Universal Ins. Co. v. Centro De
Universal Ins. Co. v. Centro De
Opinion
Not for Publication in West's Federal Reporter Citation Limited Pursuant to 1st Cir. Loc. R. 32.3
United States Court of Appeals For the First Circuit No. 04-2359
AERO-METRIC INCORPORATED; TRIATHLON LTD., f/k/a TRIATHLON MAPPING; PHOTO SCIENCE, INC.,
Plaintiffs,
v.
CENTRO DE RECAUDACIONES DE INGRESOS MUNICIPALES (CRIM),
Defendant, Cross-Claimant, Appellant,
UNIVERSAL INSURANCE CO.,
Defendant, Cross-Claimant, Appellee,
ENTEC CORPORATION, INC.; CONSULTA ECONOMICA Y PLANIFICACION, INC.; HECTOR RIVAS & ASOCIADOS (HRA); TOMMY HABIBE; CHICORP FINANCIAL SERVICES; ANALYTICAL SURVEYS INCORPORATED; EASTCAM GEOMATICS LIMITED; MANUFACTURERS AND TRADERS TRUST COMPANY, not individually but solely in its capacity as Trustee; JAMES W. SEWALL COMPANY; AMERICAN BONDING COMPANY; LIBERTY MUTUAL INSURANCE COMPANY,
Defendants.
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF PUERTO RICO
[Hon. Héctor M. Laffitte, U.S. District Judge]
Before
Lynch, Lipez, and Howard, Circuit Judges. Fernando Van Derdys, with whom Law Offices of Fernando Van Derdys was on brief, for cross-claim appellant. Eduardo Castillo-Blanco, with whom Law Offices of Ivan M. Fernandez was on brief, for cross-claim appellee.
July 8, 2005 Per Curiam. Appellant Centro de Recaudaciones de
Ingresos Municipales (CRIM) appeals from a summary judgment denying
its claim under a surety contract, issued by appellee Universal
Insurance Company, on which it was a named obligee. The procedural
history of the case is complicated, but we will confine ourselves
to the essentials, which are relatively straightforward.
On August 18, 1995, Universal agreed to act as a surety
to ENTEC Corporation, the general contractor hired by CRIM to
design, furnish, and install a Land Information Management System.
Accordingly, Universal simultaneously issued a Performance Bond,
which guaranteed to CRIM the general performance of the contract
(up to the penalty specified in the bond), and a Labor and Material
Payment Bond, which guaranteed the payment of subcontractors
(again, up to the penalty specified in the bond). Each bond was
given the number 000-41867, named ENTEC as the principal and CRIM
as the obligee, and was issued with a bond penalty sum in the
amount of $501,750.00 -- apparently, a small fraction of the value
of the project. Effective October 16, 1996, ENTEC and Universal
executed an endorsement "[t]o be attached to and form part of bond
no. 000-41867 issued on behalf of [ENTEC] as Principal and in favor
of [CRIM] as Obligee in the amount of ONE MILLION THREE THOUSANDS
FIVE HUNDRED AND 00/100 Dollars ($1,003,500.00)." The endorsement
added Chicorp Financial Services "AS ADDITIONAL OBLIGEE UNDER
CAPTIONED BOND."
-2- In May 2000, a number of subcontractors brought the
underlying lawsuit alleging, inter alia, breach of contract. CRIM
and Universal were named defendants. On May 31, 2002, Universal
filed a motion for consent and/or declaratory judgment asking the
district court to decree its liability on bond no. 000-41867 to be
the penalty sum of $501,750.00 and to dismiss all claims against it
with prejudice, subject to it paying the judgment amount to the
court. On September 17, 2002, the court entered the requested
judgment and, on October 1, 2002, Universal deposited $501,750.00
with the court.
Shortly thereafter, however, CRIM cross-claimed against
Universal under the Performance Bond in the amount of $501,750.00.
Universal moved to dismiss the cross-claim, CRIM opposed, and
several additional filings ensued. The parties' dispute centered
around whether the $501.750.00 penalty set forth on the Performance
Bond and on the Labor and Material Payment Bond was Universal's
total liability as surety, or whether Universal was separately
obligated in the amount of $501,750 under each bond, in which case
the amount deposited with the court would not reflect Universal's
total liability.
Universal pointed to the Supreme Court of Puerto Rico's
decision in Caguas Plumbing, Inc. v. Continental Constr. Corp.,
2001 JTS 169(2001), where the Court in dicta evinced an
understanding that a surety's liability under similar,
-3- simultaneously issued Performance and Labor and Material Bonds was
the single amount listed on each bond. CRIM countered that the
surety contract at issue here materially differed from that
considered in Caguas Plumbing by pointing to the endorsement, which
stated that Universal's liability was twice the $501,750.00
specified in each bond, or $1,003,500.00. Along these same lines,
CRIM also mentioned, without elaborating why it should matter, the
fact that the project cost far more than Universal's potential
liability under either reading of the contract. Universal
responded with a sworn statement from Iris M. Rivera-Menéndez,
Universal's Surety Department Manager, which averred that the sole
purpose of the endorsement was to name Chicorp Financial Services
as an additional obligee under bond no. 000-41867, that no
additional premium was charged for the issuance of the endorsement,
and that the endorsement did not alter the amount of Universal's
monetary liability in any way.
Treating the motion to dismiss as one for summary
judgment and finding the Caguas Plumbing decision to be
dispositive, the district court entered judgment in favor of
Universal. The court's brief opinion explaining the judgment made
no mention of the endorsement or the fact that the contract covered
only a fraction of the project's cost.
On appeal, CRIM makes intertwined arguments, which may be
addressed together, that the district court improperly resolved on
-4- summary judgment a material factual issue -- the intent of the
parties to the surety contract with respect to the total liability
issue. In developing its position, CRIM relies on the endorsement,
which, it says, constitutes trialworthy evidence that the parties
intended Universal's total liability to be $1,003,500.00. (CRIM
also again adverts to the fact that the project's cost far exceeded
Universal's liability, but fails to explain why this is relevant).
Universal responds by pointing out that Rivera's sworn
statement, the upshot of which is that the total liability
specified in the endorsement was a mistake, is uncontradicted. And
with the endorsement out of the picture, Universal says, we should
proceed on the same assumption as did the Caguas Plumbing court --
that the surety contract contemplated that Universal would be
liable only for the single penalty listed in each of the two bonds
(which together form a single agreement). Without disputing that
surety contracts involving the simultaneous issuance of Performance
and Labor and Material Payment Bonds usually give rise only to the
single penalty specified in each bond, CRIM replies that we should
not treat the Rivera sworn statement as dispositive on the issue of
the parties' intentions because Universal still controls, and has
not made available, the relevant documents regarding the parties'
intentions and the premiums paid.
We start with CRIM's last point -- that Universal is in
control of the documentation that might permit it to dispute
-5- Rivera's sworn statement. Perhaps this is so, but CRIM did not
object to (and does not now complain of) the district court's
decision to treat Universal's motion to dismiss as one for summary
judgment. Nor did CRIM seek to invoke Fed. R. Civ. P. 56(f) to
conduct the relevant discovery. Thus, CRIM lacks a basis to
complain about the state of the record, and we are constrained to
accept what Rivera says: that the gratuitously provided
endorsement merely added Chicorp as an additional obligee under the
surety contract and worked no change in Universal's underlying
liability. See Fed. R. Civ. P. 56(e); Celotex Corp. v. Catrett,
477 U.S. 317, 322-23(1986).
This leads us swiftly to conclude that the district court
did not err in concluding that Universal met its summary judgment
burden. While we think that the court read too much into the
Caguas Plumbing decision -- the issue presented here was not joined
in that case -- CRIM has provided us with no basis for questioning
the Caguas Plumbing court's premise that a surety who
simultaneously issues Performance and Labor and Material Payment
Bonds as part of a single surety contract is only liable for the
single penalty amount specified in each bond. See Caguas Plumbing,
P.R. Offic. Trans. at 4. In any event, the premise strikes us as
quite sensible. On a $1,000,000 project, it is easy to see how a
contractor (and thus a surety, see 10 Appleman, Insurance Law &
Practice, § 5856 (1981) (making clear that the obligations of a
-6- surety on a public contractor's bond is commensurate with that of
the contractor)) could be liable for up to $1,000,000 to various
subcontractors, or up to $1,000,000 to the obligee. But it is more
difficult to see how, absent unforeseen circumstances such as cost
overruns (which are circumstances against which a surety agreement
does not insure), the contractor could end up being liable in the
amount of $1,000,000 to both. After all, the value of any work
done by the subcontractors towards completion of the project (and
within the project's specifications) would reduce the contractor's
ultimate liability to the project's owner by that same amount.
Thus, $500,000 worth of work by the subcontractors would be
$500,000 worth of work not owed to the project's owner.
In closing, we acknowledge that, unlike the situation in
Caguas Plumbing, the penalty specified in the Performance and Labor
and Material Payment Bonds constituted only a fraction of the
project's cost. But CRIM has failed to explain, and we do not see,
why that fact should matter.
Affirmed.
-7-
Reference
- Status
- Published