Armed Services Board of Contract Appeals, 2016

Jeffrey C. Stone Inc., d.b.a. Summit Builders

Jeffrey C. Stone Inc., d.b.a. Summit Builders
Armed Services Board of Contract Appeals · Decided January 7, 2016 · Scott
Jeffrey C. Stone Inc., d.b.a. Summit Builders

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) Jeffrey C. Stone Inc., d.b.a. Summit Builders ) ASBCA No. 58372 ) Under Contract No. W912PL-10-C-0034 ) APPEARANCES FOR THE APPELLANT: John R. Jefferies, Esq.

Justin R. DePaul, Esq.

Fennemore Craig, P.C.

Phoenix, AZ APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.

Engineer Chief Trial Attorney Gilbert H. Chong, Esq.

Engineer Trial Attorney U.S. Army Engineer District, Los Angeles ORDER OF DISMISSAL The dispute has been settled. The appeal is dismissed with prejudice.

Dated: 7 January 2016

ministrative Judge Armed Services Board of Contract Appeals I certify that the foregoing is a true copy of the Order of Dismissal of the Armed Services Board of Contract Appeals in ASBCA No. 58372, Appeal of Jeffrey C. Stone Inc., d.b.a. Summit Builders, rendered in conformance with the Board's Charter.

Dated:

JEFFREY D. GARDIN Recorder, Armed Services Board of Contract Appeals

Case-law data current through December 31, 2025. Source: CourtListener bulk data.