Norwood, MA v. FERC
Norwood, MA v. FERC
Opinion
United States Court of Appeals For the First Circuit
No. 99-2155
TOWN OF NORWOOD, MASSACHUSETTS,
Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION,
Respondent. __________
NEW ENGLAND POWER COMPANY,
Intervenor.
ERRATA
At page 12, line 11, delete: "--by contrast to our case;" and
add a semicolon after "clause".
Also on page 12, add the following full paragraph between the two
existing full paragraphs:
By contrast, in our case there is no effort by anyone
to charge or obtain a rate different than that on file with
the Commission. And, as for duration, all of the contract
terms being given effect by the FERC orders under review are
on file with the Commission; the Norwood-New England Power
contract amendment, filed with the Commission in 1989, explicitly permitted Norwood to elect to extend the contract
(which Norwood then did). Thus, the Commission, when it
accepted the amendment for filing, knew that Norwood now had
the option to extend the duration by specific increments.
This is a situation very different from Arkla where, based
on a "favored nations" clause containing no specific rate,
the producer sought--over the Commission’s expressed
objection--to recover from the purchasing utility a rate for
natural gas higher than the specific rate on file with the
Commission.
Reference
- Status
- Published