
. Id. § 39.253(g).
. Section 39.262(k) provides:
(k) Notwithstanding Section 39.252, to the extent that a customer’s actual load has been lawfully served by a fully operational qualifying facility before September 1, 2001, or by an on-site power production facility with a rated capacity of 10 megawatts or less, any charge for recovery of stranded costs under this section or Sub-chapter G assessed on that customer after the facility becomes fully operational shall be included only in those tariffs or charges associated with the services actually provided by the transmission and distribution utility, if any, to the customer after the facility became fully operational and may not include any costs associated with the service provided to the customer by the electric utility or its affiliated transmission and distribution utility under their tariffs before the operation of that qualifying facility. To qualify under this subsection, a qualifying facility must have made substantially complete filings on or before December 31, 1999, for all necessary site-specific environmental permits under the rules of the Texas Natural Resource Conservation Commission in effect at the time of filing.
Id. § 39.262(k).
. Id. § 39.253(i) (emphasis added).
. Id. § 39.253(c)-(e).
. Id. at 286.
. Id.
. Tex. Util.Code § 39.253(g).
. TXU, 51 S.W.3d at 286.
. Tex. UtiiXode § 39.253(c)-(e).
. Id. § 39.253(h).
. Id.
. See supra, 51 S.W.3d at 259; see also Stanford v. Butler, 142 Tex. 692, 181 S.W.2d 269, 273 (1944) (observing that courts will ordinarily adopt and uphold a construction placed upon a statute by a department charged with its administration if the statute is ambiguous or uncertain, and the construction is reasonable); Texas Ass’n of Long Distance Tel. Cos. v. Pub. Util. Comm'n, 798 S.W.2d 875, 884 (Tex.App. — Austin 1990, writ denied) (observing that construction of a statute by an administrative agency charged with its enforcement is entitled to great weight, particularly if the statute is ambiguous, so long as the agency’s construction is reasonable and does not contradict the plain language of the statute); Tex. Gov’t Code § 311.023(6) (providing that in construing a statute, whether or not the statute is ambiguous on its face, a court may consider the administrative construction of the statute).
. Tex. Util.Code § 39.303(e).
. Id. § 39.303(f).
. Id.
. Id.
. 453 S.W.2d 379,. 382 (Tex.Civ.App. — Fort Worth 1970, writ ref d n.r.e.).
. 599 S.W.2d 800 (Tex. 1980).
. Richardson v. City of Pasadena, 513 S.W.2d 1, 3 (Tex. 1974).
. Id. at 4.
. Bexar County Sheriffs Civil Serv. Comm’n v. Davis, 802 S.W.2d 659, 664 (Tex. 1990).
. Id. (quoting Gagnon v. Scarpelli, 411 U.S. 778, 788, 93 S.Ct. 1756, 36 L.Ed.2d 656 (1973)).
. See Fay-Ray Corp. v. Texas Alcoholic Beverage Comm’n, 959 S.W.2d 362 (Tex.App.—Austin 1998, no pet.).
. 16 Tex. Admin. Code § 22.206 (requiring a full hearing after a non-unanimous settlement on "issues that remain in dispute”).
. 809 S.W.2d 201, 207 (Tex. 1991).
. 733 S.W.2d 905, 913 (Tex.App. — Austin 1987, writ denied).
. See City of El Paso v. Pub. Util. Comm’n, 883 S.W.2d 179, 182-83 (Tex. 1994) (citing Mobil Oil Corp. v. Fed. Power Comm’n, 417 U.S. 283, 314, 94 S.Ct. 2328, 41 L.Ed.2d 72 (1974)).
. Id. at 183-84.
. 16 Tex. Admin. Code § 22.206.
. See Imperial Am. Res. Fund, Inc. v. R.R. Comm’n, 557 S.W.2d 280, 288 (Tex. 1977).
Concurring Opinion
joined by Chief Justice PHILLIPS, Justice ABBOTT, Justice HANKINSON, and Justice JEFFERSON, concurring.
We join fully in the Court’s judgment affirming the district court and in Justice Owen’s concurring opinion. This is the opinion of the Court regarding the validity of the “non-standard true-up” included in the Public Utility Commission’s financing order for Central Power and Light Company.
Under chapter 39 of the Public Utility Regulatory Act,
A financing order shall include a mechanism requiring that transition charges be reviewed and adjusted at least annually, within 45 days of the anniversary date of the issuance of the transition bonds, to correct any overcollections or undercollections of the preceding 12 months and to ensure the expected recovery of amounts sufficient to timely provide all payments of debt service and other required amounts and charges in connection with the transition bonds.5
The Commission determined that the true-up for CPL should not only adjust the transition charge rate for each class based on changes in consumption within the class — what the Commission called a “standard true-up” — but should also adjust the allocation of transition charges among the classes if any class’s consumption is
Section 39.303(c) states that “[transition charges shall be collected and allocated among customers in the same manner as competition transition charges under Section 39.201.”
(c) The allocation to the residential class shall be determined by allocating to all customer classes 50 percent of the stranded costs in accordance with the methodology used to allocate the costs of the underlying assets in the electric utility’s most recent commission order addressing rate design and allocating the remainder of the stranded costs on the basis of the energy consumption of the classes.
(d) After the allocation to the residential class required by Subsection (c) has been calculated, the remaining stranded costs shall be allocated to the remaining customer classes in accordance with the methodology used to allocate the costs of the underlying assets in the electric utility’s most recent commission order addressing rate design. Non-firm industrial customers shall be allocated stranded costs equal to 150 percent of the amount allocated to that class.
(e) After the allocation to the residential class required by Subsection (c) and the allocation to the nonfirm industrial class required by Subsection (d) have been calculated, the remaining stranded costs shall be allocated to the remaining customer classes in accordance with the methodology used to allocate the costs of the underlying assets in the electric utility’s most recent commission order addressing rate design.
(f) Notwithstanding any other provision of this section, to the extent that the total retail stranded costs, including regulatory assets, of investor-owned utilities exceed $5 billion on a statewide basis, any stranded costs in excess of $5 billion shall be allocated among retail customer classes in accordance with the methodology used to allocate the costs of the underlying assets in the electric utility’s most recent commission order addressing rate design.
(g) The energy consumption of the customer classes used in Subsections (a)(2) and (c) shall be based on the relevant class characteristics as of May 1, 1999, adjusted for normal weather conditions.
(h) For purposes of this section, “stranded costs” includes regulatory assets.
(i) Except as provided by Section 39.262(k), no customer or customer class may avoid the obligation to pay the amount of stranded costs allocated to that customer class.
Residential 37.0664%
Commercial & Small Ind. — Energy 21.5756%
Commercial & Small Ind. — Demand 26.9570%
Large Industrial — Firm 4.4891%
Large Industrial — Non-firm 5.5190%
Standby — Firm 1.4227%
Standby — Non-firm 0.3844%
Municipal & Cotton Gin 2.5858%
Total 100.0000%
To derive each class’s transition charge rate per unit of service, CPL’s financing order requires the transition bonds servi-cer to determine the total revenue needed to meet obligations for the upcoming year, multiply that amount by the percentage factors above to get each class’s dollar allocation, and then divide that allocation by the class’s usage forecast for the year in terms of billing units (e.g., kilowatt-hours for residential customers and kilowatts for demand customers), to arrive at a per-unit transition charge rate to bill the customer. Thus, usage and rate are inversely related. If usage increases, the unit rate decreases, and vice versa. If actual usage during the year varies from the forecast so that a class is charged more or less than its allocation, the class rate for the following year is adjusted up or down to compensate for the overpayment or underpayment the prior year. This adjustment is the standard true-up, and it is not challenged in this case.
Transition charges are nonbypassable; that is, they must be paid by every consumer of electricity in the utility’s service area whether the consumer buys electricity from the utility or not.
It is undisputed that consumption by CPL’s industrial customers has already dropped more than ten percent since April 30, 1999. Texas Industrial Energy Consumers, a party to this case, states that
To illustrate the operation of the nonstandard true-up, OPC offers the following example. Suppose a utility must allocate $100 million in annual transition charges among four classes of customers. Assuming allocation percentages and class usage, the rates for each class are calculated as follows:
_Residential Commercial Industrial Other
(1) Allocation of total annual transí- 40% 20% 10% 30%
tion charges (assumed)_
(2) Annual dollar allocation $40 MM $20 MM $10 MM $30 MM
(multiply $100 MM by line 1)_
(3) Annual unit usage (assumed)_700 MM_260 MM_23 MM 500 MM
(4) Rate per unit (divide line 2 by 5.7c 7.7c 43.5<t 6.0c line 3)
If forecast industrial usage drops to 16 MM units, and consumption by all the other classes remains the same, industrial customers will provide only $7 million in transition charges at a 43.5c rate, leaving a $3 million deficit. If that $3 million is reallocated to the four classes using the non-standard true-up prescribed in CPL’s financing order, the rates for each class would be calculated as follows:
_Residential Commercial Industrial Other
(1) Allocation of total annual transí- 40% 20% 10% 30%
tion charges (assumed)_
(2) Dollar allocation of deficit $1.2 MM $600 K $300 K $900 K
(multiply $3 MM by line 1)_
(3) Dollar allocation of balance_$40 MM_$20 MM_$7 MM $30 MM
(4) Total after reallocation_$41.2 MM $20.6 MM $7.3 MM $30.9 MM
(5) Annual unit usage_700 MM_260 MM_16 MM 500 MM
(6) Rate per unit (divide line 4 by 5.9c 7.9c 45.6c 6.2c line 5)
If industrial class customers had borne the entire rate increase due to their reduced consumption, their rate would have increased to 62.5c and the other three rates would have stayed the same. One will notice in this illustration, although OPC
With this understanding of the non-standard true-up, we return to OPC’s arguments. First, OPC argues that however reasonable and beneficial the non-standard true-up might appear, it simply is not authorized by the PURA. Section 39.253 requires a fixed allocation based on historical data and does not contemplate realloca-tions among classes based on future changes in consumption of electricity. To read section 39.307 to allow for adjustments in section 39.253 allocations among classes, OPC contends, would violate the clear provision of section 39.253(f) that with the exceptions we have already noted, “no customer or customer class may avoid the obligation to pay the amount of stranded costs allocated to that customer class.” Rather, OPC argues, section 39.307 permits only intra-class rate adjustments required by inaccurate forecasts of usage and does not allow for adjustments in the allocations made under section 39.253. OPC points to the language in section 39.307 that true-up adjustments are “to correct any overcollections or undercollec-tions of the preceding 12 months”.
We agree with the Commission and CPL, however, that OPC’s argument ignores broader language in section 39.307 requiring adjustments “to ensure the expected recovery of amounts sufficient to timely provide all payments of debt service and other required amounts and charges in connection with the transition bonds.” A significant shrinkage of CPL’s industrial classes would unquestionably threaten the collection of “amounts sufficient to timely provide all payments of debt service”. OPC does not dispute this fact, nor does it argue that we should simply invalidate the non-standard true-up procedure in the financing order and leave no means to address the problem. Rather, OPC urges us to remand the case to the Commission to find a different solution. But the requirement of section 39.307 that adjustments be made to protect the discharge of transition bond obligations does not limit the means available to the Commission. The nonstandard true-up does not permit classes to avoid allocated charges, as prohibited by section 39.253(i); the procedure merely allows minimal adjustments to ensure the payment of transition bonds — which benefits all of the classes.
OPC argues that reading section 39.307 to allow a non-standard true-up makes section 39.253 a dead letter, allowing the Commission to make whatever allocations it may choose. We disagree. Section 39.307 does not convey such broad discretion, and the Commission makes no claim for such authority. Rather, as the Commission itself recognized in CPL’s financing order, transition charge allocations among customer classes must start with section 39.253, and that allocation must remain undisturbed unless and until its structure threatens the recovery of sufficient revenue to pay the transition bonds
OPC argues that the non-standard true-up will raise residential rates, making it more difficult for non-incumbent retailers to compete and thereby defeating the purpose of chapter 39 deregulation. But as its own illustration shows, the impact of a non-standard true-up on residential rates may well be minuscule. Somewhat inconsistently, OPC argues that a non-standard true-up is unnecessary because the threat of industrial load loss to CPL is not great. Of course, if that turns out to be correct, the non-standard true-up may not be much used or have much effect. In any event, we are not persuaded that the Commission’s order jeopardizes retail competition in residential electricity markets simply because it adopts a procedure used successfully in other states to protect transition bonds.
OPC argues that even if the PURA authorized the Commission to adopt some type of non-standard true-up procedure, the evidence in this proceeding did not support the Commission’s decision in CPL’s financing order to trigger the nonstandard true-up procedure whenever forecast consumption in one class falls below ninety percent of consumption for the year ending April 30, 1999. OPC argues that the ten percent figure was arbitrarily chosen, but as we have noted, the record contains testimony by a Commission staff witness that a class with a decrease in usage of four to seven percent “may be at risk for a cascading load loss scenario.” We have not been cited to any evidence that the ten percent figure was too low. OPC’s argument that the record does not support measuring the ten percent reduction against the year ending April 30,1999, instead of the year immediately preceding the true-up, has more force. OPC contends that the Commission did not fully consider that because CPL’s industrial load loss since April 30, 1999, already exceeds ten percent, the non-standard true-up will be triggered to determine the first rates, and if industrial usage does not increase, may be triggered every year afterward, thereby becoming the standard true-up. As explained more fully in Part XI of, JustiCe Owen’s concurring opinion, we are troubled that the Commission’s haste in this proceeding may have resulted in an incomplete consideration of the complex and critical issues presented. With respect to the ten percent trigger, however, OPC argued its position to the Commission fully, explaining in detail the possible effects of the trigger, just as it has here. While the evidence supporting the Commission’s decision is slight, we cannot say in this case that the decision was arbitrary.
Finally, OPC argues that the Commission did not fully consider alternatives to the non-standard true-up. With respect to one alternative advanced by OPC’s witness — a non-standard true-up among three “super-classes”, combining CPL’s eight customer classes — was fully presented and discussed in the record. The only other alternative that OPC has advanced here is that customers in a class likely to have decreased usage should be required to pay increased transition charges in advance to provide a fund for bond payments later. But if increased rates due to decreased usage will drive customers from a class, we fail to see why increased rates due to anticipated decreased usage will not have the same effect. We find no support for this alternative in the record. OPC has not suggested an alternative solution that
Justice Owen’s dissenting opinion makes three additional arguments which we address briefly. First, she notes that there can be no default on transition bond payments until a class has been completely vacated, leaving no one to pay its share of the transition charges. If the Commission’s concern were really “to ensure the expected recovery of amounts sufficient to timely provide all payments of debt service and other required amounts and charges in connection with the transition bonds” as authorized by section 39.307, the Commission need not have provided for any adjustments to class allocations until one class was vacant. However, we do not agree that the Commission was required to do nothing until the predicted exodus from the industrial class was complete, thereby impairing, at present, the marketability of the transition bonds. Moreover, if the nonstandard true-up prevents the complete vacancy of the industrial class, the other classes will benefit because industrial customers will remain to pay a portion of the transition charges.
Second, Justice Owen argues that section 39.307 is a general provision and therefore cannot be used to “nullify” section 39.253. We disagree that the nonstandard true-up “nullifies” the allocations prescribed by section 39.253. At most, the adjustments are slight, and some adjustments are almost certainly unavoidable if bond obligations are to be met. In our view, Justice Owen would deprive section 39.307 of its express purpose of protecting the means of satisfying bond obligations.
Lastly, unlike OPC, who argues for a remand so that the Commission can devise an alternate solution, Justice Owen argues that the dilemma facing the Commission and parties in this case is simply inescapable without legislative solution. We recognize that we cannot alter a statute’s plain meaning merely to make it more workable, but as we have explained, we believe our reading of section 39.307 is faithful both to its language and to PURA’s purposes.
Accordingly, we conclude that the nonstandard true-up procedure in CPL’s financing order does not violate the PURA.
. Tex. UtilXode §§ 39.001-909 [hereinafter PURA],
. PURA §§ 39.301; 39.302(2), (6)-(8); 39.303; 39.304.
. Id. §§ 39.201 (j), 39.252(b), 39.253(c)-(i), 39.303(c).
. Id.
. Id. § 39.307.
. Id. § 39.303(c).
. Id. § 39.20 l(j).
. Id. §§ 39.302(7), 39.306; see id. § 39.252.
. Id. §§ 39.253(0, 39.262(k).
Dissenting Opinion
dissenting.
I agree with the Court’s disposition of the direct appeals in these cases in all respects but one, which is the Court’s conclusion that the Commission was authorized by section 39.307 of the PURA to adopt a non-standard trueup. Accordingly, I respectfully dissent in part from the Court’s judgment.
I recognize that a mechanism for dealing with what the parties describe as “cascading load loss” may be critical to the marketability of transition bonds and therefore to the viability of securitization financing. However, I am constrained to conclude that the PURA ties the Commission’s hands. Neither section 39.253 nor section 39.307 gives the Commission discretion to reallocate transition charges among customer classes in a manner that is different from the allocation required by section 39.253.
In somewhat simplified terms, the nonstandard trueup provides that if in a given year, the predicted load within a class is projected to decrease by more than ten percent of what the load for that class was for the twelve months ended April 30, 1999, then the amount of transition charges attributable to the projected lost load are reallocated among all customer classes. In short, customers in some classes pay more transition charges than the allocation mechanism prescribed in
Section 39.303(c) of the PURA says that transition charges “shall be collected and allocated among customers” in the manner prescribed by section 39.201.
CPL has eight classes of customers among which transition charges are allocated. They include the residential class, commercial classes, firm industrial customers, non-firm industrial customers, and others. Section 39.253 allocates transition charges to the residential class differently than to the other classes.
Although the Court correctly concludes that there is some ambiguity in section 39.253 about how allocations are to be made among classes of customers, it is nevertheless clear that section 39.253 requires a financing order to establish a fixed percentage for each class that determines how much of the transition charges are to be allocated to each class based on historical data. Section 39.253 does not allow subsequent adjustment of the allocation to take into account growth or, conversely, load loss within each class during the life of the transition bonds, much less projected load loss.
The Commission applied the methodology used in CPL’s last rate design case to the consumption data in that case to arrive at allocation factors, that is percentages, for each class of customers. The Court correctly says that the Commission could have chosen to apply the same rate design methodology to more recent, but nonetheless historical, data.
This can be seen from the examples given by the Court. The Court assumes that $100 million in annual transition charges must be allocated among four classes of customers based on each class’s historical usage. Applying the allocation factors assumed by the Court, each class is assigned the obligation to pay a dollar amount:
_Residential Commercial Industrial Other
(1) Allocation of total annual transí- 40% 20% 10% 30% tion charges (assumed, based on historical usage)_
(2) Annual dollar allocation $40 MM $20 MM $10 MM $30 MM (multiply $100 MM by line 1)
In the Court’s example, a load loss of 16 MM units is forecasted in the industrial class, which is more than a ten percent decrease in that class’s load as of the year ended April 30, 1999. That load loss would trigger the non-standard trueup, and each class’s responsibility to pay its assigned dollar amount is reallocated. Under the Court’s example, $3 million in transition charges that would otherwise be borne by the industrial class is reallocated across all classes:
_Residential Commercial Industrial Other
(1) Allocation of total annual transí- 40% 20% 10% 30% tion charges (assumed, based on historical usage)_
(2) Dollar allocation of deficit $1.2 MM $600 K $300 K $900 K (multiply $3 MM by line 1)_
(3) Dollar allocation of balance_$40 MM $20 MM $7 MM $30 MM
(4) Total after reallocation_$41.2 MM $20,6 MM $7.3 MM $30.9 MM
(5) Resulting allocation factor after 41.2% 20.6% 7.3% 30.9% reallocation of annual transition charges
It is readily apparent that allocation factors for each class have in reality been changed. The residential class no longer bears the percentage of responsibility assigned to it by the methodology set forth in section 39.253. Its obligation is a higher percentage. Likewise, the industrial class is no longer required to shoulder 150 percent of the transition charges allocated to
I agree with the Office of Public Utility Counsel and the Texas Retailers Association that the non-standard trueup contravenes requirements in section 39.253 that are not ambiguous. I agree with those parties that the Commission may not take actions that are in excess of or inconsistent with express statutory provisions. The Third Court of Appeals “restated the familiar principles” in Southwestern Bell Telephone Co. v. Public Utility Commission:
“[A]n agency can adopt only such rules as are authorized by and consistent with its statutory authority.” Railroad Comm’n v. Lone Star Gas Co., 844 S.W.2d 679, 685 (Tex. 1992) (quoting State Bd. of Ins. v. Deffebach, 631 S.W.2d 794, 798 (Tex.App. — Austin 1982, writ ref d n.r.e.)). In this connection, it is well settled that an agency rule may not impose additional burdens, conditions, or restrictions in excess of or inconsistent with the relevant statutory provisions.14
The Commission and those who side with it rely on section 39.307 for authority to adopt non-standard trueups. That provision of the PURA says that a financing order must include an adjustment mechanism “to correct any overcollections or un-dercollections of the preceding 12 months and to ensure the expected recovery of amounts sufficient ■ to timely provide all payments of debt service and other required amounts and charges in connection with the transition bonds.”
The Commission knows how to design a provision that would protect transition bondholders from the complete loss of customers in a class. It did so in the financing order at issue in TXU Electric Co. v. Public Utility Commission.
My fundamental problem with the Court’s holding is that it reads section 39.253 out of the PURA without express language in section 39.307 that can be used to do that. The Court has construed section 39.307 to allow the Commission to allocate transition charges in any manner that it chooses, as long as the Commission deems that necessary to ensure payment of the transition bonds. To give but one example, the Commission could decide not to afford residential customers the protections that section 39.253 provides by choosing to allocate transition costs in a manner entirely different from the one set forth by the Legislature. I recognize that the Commission did not take such a drastic step in CPL’s financing order. But once the moorings of section 39.253 are cut by giving the Commission authority under section 39.307 to allocate transition costs in any manner that it deems necessary, section 39.253 becomes a dead letter.
The general directive that section 39.307 gives to the Commission to “ensure the expected recovery of amounts” to retire transition bonds cannot override the more specific directives in other sections of the PURA about how transition charges are to be allocated among classes of customers. This Court’s decision in State v. Jackson
When the Legislature acts with respect to a particular matter, the administrative agency may not so act with respect to the matter as to nullify the Legislature’s action even though the matter be within the agency’s general regulatory field.
There is little case law announcing the rule last stated, no doubt because it is self-evident.20
In the case before the Court today, section 39.307 is a general grant of regulatory authority. It cannot nullify the specific directive in section 39.253 about how transition charges are to be allocated among customer classes.
I recognize that the Commission found itself in a dilemma. Section 39.253 allocates transition charges in such a way that load loss leading to a death spiral is not unlikely. In Jackson, this Court recognized a similar dilemma: “The State puts its position in these words: ‘The need for administrative closing of the bays increases when and as the Legislature increases
“The problem of statutory construction is to ascertain the intent of the Legislature. When we abandon the plain meaning of words, statutory construction rests upon insecure and obscure foundations at best. It should perhaps be reiterated that Courts have no concern with the wisdom of legislative acts, but it is our plain duty to give effect to the stated purpose or plan of the Legislature, although to us it may seem ill advised or impracticable.”23
I would hold that the Commission did not have the statutory authority to include a non-standard trueup in CPL’s financing order. Accordingly, I respectfully dissent.
. Tex. Util.Code § 39.303(c) (emphasis added).
. Id. § 39.201Q).
. Id. § 39.253(h) ("For purposes of this section, ‘stranded costs' includes regulatory assets.”).
. Id. § 39.253(c)-(e).
. Id. § 39.253(c).
. Id. § 39.253(g).
. Id. § 39.253(c).
. Id. § 39.253(d).
. Id.
. 51 S.W.3d at 259.
. Id.
. Tex. Util.Code § 39.253(i).
. Id.
. 888 S.W.2d 921, 926 (Tex.App. — Austin 1994, writ denied) (quoting R.R. Comm’n v. ARCO Oil & Gas Co., 876 S.W.2d 473, 481 (Tex.App. — Austin 1994, writ denied)).
. Tex. UtiiXode § 39.307 (emphasis added).
. Such a situation might result in challenges to the validity or constitutionality of the true-up provision, but there is no such challenge in this case.
. 51 S.W.3d 275 (Tex. 2001).
. Tex. Util.Code § 39.307.
. 376 S.W.2d 341 (Tex. 1964).
.Id. at 344-45.
. Mat 346.
. Id.
. Id. (quoting State Bd. of Ins. v. Betts, 158 Tex. 612, 315 S.W.2d 279, 281 (1958)).
Reference
- Full Case Name
- CITY OF CORPUS CHRISTI, Et Al., Appellants, v. PUBLIC UTILITY COMMISSION OF TEXAS, Et Al., Appellees; Power Choice, Inc., Appellant, v. Public Utility Commission of Texas and Central Power and Light Company, Appellees
- Cited By
- 225 cases
- Status
- Published