Armed Services Board of Contract Appeals, 2016

Munilla Construction Management, LLC

Munilla Construction Management, LLC
Armed Services Board of Contract Appeals · Decided October 6, 2016 · Stempler
Munilla Construction Management, LLC

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) Munilla Construction Management, LLC ) ASBCA No. 60664 ) Under Contract No. W912EP-13-C-0008 ) APPEARANCE FOR THE APPELLANT: Karl Dix, Jr., Esq.

Smith, Currie & Hancock LLP Atlanta, GA APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.

Engineer Chief Trial Attorney Joshua R. Holmes, Esq.

B. Seth Johnson, Esq.

Engineer Trial Attorneys U.S. Army Engineer District, Jacksonville ORDER OF DISMISSAL The dispute has been settled. The appeal is dismissed with prejudice.

Dated: 6 October 2016

Administrative Judge Acting Chairman Armed Services Board of Contract Appeals

I certify that the foregoing is a true copy of the Order of Dismissal of the Armed Services Board of Contract Appeals in ASBCA No. 60664, Appeal ofMunilla Construction Management, LLC, rendered in conformance with the Board's Charter.

Dated:

JEFFREY D. GARDIN Recorder, Armed Services Board of Contract Appeals

Case-law data current through December 31, 2025. Source: CourtListener bulk data.