Armed Services Board of Contract Appeals, 2014

Pulliam Construction Company, Inc.

Pulliam Construction Company, Inc.
Armed Services Board of Contract Appeals · Decided February 5, 2014 · Stempler
Pulliam Construction Company, Inc.

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of-- ) ) Pulliam Construction Company, Inc. ) ASBCA Nos. 58523, 58524, 58525 ) 58526,58527,58528 ) 58529,58530 ) Under Contract No. N62473-06-D-1017 ) APPEARANCE FOR THE APPELLANT: Thomas M. Finrow, Esq.

The Law Firm of Thomas M. Finrow LaMesa, CA APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq.

Navy Chief Trial Attorney Genifer M. Tarkowski, Esq.

Trial Attorney ORDER OF DISMISSAL The dispute has been settled.

The appeals ar~ dismissed with prejudice.

Dated: 5 February 2014

Administrative Judge Vice Chairman Armed Services Board of Contract Appeals I certify that the foregoing is a true copy of the Order of Dismissal of the Armed Services Board of Contract Appeals in ASBCA Nos. 58523, 58524, 58525, 58526, 58527, 58528, 58529, 58530, Appeals of Pulliam Construction Company, Inc., rendered in conformance with the Board's Charter.

Dated:

JEFFREY D. GARDIN Recorder, Armed Services Board of Contract Appeals

Case-law data current through December 31, 2025. Source: CourtListener bulk data.