Centerpoint Energy, Inc. v. Public Utility Commission
Centerpoint Energy, Inc. v. Public Utility Commission
Opinion of the Court
delivered the opinion of the Court,
We deny the motion for rehearing. We withdraw our opinion of June 18, 2004 and substitute the following in its place.
In a regulated environment, electric utility companies made very large expenditures to build generation plants, some of which were nuclear power plants. Under regulation, those utilities and their shareholders were entitled to, and had, a reasonable opportunity to recover through rates not only their reasonable and prudent investments of capital in those plants, but also a reasonable, regulated return on those investments.
The Legislature concluded that if generating plants became uneconomic as a result of legislatively mandated deregulation, it was in the public interest for utilities to be made whole by recovering their full investment in those generation plants, although the utilities would no longer receive a return on those investments.
In a rulemaking proceeding, the Texas Public Utility Commission determined that carrying costs on a true-up balance must be calculated from the later date, the date of a true-up final order (sometime after January 10, 2004).
The court of appeals also rejected a related challenge to Rule 25.263(l)(3). In separate proceedings not before us, the Commission directed CenterPoint and AEP to reverse early efforts to mitigate potential stranded costs.
We hold that Rule 25.263(l)(3) is inconsistent with the Legislature’s intent, expressed in Chapter 39 of the PURA, that utilities fully recover their “net, verifiable, nonmitigable stranded costs incurred in purchasing power and providing electric generation service,”
Because Rule 25.263(l)(3) is invalid and we are remanding this matter to the Commission, we do not address whether or under what circumstances generation companies might be entitled to interest on refunds of early mitigation credits if those refunds were to be reversed.
I
We first consider the standard of review. The Commission’s order adopting Rule 25.263
Section 39.001 of the PURA has separate provisions governing review of the validity of a competition rule. Section
CenterPoint and AEP nevertheless filed a direct appeal in the Third Court of Appeals, and the court of appeals’ opinion recites that the court had before it a direct appeal under subsections 39.001(e) and (f) of the Act.
II
This is the fourth case in which we have addressed issues arising out of the partial deregulation of the electric power industry, including issues concerning stranded costs.
The Commission recognizes that if costs are stranded in a deregulated environment, a generation company is entitled to recover carrying costs on those stranded costs, which are recovered over time either through a competition transition charge or securitization. The dissent does not dispute that the Act implicitly, if not explicitly, assumes that there will be carrying
The Commission says such a gap is permissible. The Commission determined in Rule 25.263(0(3) that carrying costs on stranded costs should be recovered by electric utilities only from the date of the final true-up order.
In its order adopting Rule 25.263(l)(3), the Commission explained why it chose the date of a final true-up order as the date from which carrying costs should accrue by saying “a utility’s true-up balance becomes due upon the issuance of a final order in that utility’s true-up proceeding.”
The generation companies counter that the date as of which stranded costs are to be determined is December 31, 2001, as reflected throughout chapter 39. The generation companies also contend that under section 39.262(d), they are entitled to recover the amount the capacity auction true-up yields, without regard to whether they have stranded costs. Capacity auc
Because of the complexity of the issues, we think it helpful to outline our conclusions before examining the Act in greater detail. We conclude that the Commission’s construction of chapter 39 was incorrect regarding the date as of which stranded costs are to be determined. Chapter 39 reflects that the amount of stranded costs, if any, is to be determined as of the day before competition began — December 31, 2001 — or earlier in some cases.
That does not mean that generation companies are entitled to carrying costs on the entire positive balance of stranded costs, if any, from January 1, 2002. Based on the record before us, it appears that the design of the capacity auction true-up may have permitted generation companies to recover during 2002 and 2003 at least a portion of their fixed costs, including stranded costs, if any. That determination cannot be made from this record. Preventing an overrecovery of stranded costs requires a determination, on a company-by-company basis, of whether proceeds from a capacity auction true-up had a component for return on or of stranded costs and of the quantity of any such return. We accordingly remand this proceeding to the Commission for further consideration.
The dissent asserts that our holding “potentially” entitles utilities to “billions of dollars in interest.”
The pertinent sections of Chapter 39 and the record in this case are considered more thoroughly below.
Ill
The deregulation process has many components, some of which can be briefly summarized for purposes of this appeal. The Legislature determined that the production and sale of electricity should no longer be regulated in Texas, except for transmission and distribution services and the recovery of stranded costs.
Resolution of the issues raised by Rule 25.263 requires a more detailed focus, however, on provisions of chapter 39 that govern generation companies and stranded costs.
A
In enacting deregulation legislation, the Legislature had before it a 1998 report prepared by the Public Utility Commission that analyzed potential stranded costs.
That report identified a number of generation companies that, in a deregulated market, were projected to have unrecoverable or “stranded” costs, principally nuclear power plant investments. The Legislature required electric utilities identified in this 1998 report as having projected stranded costs to use “a number of tools ... to mitigate stranded costs” by “reducing] the net book value of, otherwise referred to as ‘acceleratfing]’ the cost of recovery of, its stranded costs” before customer choice began on January 1, 2002.
The Legislature recognized that these early mitigation efforts might not be sufficient to eliminate stranded costs. In the period leading up to customer choice on January 1, 2002, the Legislature gave electric utilities another option. At any time after September 1, 1999 (the start of the retail rate-freeze period), a utility was permitted to securitize 100 percent of its reg
The only explicit reference to carrying costs on stranded costs appears in a section of the Act regarding securitization.
In making the determination of whether securitization benefited ratepayers, the Legislature directed the Commission to look at the entire remaining life of stranded costs, beginning as early as September 2, 1999.
For estimated stranded costs that had not been mitigated or had not been or could not be securitized, the Legislature provided that those costs should be recovered through competition transition charges starting on the first day of competition, January 1, 2002. The Legislature directed in section 39.201 that between April 1, 2000 and January 1, 2002 the Commission was to determine any expected competition transition charge and make it effective on January 1, 2002.
It is highly significant to the question before us today that the Legislature said in section 39.201 that the pertinent date for quantifying stranded costs was December 31, 2001, “the last day of the freeze period” and the last day before customer choice began on January 1, 2002.
C
The Legislature’s use of the words “remaining stranded costs” in section 39.201(Z) is also significant.
D
As it turned out, the calculations made by the Commission in 2001 using the ECOM model showed that no generation company was projected to have stranded costs as of December 31, 2001. Accordingly, no competition transition charges were implemented for any generation company. That fact seems to have obscured the Commission’s view of the date as of which section 39.201 says stranded costs are to be measured. Rule 25.263(l)(3) is contrary to what the Legislature contemplated could happen under section 39.201. If stranded costs had been projected in 2001 to exist on December 31, 2001 for a generation company, then that company was entitled to begin collecting stranded costs.
If company A had been projected in 2001 to have $5,000,000 in stranded costs, A would have begun recovering $5,000,000 plus carrying costs through a competition transition charge from January 1, 2002 over a number of years.
But, as has happened, assume that A was projected in 2001 to have no stranded costs and therefore did not receive a competition transition charge in 2002 and 2003. Further assume that in a 2004 true-up proceeding, it is determined that A has stranded costs of $5,000,000. The Commission says that A could begin recovering $5,000,000 plus carrying costs from 2004 over a period of years. The net result would be that A recovered carrying costs only from 2004.
We must ask, why would the Legislature, planning in 1999 for various contingencies, have intended for company A to recover two years of carrying costs if the 2001 projection turned out to be an accurate predictor of actual stranded costs, but not if the 2001 projection was not an accurate predictor of actual stranded costs? It is extremely unlikely this was the Legislature’s intent, particularly when it is undisputed that if the 2001 projection overestimated, rather than underestimated stranded costs, overrecovery dating back to January 1, 2002 would be reversed.
If the Commission and TIEC were correct that no stranded costs could come into existence until the end of a true-up proceeding, which would be sometime in 2004 or perhaps beyond, then a generation company that collected competition transition charges under section 39.201 would be required under the rationale of Rule 25.263(i) to refund all carrying costs collected as part of those charges between January 1, 2002 and a final true-up order. Nothing in chapter 39 suggests such a result. For example, suppose that the 2001 ECOM model calculations made pursuant to section 39.201 had projected that a generation company’s stranded costs as of December 31, 2001 were $5,000,000, and that company began collecting competition transition charges over a fifteen-year period to recover that amount. Additionally assume that in 2004, the final true-up showed that the company’s stranded costs were $5,000,000, and that $1,000,000 of those costs had been recovered through competition transition charges. Applying the Commission’s reasoning, the generation company would have to refund the carrying cost component in the transition charges collected from 2002 until 2004. Indeed, applying the Commission’s reasoning, the company would have to refund interest on the carrying costs to make up for the time value of the carrying costs that the company collected before 2004.
The Commission’s contentions in this appeal regarding carrying costs are inconsistent with its own rule. Rule 25.263(g)(2)(A) recognizes that under the example in the paragraph above, a company that began collecting carrying costs in 2002 as part of a competition transition charge would keep those carrying costs if, in a 2004 true-up proceeding, it is found to have stranded costs. Rule 25.263(g)(2)(A) provides that in a final true-up, any generation-related invested capital recoverable through a competition transition charge, exclusive of carrying costs, projected to be collected through the date of the final order in the true-up proceeding, is to be deducted from the December 31, 2001 book value of generating assets.
The Commission’s rule creates an anomaly. Whether carrying charges can be collected from January 1, 2002 depends entirely on whether the 2001 ECOM model projected stranded costs. If the model did, then unquestionably, section 39.201 required the Commission to put into effect competition transition charges through which generation companies would begin recovering stranded costs and carrying costs on those stranded costs.
E
Other parts of section 39.201 indicate that the Legislature considered December 31, 2001 to be the date as of which stranded costs would finally be calculated in a true-up proceeding. Subsection 39.201(7) says: “Two years after customer choice is introduced [which would be 2004], the stranded cost estimate under this section shall be reviewed and, if necessary, adjusted to reflect a final, actual valuation in the true-up proceeding under Section 39.262.”
Section 39.262 sets forth in greater detail how the final true-up proceedings are to be conducted in 2004. Section 39.262(c) refers to “finaliz[ing]” “the estimated stranded costs used to develop the competition transition charge in the proceeding held under Section 39.201.”
F
The reference in section 39.201(g) to the definition of stranded costs in Subchapter F leads to another reference to the December 31, 2001 date. Stranded costs are defined in Subchapter F as follows:
“Stranded cost” means the positive excess of the net book value of generation assets over the market value of the assets, taking into account all of the electric utility’s generation assets, any above market purchased power costs, and any deferred debit related to a utility’s discontinuance of the application of Statement of Financial Accounting Standards No. 71 (“Accounting for the Effects of Certain Types of Regulation”) for generation-related assets if required by the provisions of this chapter. For purposes of Section 39.262 [regarding true-up proceedings], book value shall be established as of December 31, 2001, or the date a market value is established*94 through a market valuation method under Section 89.262(h), whichever is earlier, and shall include stranded costs incurred under Section 39.263.82
The Legislature defined stranded costs by using December 31, 2001, the day before customer choice was to begin, as the benchmark for book value, or an earlier date if assets were sold or exchanged.
The Commission and TIEC point out that the definition of stranded costs in section 89.251(7) has two components, book value as of December 31, 2001, and market value, which may not be determined for some companies until 2004 or beyond. This, they say, is justification for concluding that stranded costs do not come into existence, and therefore the company has no right to carrying costs, until the date of a final order in a true-up proceeding. This reasoning has several flaws. The first is the wording of the Act itself.
Section 39.251(7) recognizes that stranded costs may be finally determined even before January 1, 2002, the date that competition began, and certainly before 2004.
Similarly, a company may have been projected to have no stranded costs when the Commission performed the ECOM model calculation in 2001 required by section 39.201. That company may sell or exchange assets sometime in 2002 or 2003. Stranded costs can be finally quantified once that sale or exchange occurs. Yet the Commission says that these stranded costs could not come into existence until 2004 and that the generation company is not entitled to accrue any carrying charges on these stranded costs until the date the Commission issues a final order in a true-up proceeding. Here again, the statutory language does not support such a result.
G
TIEC and, to some extent, the Commission argue that because of fluctuations in market prices from December 31, 2001 until the date of final orders in true-up proceedings in 2004, stranded costs could come in and out of existence. Therefore, they say, it is reasonable to choose a date in 2004 rather than December 31, 2001. This contention ignores the fact that no gain could be realized from upswings in the market value of generation assets unless those assets were sold or exchanged. Interim market swings therefore have nothing to do with the stranded cost equation (net book value of generation assets over the market value of the assets)
There is no cause for concern that rises in gas prices during the interim between January 1, 2002 and December 31, 2003 would translate into excess profits for power companies, even if their nuclear power plants operated profitably. As will be discussed in more detail in section IV below, the return that a power company could earn during 2002 and 2003 was predetermined in 2001. If that predetermined margin is exceeded, then the excess will be refunded by the power company pursuant to the capacity auction true-up under section 39.262(d)(2).
H
This Court did not resolve the issue now before us in In re TXU.
I
Importantly, neither the Commission nor TIEC has offered any rationale to explain why the Legislature chose to use the book value of generation assets on December 31, 2001 (or even earlier) in calculating stranded costs if it intended for stranded costs to come into existence only after a final true-up proceeding in 2004 or beyond. But conversely, there is a compelling reason to determine the amount of stranded costs that existed as of December 31, 2001 and yet use the market value in 2002, 2003, or 2004 of the stranded assets. That compelling reason is that the Legislature knew with certainty that there would be no valid market indicators on December 31, 2001, the day before customer choice began, or for up to two years thereafter.
The fact that the Legislature permits the actual market value of assets in 2002, 2003, or 2004,
IV
It is no coincidence that the capacity
There are two objectives accomplished by the capacity auction true-up proceeding that are pertinent to this appeal. The first is that a generation company is limited to a set margin that it will receive for sales of power, no matter how high or how low gas prices and fuel costs might be during 2002 and 2003. The second is that a generation company is permitted to earn a return on its generation assets during this period. What cannot be determined from this record is how much of that return is a return of or on stranded costs.
Section 39.153 requires a generation company to auction entitlements to at least 15 percent of its total power generation capacity, commencing at least 60 days before the beginning of customer choice.
At the end of the first two years that this auction obligation is in effect (essentially 2002 and 2003), as part of the true-up proceeding in section 39.262,
The court of appeals held that the Commission erred by requiring in Rule 25.263 that any amount owed to the power company resulting from the calculation under subsection 39.262(d) be netted against any “negative” stranded cost calculation.
In the rulemaking proceeding that led to the adoption of Rule 25.263, the power companies, TIEC, and others disputed how the capacity auction true-up determination should be made. The same order that decided that carrying costs on stranded costs should be recoverable only from the date of a final true-up order also decided how the capacity auction true-up would be calculated.
It is not clear from the Commission’s order in this rulemaking proceeding precisely what is calculated by the capacity auction true-up, but filings by the power companies as part of the process do shed some light on the matter. Reliant Energy, Inc., now known as CenterPoint, said in written public comments (part of the record in this case) that the capacity auction true-up calculation resulted in a “margin predicted to be available to contribute to fixed costs and therefore to reduce stranded costs.” Reliant explained in greater detail:
For purposes of the true-up, the ECOM model has two main components: the price of power and the price of fuel. The difference between those components is the margin predicted to be available to contribute to fixed costs and therefore to reduce stranded costs. Assume, for example, that the ECOM price of power is $43/mwh, and the ECOM price of gas is $33/mwh. The margin that is available to reduce stranded costs in this example is $10/mwh.
The capacity auction will also yield a price of power and a price of fuel. The purpose of the PURA § 39.262(d)(2) true-up is to ensure that the [power generation company] ultimately receives the same margin from the capacity auction process as the ECOM model predicted. The [power generation company] may recover part of, all of, or more than that ECOM margin through the*98 bid premiums. In addition, the [power generation company] will experience some gain or loss on fuel when the capacity auction strike prices are compared to the [power generation company’s] actual costs. The remainder (or overcollection) of the margin should be recovered from (or paid back to) ratepayers in the true-up proceeding. Thus, at the time of the true-up, the [power generation company] can be made whole by the following formula:
(ECOM market revenues — ECOM fuel costs) — ((capacity auction price x total busbar sales) — actual fuel costs)
Maintaining the assumption that the margin between the ECOM price of power and the ECOM price of gas is $10/mwh, the [power generation company] should retain that margin in the capacity auction true-up, assuming sales remain the same. For example, suppose the capacity auction price is composed of a $2/mwh bid premium and a $33/mwh fuel cost, for a total capacity auction price of $35/mwh. Assuming that the actual fuel cost is $33/mwh, the [power generation company] would recover from the entitlement holder all of its fuel costs and $2/mwh to apply against stranded costs. But to retain the net margin of $10/mwh in the ECOM model, the [power generation company] should be allowed to recover $8/mwh from ratepayers.
This method could work to the benefit of ratepayers as well. For example, assume that the capacity auction price was $42/mwh and the price of gas was $30/ mwh. In that instance, the [power generation company] would overrecover its expected margin by $2/mwh and would owe that amount to ratepayers.
The Commission adopted a formula for calculating the capacity auction true-up amount that is substantially the same as that proposed by Reliant, except that the Commission limited the true-up to the years 2002 and 2003, omitting any calculation for the months in 2004 before a final true-up order is issued for each power company. No one challenges Rule 25.263 with regard to the capacity auction true-up calculation.
The capacity auction true-up calculation will be company-specific, based on a margin developed in each company’s unbundled cost of service (UCOS) proceeding.
What can be gleaned from the record in this proceeding is that some portion of the margin that results from the capacity auction true-up may contain a component that allows a return of or on stranded costs. The court of appeals held that if a power company is entitled to bill the transmission and distribution utility for the amount that netting the final fuel balance and capacity auction true-up yields, then that amount cannot be netted against a stranded cost calculation that results in a negative number.
TIEC is incorrect when it contends that the margin yielded in the ECOM model worksheets for each company with regard to the capacity auction true-up was intended by the Legislature to be the only means of recovering carrying costs on stranded costs until 2004. Sections 39.201 and 39.262(d) contemplate that a company may recover both competition transition charges from January 1, 2002, as well as the margin contemplated in the capacity auction true-up.
[[Image here]]
For the reasons considered above, we hold that Rule 25.263(0(3) is invalid, and we remand this proceeding to the Commission for further consideration.
. See generally City of Corpus Christi v. Pub. Util. Comm’n, 51 S.W.3d 231, 238 (Tex. 2001).
. See generally Chapter 39 of the Texas Public Utility Regulatory Act, Tex Util.Code §§ 39.001-910.
. Id. § 39.001(b).
. Id. § 39.251(7).
. Id. § 39.001(b)(2); see also City of Corpus Christi, 51 S.W.3d at 237-38.
. Tex Util.Code § 39.001(b)(2); see also City of Corpus Christi, 51 S.W.3d at 238.
. Tex. Util.Code § 39.252(a).
. Id. §§ 39.201, .251-.254, .250-.265, .301-.313.
. Id. §§ 39.201(k), .262(c).
. 16 Tex. Admin. Code § 25.263(l)(3).
. See Tex. Pub. Util. Comm’n, Application of Reliant Energy for Approval of Unbundled Cost of Service Rate Pursuant to PURA § 39.201 and Public Utility Commission Substantive Rule § 25.344, Docket No. 22355 (Oct. 4, 2001) (order), available at http://inter-change.puc.state.tx.us (accessed June 17, 2004); Tex. Pub. Util. Comm'n, Application of Central Power & Light Company for Approval of Unbundled Cost of Service Rate Pursuant to PURA § 39.201 and Public Utility Commission Substantive Rule § 25.344, Docket No. 22352 (Oct. 5, 2001) (order), available at http://inter-change.puc.state.tx.us (accessed June 17, 2004).
. Id.
. Tex. Util.Code § 39.252(a).
. Id. § 39.201(g); see also id. §§ 39.251(7), .201(l).
. Id. § 39.262(d).
. Id. § 39.262(a) (utilities may not be permitted to overrecover stranded costs).
. 26 Tex. Reg. 10498, 10520 (2001) (citing Tex. Util.Code § 14.002); see also 26 Tex. Reg. 4359, 4360 (2001) (proposed June 15, 2001) (stating in the Notice of Proposed Rulemaking that Rule 25.263 was proposed under Tex Util.Code §§ 14.002, 39.252, and 39.262).
. Tex. Util.Code § 14.002.
. 26 Tex. Reg. 10498, 10520 (2001) (citing Tex Util.Code §§ 39.252, .262).
. Tex. Util.Code § 39.001(e).
. Id.
. Id. § 39.001(f).
. See Pub. Util. Comm'n v. City Pub. Serv. Bd. of San Antonio, 53 S.W.3d 310, 315-16 (Tex. 2001); see also Office of Pub. Util. Counsel v. Pub. Util. Comm’n, 104 S.W.3d 225, 232 (Tex.App.-Austin 2003, no pet.).
. The prior decisions are City of Corpus Christi v. Public Utility Commission, 51 S.W.3d 231 (Tex. 2001), TXU Electric Co. v. Public Utility Commission, 51 S.W.3d 275 (Tex. 2001), and In re TXU Electric Co., 67 S.W.3d 130 (Tex. 2001).
. Tex Util.Code § 39.302(5).
. City of Corpus Christi, 51 S.W.3d at 238.
. Tex Util.Code § 39.001(b)(2).
. City of Corpus Christi, 51 S.W.3d at 238.
. Tex. Util.Code § 39.301.
. The rule says:
The TDU [transmission and distribution utility] shall be allowed to recover, or shall be liable for, carrying costs on the true-up balance. Carrying costs shall be calculated using the utility’s cost of capital established in the utility’s UCOS [unbundled cost of service] proceeding, and shall be calculated for the period of time from the date of the true-up final order until fully recovered.
16 Tex. Admin. Code § 25.263(l)(3).
. Id.
. Tex. Util.Code § 39.262(c).
. 26 Tex. Reg. 10498, 10519 (2001).
. Tex. Util.Code § 39.262(d).
. Id. §§ 39.201, .251(7), .262(c), .262(h).
. 143 S.W.3d at 99 (Brister, J., dissenting).
. Tex. Util.Code § 39.001(a).
. Id. §§ 39.101(a), .102.
. Id. § 39.001(b).
. Id. § 39.052.
. Id. § 39.051(b).
. Id. § 39.202.
. Id. § 39.202(a).
. See, e.g., id. §§ 39.254, .262(i) (referring to the Report to the Texas Senate Interim Committee on Electric Utility Restructuring, Potentially Strandable Investment (ECOM) Report: 1998 Update (Apr. 1998)).
. Id. § 39.254.
. Id. § 39.257.
. Id. § 39.254.
. Id. § 39.256.
. "Regulatory assets” are defined in section 39.302(5) of the Utilities Code. See generally City of Corpus Christi v. Pub. Util. Comm’n, 51 S.W.3d 231 (Tex. 2001); TXU Elec. Co. v. Pub. Util. Comm’n, 51 S.W.3d 275 (Tex. 2001).
. Tex. Util.Code §§ 39.201(i), .301-303.
. Id. § 39.301.
. Id. §§ 39.301, .303(a).
. Id. § 39.301.
. Id.
. Id. § 39.303(a).
. See generally TXU Elec. Co. v. Pub. Util. Comm’n, 51 S.W.3d 275, 277 (Tex. 2001); City of Corpus Christi v. Pub. Util. Comm’n, 51 S.W.3d 231, 235-36 (Tex. 2001).
. Tex Util.Code § 39.201(i)(1).
. Id. §§ 39.301, .302(4), .302(7), .303.
. Id. §§ 39.201(i), .301; see also generally TXU Elec. Co., 51 S.W.3d at 281-84.
. Tex. Util.Code § 39.201(a), (c), (d).
. Id. § 39.201(h) (referring to Utility Code section 39.262(i)).
. Id. § 39.201(g). The freeze period is defined in Tex. Util.Code § 39.052(a) as September 1, 1999 until January 1, 2002.
. Id. § 39.201(d), (g).
. Id. § 39.201(l).
. Id.
. Id. § 39.201(d).
. Id. § 39.201(k).
. Id. § 39.201(a)-(k).
. Id. § 39.201(l).
. Id. §§ 39.201(l), .262(g).
. 16 Tex. Admin. Code § 25.263(g)(2)(A).
. Tex. Util.Code § 39.201(a), (b), (d), (f), (g), (h), (k).
. Id. § 39.201(l).
. Id. § 39.201(g), (h), (2) (emphasis added).
. Id.
. Id. § 39.262(c); see also id. § 39.262(h) (describing the methods of quantifying stranded costs “for the purpose of finalizing the stranded cost estimate used to establish the competition transition charge under Section 39.201”).
.Id. § 39.201(g).
. Id. § 39.251(7).
. Id.; see also id. § 39.262(h) (outlining the methods for quantifying stranded costs to finalize the stranded cost estimate used to establish the competition transition charge).
.Id. § 39.251(7).
. Id. §§ 39.251(7), .262(h).
. Id. § 39.251(7).
. Id.
. Id. § 39.262(d)(2).
. 67 S.W.3d 130 (Tex. 2001).
. Id. at 166 (Hecht, J., dissenting).
. Id. at 165-66 (Hecht, J., dissenting).
. See Tex Util.Code § 39.262(h).
. See id. § 39.262(i).
. Id. §§ 39.153, .262(d).
. Id.
. Id. § 39.262(c).
. Id. § 39.251(7).
. Id. § 39.153(a).
. Id. § 39.153(b).
. Id. § 39.262(d).
. 16 Tex. Admin. Code § 25.263; see also 26 Tex. Reg. 10498, 10498-501, 10524 (2001).
. Tex. Util.Code § 39.262(d).
. Id.
. Id.
. 101 S.W.2d at 138-41.
. 26 Tex. Reg. 10498 (2001).
. Id. at 10501.
. Id.
. 16 Tex. Admin. Code § 25.263(i)(1).
. Tex. Util.Code § 39.262(a).
. Id. §§ 39.201(l), .252, .262(c).
. Id. §§ 39.201, .262(a), (d).
Dissenting Opinion
joined by Chief Justice PHILLIPS, Justice SCHNEIDER and Justice SMITH, dissenting.
As a part of electricity-market deregulation, the Legislature allowed existing utility companies to recover stranded costs— but no more. The Legislature said nothing about interest. Nevertheless, the Court holds utilities are potentially entitled to billions
In preparation for the third and final stage of the transition to competition in the electric industry, the Legislature directed the Public Utility Commission to establish procedures for a “true-up proceeding” to be conducted in 2004.
Stranded costs represent the costs of building and operating an electric power plant that would have been recoverable under regulation, but are unlikely to be recoverable in a competitive market.
The statute does not say whether interest should run on stranded costs until they are recovered, and if so from when. The Commission concedes a utility would not recover “all” of its stranded costs if interest does not run from the true-up forward.
But the utilities argue the Commission violated the statute by not providing for additional interest from January 1, 2002 (when competition started) until the true-up. For several reasons, I disagree.
First, the deregulation statute never mentions interest. I find it difficult to say the Commission violated the statute by failing to do something the statute never mentions.
Second, the sole provision of the statute on which the utilities rely is stated in permissive rather than mandatory terms:
An electric utility is allowed to recover all of its net, verifiable, nonmitigable stranded costs incurred in purchasing power and providing electric generation service.10
The focus of this section (entitled “Right to Recover Stranded Costs”) is not on making sure the Commission gives utilities their due, but on making sure customers do not avoid stranded cost recovery by switching to a new provider
Third, the statute allows for recovery only of stranded costs that are “verified” and “nonmitigable.” The Legislature provided that stranded costs were to be mitigated (so far as possible) before the true-up proceedings, and verified during them.
Fourth, even if the statute is ambiguous regarding interest, the Commission’s interpretation is entitled to “great weight” as long as it is reasonable and does not conflict with the statute’s language.
There are several reasons the Legislature may have chosen not to make consumers pay interest on the utilities’ stranded costs between 2002 and 2004. In the first place, the statute provided a number of tools for utilities to mitigate stranded costs beginning in 1999, several years before competition began in 2002.
Second, calculations of stranded costs for 2002 and 2004 are both estimates based on formulas mandated by statute.
CenterPoint argues interest must be paid on stranded costs from 2002 because they came into existence when competition began. But the concept of “stranded costs” is entirely a regulatory accounting construct — it is impossible to say when such a concept comes into “being” in any existential sense. Of course, if the cost of building a nuclear power plant cannot be recovered in a competitive market, the loss suffered by investors is certainly real. But that loss cannot be known until the last kilowatt is sold, and no one suggests waiting until then.
Accordingly, the stranded costs that will be paid to utilities are those created by the statute, and should be paid when and to the extent the statute provides. The Legislature recognized that any estimate of stranded costs might vary widely and continue to do so for many years. Nevertheless, the Legislature provided for a final determination of stranded costs during the
CenterPoint argues that stranded costs should be treated like a jury verdict— though the amount of damages is not calculated until the jury does so, prejudgment interest nevertheless runs from the original occurrence. In the first place, we are not at liberty to decide the question before us on equitable principles, as we originally did with respect to prejudgment interest.
Moreover, with stranded costs, a more apt analogy would be a system in which a jury returns a different verdict every day for a period of years, each one very different from the verdict the day before, and each one correct. In such a system, it would be difficult to say what principal amount should be used to calculate interest. There would also be substantial costs involved in calculating stranded costs so often.
Instead, the Legislature provided for a single definitive determination at the 2004 true-up proceedings, a somewhat arbitrary date that no party challenges, and that (depending on circumstances yet to occur) may operate to the benefit or detriment of utilities or consumers. Given the statute’s clear designation of when stranded costs are finally determined, and its silence regarding interest, the Commission’s rule is both reasonable and consistent with the statute, and thus entitled to our deference.
In a government of separated powers, it is not our role to decide whether paying interest to utilities during 2002 and 2003 would be wise, or fair, or what we would do in similar circumstances. We can decide only whether the Commission violated the deregulation statute by providing for interest from the 2004 true-up forward. Because the statute is silent on the matter, I would hold it did not.
.CenterPoint asserts in its petition for review that it alone would lose $1 billion in interest on stranded costs between 2002 and the true-up proceeding in 2004.
. 143 S.W.3d at 84.
. TEX. UTIL.CODE § 39.262(c).
. 16 TEX. ADMIN. CODE § 25.263.
. See TEX. UTIL.CODE § 39.251(7); In re TXU Elec. Co., 67 S.W.3d 130, 132 (Tex. 2001) (Phillips, C J., concurring).
. TEX. UTIL.CODE § 39.252(a).
. See id. § 39.262(c).
. 16 TEX. ADMIN. CODE § 25.263(l)(3).
. TEX. UTIL.CODE § 39.252(a) (emphasis added).
. Id. § 39.252(c).
. Id. § 39.252(b).
. See generally id. § 39.254-.262.
. State v. Pub.Util. Comm’n of Tex., 883 S.W.2d 190, 196 (Tex. 1994); see also Osterberg v. Peca, 12 S.W.3d 31, 51 (Tex. 2000) (giving "great weight” to Texas Ethics Commission’s interpretation).
. See TEX. UTIL.CODE §§ 39.201(i)(1) (allowing securitization of up to 75% of stranded costs), 39.254 (requiring earnings in excess of the allowed rate of return to be applied to stranded costs), 39.256(a) (allowing redirection of transmission asset depreciation); see generally § 39.254 (requiring utilities to use mitigation tools).
. See id. §§ 39.201(h), 39.262(i). Neither calculation would be an estimate to the extent the underlying stranded costs (power-generation assets, primarily nuclear power plants) were sold, see id. § 39.262(h)(1), but there is no indication in our record that such plants have changed hands.
.See id. 39.201(h). The statute provided for adjustment of rates at the 2004 true-up to provide recovery of stranded costs, but did not require reimbursement of interest if the 2001 estimates were lower or higher. Id. § 39.262(g) ("If the commission determines that the nonbypassable delivery rates are not sufficient, the commission may extend the original collection period for the [CTC] charge or, if necessary, increase the charge.’’).
. See Cavnar v. Quality Control Parking, Inc., 696 S.W.2d 549, 552 (Tex. 1985), superseded by TEX. FIN.CODE § 304.102.
Reference
- Full Case Name
- CENTERPOINT ENERGY, INC. F/K/A Reliant Energy, Incorporated and American Electric Power Company, Inc., Petitioners, v. PUBLIC UTILITY COMMISSION OF TEXAS, Respondent
- Cited By
- 71 cases
- Status
- Published