Armed Services Board of Contract Appeals, 2020

Emerson Development VIII, LLC

Emerson Development VIII, LLC
Armed Services Board of Contract Appeals · Decided October 2, 2020 · McNulty
Emerson Development VIII, LLC

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Emerson Development VIII, LLC ) ASBCA No. 61962 ) Under Contract Nos. DACA-31-5-2014-0305 ) DACA-31-5-2015-0404 ) APPEARANCE FOR THE APPELLANT: Terrence M. O’Connor, Esq.

Berenzweig Leonard, LLP McLean, VA APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney Michael T. Shields, Esq.

Engineer Trial Attorney U.S. Army Engineer District, Baltimore ORDER OF DISMISSAL The appeal has been settled. The parties jointly stipulate to dismiss this appeal pursuant to Rule 18(b) of the Rules of the Armed Services Board of Contract Appeals.

Accordingly, this appeal is hereby dismissed without prejudice. Unless either party or the Board acts to reinstate the appeal within 180 days from the date of this Order, the dismissal shall be deemed with prejudice.

Dated: October 2, 2020

CHRISTOPHER M. MCNULTY Administrative Judge Armed Services Board of Contract Appeals I certify that the foregoing is a true copy of the Order of Dismissal of the Armed Services Board of Contract Appeals in ASBCA No. 61962, Appeal of Emerson Development VIII, LLC, rendered in conformance with the Board’s Charter.

Dated: October 6, 2020

PAULLA K. GATES-LEWIS Recorder, Armed Services Board of Contract Appeals