Better Built + Clark, LLC
Opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS• Appeal of -- ) ) Better Built + Clark, LLC ) ASBCA No. 60305 ) Under Contract No. N40083-1 O-C-0021 ) APPEARANCE FOR THE APPELLANT: R. Edward Boucher, Esq.
Kotz Sangster Wysocki P.C.
Detroit, MI APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq.
Navy Chief Trial Attorney Timothy J. Cothrel, Esq.
Trial Attorney ORDER OF DISMISSAL WITHOUT PREJUDICE Appellant appealed the decision of the contracting officer denying its claim for additional costs associated with electrical work related to construction of an Armed Forces Reserve Center, Akron, Ohio. The parties agreed to a settlement, however, the settlement amount of $165,000 has not been paid. The parties jointly request that the Board dismiss without prejudice pursuant to Board Rule 18(b) pending payment of the agreed upon settlement amount. Accordingly, the above-referenced appeal is hereby dismissed without prejudice. Unless either party or the Board acts within 180 days from the date of this Order to reinstate this appeal, the dismissal shall be deemed with prejudice.
Dated: August 15, 2019
Administrative Judge Armed Services Board of Contract Appeals I certify that the foregoing is a true copy of the Order of Dismissal of the Armed Services Board of Contract Appeals in ASBCA No. 60305, Appeal of Better Built+ Clark, LLC, rendered in conformance with the Board's Charter.
Dated: PAULLA K. GATES-LEWIS Recorder, Armed Services Board of Contract Appeals
Case-law data current through December 31, 2025. Source: CourtListener bulk data.