United States ex rel. Bryant v. Lembke Construction Co.
Opinion of the Court
This Miller Act case was brought in the United States District Court by the use plaintiff-appellant against appellees Lembke Construction Company, Inc., a prime contractor on a government construction contract, and its surety, Glens Falls Insurance Company. The District Court rendered judgment for the appellees.
Appellee Lembke Construction Company contracted to construct certain facilities for the United States Government. As required by the Miller Act,
Since appellant Bryant had no contractual relationship with the prime contractor, appellee Lembke, Bryant cannot recover on the payment bond unless he can
The Supreme Court in Clifford F. MacEvoy Co. v. United States et al., 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163, addressed itself to an interpretation of “subcontractor” as the word is used in the proviso. In that case, considering the Miller Act’s history, the Court rejected a broad generic definition of the word and, instead, found that it was intended to have a “more technical meaning, as established by usage in the building trades * *
The MacEvoy case does tell us that “The Miller Act * * * is highly remedial in nature. It is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.”
In this case, Adams undertook to furnish concrete. There was by this undertaking no substantial delegation of any portion of Lembke’s contract. The concrete Adams undertook to deliver was in no way a “customized” material, thus bringing Adams within the purview of those eases holding that a supplier of such “customized” material is a subcontractor, even though he does not perform many services in reference to installation.
We agree with appellant that “subcontractor” must be given a judicial interpretation and that its meaning is not dependent upon how the parties designate themselves.
We think it would fly in the face of the “practical considerations underlying the [Miller] Act"
Affirmed.
. 40 U.S.C. § 270a.
. The statute has been quoted so often in other opinions, we quote only that part necessary for a determination of the question in this case:
“ * * * Provided, however, That any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. * * * ”
. Clifford F. MacEvoy Co. v. United States et al., supra, 322 U.S. at 108, 64 S.Ct. at 894.
. Clifford F. MacEvoy Co. v. United States et al., supra, 322 U.S. at 107, 64 S.Ct. at 893; See Golden West Construction Company v. United States et al., 10 Cir., 304 F.2d 753 and Woods Construction Company v. Pool Construction Company, 10 Cir., 348 F.2d 687 and cases there cited.
. United States for the Use and Benefit of Gulfport Piping Company v. Monaco and Son, Inc., U.S.D.C.Md., 222 F.Supp. 175, reversed on other grounds, 4 Cir., 336 F.2d 636; and see United States for Use of Wellman Engineering Company v. MSI Corporation, 2 Cir., 350 F.2d 285.
. See United States to Use of Hardwood Products Corp. v. John A. Johnson & Sons, D.C.W.D.Pa., 137 F.Supp. 562; Basich Brothers Construction Company v. United States, 9 Cir., 159 F.2d 182; United States for Use of Wellman Engineering Company v. MSI Corporation, 2 Cir., 350 F.2d 285.
. United States for Use of Potomac Rigging Company v. Wright Contracting Company, U.S.D.C.Md., 194 F.Supp. 444, 447; Brown & Root, Inc. v. Gifford-Hill & Co., 5 Cir., 319 F.2d 65. Compare United States to Use of Hardwood Products Corp. v. John A. Johnson & Sons, D.C.W.D.Pa., 137 F.Supp. 562 and United States for Use of Wellman Engineering Company v. MSI Corporation, 2 Cir., 350 F.2d 285.
. See Clifford F. MacEvoy Co. v. United States et al., supra, 322 U.S. at 108, 64 S.Ct. 890; United States for Use of Wellman Engineering Company v. MSI Corporation, 2 Cir., 350 F.2d 285 and United States for the Use and Benefit of Gulfport Piping Company v. Monaco and Son, Inc., U.S.D.C.Md., 222 F.Supp. 175, reversed on other grounds, 4 Cir., 336 F.2d 636.
. Clifford F. MacEvoy Co. v. United States et al., supra, 322 U.S. at 108, 64 S.Ct. at 894; see also United States for Use of Potomac Rigging Company v. Wright Contracting Company, supra.
. The District Court specifically found:
“That the contracting industry by custom and usage in the contracting business recognizes the distinction between the Standard Form of Material Contract and the Standard Subcontract Form and the following requirements in connection therewith:
“That under Standard Form of Material Contracts sales tax is added to the price, and that in the use of Standard Subcontract Forms the sales tax is figured in the price and not added thereto; that in the case here before the Court the contract on the Standard Form of Material Contract added the tax to the price therein contained and did not include the tax in the price set forth.
“That under the Standard Form of Material Contract payrolls are not submitted to the prime contractor and under the Standard Subcontract Form of agreement payrolls are submitted to the prime contractor; that in the case here before the Court no payrolls were submitted to the prime contractor by the Adams Concrete Co. under the Standard Form of Material Contract.
“That under the Standard Form of Material Contract copies of such contracts are not required to be furnished the Bureau of Indian Affairs, and under the Standard Subcontract Form copies are required to be furnished the United States Bureau of Indian Affairs; that in the case here before the Court no copies of the contract entered into on the Standard Form of Material Contract were furnished the United States Department of the Interior, Bureau of Indian Affairs.
“That under Standard Form of Material Contract no performance bond is required, and under the Standard Subcontract Form performance bonds are required; that in the case here before the Court no performance bond was furnished by the Adams Concrete Co. under Standard Form of Material Contract but was required under Standard Subcontract Form.”
. Clifford F. MacEvoy Co. v. United States et al., supra, 322 U.S. at 110, 64 S.Ct. at 895.
. Ibid.
Reference
- Full Case Name
- UNITED STATES of America, for the Use of Harold BRYANT, dba Rio Grande Sand and Gravel v. LEMBKE CONSTRUCTION COMPANY, Inc., and Glens Falls Insurance Company
- Cited By
- 11 cases
- Status
- Published