Armed Services Board of Contract Appeals, 2016

Lebolo-Watts Constructors 01 JV, LLC

Lebolo-Watts Constructors 01 JV, LLC
Armed Services Board of Contract Appeals · Decided October 4, 2016 · Page
Lebolo-Watts Constructors 01 JV, LLC

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of -- ) ) Lebolo-Watts Constructors 01 JV, LLC ) ASBCA Nos. 59739, 59910 ) Under Contract No. W912DR-11-C-0033 ) APPEARANCES FOR THE APPELLANT: Herman M. Braude, Esq.

Edward D. Manchester, Esq.

Braude Law Group, P.C.

Washington, DC APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.

Engineer Chief Trial Attorney William J. Selinsky, Esq.

Scott C. Seufert, Esq.

David B. Jerger, Esq.

Engineer Trial Attorneys U.S. Army Engineer District, Baltimore ORDER OF DISMISSAL The parties' joint motion of 29 September 2016 states that the parties have "settled the claim that is the subject of these appeals by agreement dated July 7, 2016 and by Contract modification P00003, which effectuated the settlement agreement." They ask that these appeals be dismissed with prejudice.

The parties' motion is granted, and these appeals are dismissed with prejudice.

Dated: 4 October 2016

REBA PAGE Administrative Judge Armed Services Board of Contract Appeals I certify that the foregoing is a true copy of the Order of Dismissal of the Armed Services Board of Contract Appeals in ASBCA Nos. 59739, 59910, Appeals ofLebolo-Watts Constructors 01 JV, LLC, rendered in conformance with the Board's Charter.

Dated:

JEFFREYD. GARDIN Recorder, Armed Services Board of Contract Appeals