Outokumpu Stainless USA, LLC v. Converteam SAS
Opinion
*1320
This appeal requires us to examine seemingly interrelated-but actually quite separate-questions under the Convention on the Recognition and Enforcement of Foreign Arbitral Awards ("New York Convention" or "Convention"): (1) whether an action between a buyer and a sub-contractor of a seller "relates to" an arbitration agreement signed by the buyer and seller sufficient to establish federal subject matter jurisdiction, and (2) whether a non-signatory sub-contractor may compel arbitration against the buyer under that arbitration agreement. In following our sister circuits, we conclude that these inquiries require a bifurcated analysis.
Beiser v. Weyler
,
I. FACTUAL BACKGROUND
Plaintiff Outokumpu Stainless, LLC ("Outokumpu") operates a steel plant in Calvert, Alabama. The facility contains three "cold rolling mills," or CRMs, required for manufacturing and processing certain steel products. In November 2007, while the plant was still under construction, Outokumpu's predecessor ThyssenKrupp Stainless USA LLC entered into three contracts with Fives (then F.L. Industries, Inc.) to provide three different sized CRMs ("Outokumpu-Fives Contracts" or the "Contracts"). The Outokumpu-Fives Contracts each contain an arbitration clause:
All disputes arising between both parties in connection with or in the performance *1321 of the Contract shall be settled through friendly consultation between both parties. In case no agreement can be reached through consultation after a maximum period of 30 days or as soon as one of the parties involved appeals for the arbitration tribunal the dispute shall be considered as failed and any such dispute shall be submitted to arbitration for settlement.
The arbitration clause further requires that the arbitration take place in Dusseldorf, Germany in accordance with the Rules of Arbitration of the International Chamber of Commerce and that the forum apply the substantive law of Germany.
The Contracts define Outokumpu as the "Buyer" and Fives as the "Seller," and state that "Buyer and Seller [are] also referred to individually as 'Party' and collectively as 'Parties.' " The Contracts further provide that: "When Seller is mentioned it shall be understood as Sub-contractors included, except if expressly stated otherwise." The Contracts define "Sub-contractor" as "any person (other than the Seller) used by the Seller for the supply of any part of the Contract Equipment, or any person to whom any part of the Contract has been sub-let by the Seller[.]" Appended to each Contract is a subcontractor list that enumerates the "Preferred Brands or Manufacturers" for Outokumpu and Fives; Defendant GE Energy Conversion France SAS ("GE Energy"), formerly known as Converteam SAS, is on that list.
Each CRM requires three motors, and Fives subcontracted with GE Energy to supply all nine motors. The motors were manufactured in France and delivered and installed in Alabama between 2011 and 2012. However, by June 2014, the motors began to fail. Despite inspections and emergency repairs, motors from all three of the CRMs failed by August 2015.
Outokumpu approached Fives about replacing or repairing the motors. Through correspondence between GE Energy and Fives, Outokumpu discovered that GE Energy, Fives, and a third company, DMS SA, had entered into a subcontractor agreement, the "Agreement for Consortial Cooperation," three weeks after the Outokumpu-Fives contracts were executed. The Consortial Agreement had "the aim of optimizing the chances of the parties to be awarded the project." Under the Consortial Agreement, GE Energy, Fives, and DMS agreed that "[a]ny and all stipulations of the [Outokumpu-Fives Contracts] shall apply mutatis mutandis to each party for its own scope of supply and services."
The Consortial Agreement in turn contains its own arbitration clause as follows:
The PARTIES shall endeavor to settle any dispute, controversy or claim arising out of or in connection with this AGREEMENT or with the [Outokumpu-Fives Contracts] or the breach, interpretation or validity of this Agreement amicably.
If not agreement settlement can be reached within a reasonable time, either PARTY may commence arbitration after serving a 15 days written notice to the other PARTY. Such dispute shall be finally settled under the Rules of Arbitration of the International Chamber of Commerce by one or more arbitrators appointed in accordance with the said Rules. The place of arbitration shall be Paris.
...
In the event a dispute occurs between [Outokumpu] and [Fives], which results in an arbitration proceeding under the [Outokumpu-Fives Contracts], [Fives] shall have the right to join the other PARTY into the arbitration proceedings with [Outokumpu] and the PARTY so *1322 joined hereby agrees that it shall be bound by the arbitral award, as long as the latter is given the opportunity to defend its interest in the arbitration procedure held under the [Outokumpu-Fives Contracts].
Under the Consortial Agreement, Fives was designated the "Leading Party" of the consortium and was tasked with representing the interests of the consortium.
II. THE DISTRICT COURT PROCEEDINGS
When Outokumpu was unable to resolve the issues related to the motors with GE Energy, Outokumpu and its insurers filed suit in the Circuit Court of Mobile, Alabama on June 10, 2016. GE Energy timely removed based on federal subject matter jurisdiction under
As to the motion to remand, the district court, adopting the magistrate's report and recommendation, found removal proper under the New York Convention and the Federal Arbitration Act ("FAA") since this case "relates to" the arbitration agreement found in the Outokumpu-Fives Contracts and that arbitration agreement "fall[s] under the Convention." As to the motion to compel arbitration, the district court found that each of the four jurisdictional prerequisites under Bautista was met and no affirmative defense applied. Specifically, as to the first prerequisite, the district court found there was an "agreement in writing," signed by the Outokumpu and GE Energy, since Outokumpu signed the Contracts and GE Energy, as a sub-contractor, was not expressly excluded from the arbitration provision. The second prerequisite was not contested by the parties. As to the third and fourth prerequisite, the district court found that the arbitration agreement arose out of a legal commercial relationship between Outokumpu and Fives and that that relationship had some reasonable relationship with a foreign state. Accordingly, the district court granted the motion to compel and dismissed the action.
III. STANDARD OF REVIEW
We review
de novo
both the district court's denial of the motion to remand and the district court's grant of the motion to compel arbitration and dismiss.
Escobar v. Celebration Cruise Operator, Inc.
,
IV. THE MOTION TO REMAND
Federal policy favors arbitral dispute resolution.
Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth, Inc.
,
In amending the FAA, Congress further sought to promote the development of a uniform body of federal law under the Convention.
Beiser v. Weyler
,
The phrase "falling under the convention" is defined in Section 202:
An arbitration agreement or arbitral award arising out of a legal relationship, whether contractual or not, which is considered as commercial, including a transaction, contract, or agreement described in section 2 of this title, falls under the Convention. An agreement or award arising out of such a relationship which is entirely between citizens of the United States shall be deemed not to fall under the Convention unless that relationship involves property located abroad, envisages performance or enforcement abroad, or has some other reasonable relation with one or more foreign states.
Our sister circuits, however, have had occasion to interpret this phrase. In
Beiser
, a consulting company's principal sued in his individual capacity regarding an oil investment.
Both the Eighth and Ninth Circuits have followed the Fifth Circuit.
Reid v. Doe Run Res. Corp.
,
We join the Fifth, Eighth, and Ninth Circuits and agree that the "relates to" language of Section 205 provides for broad removability of cases to federal court. While the link between the arbitration agreement and the dispute is not boundless, the arbitration agreement need only be sufficiently related to the dispute such that it conceivably affects the outcome of the case. Thus, as long as the argument that the case "relates to" the arbitration agreement is not immaterial, *1324 frivolous, or made solely to obtain jurisdiction, the relatedness requirement is met for purposes of federal subject matter jurisdiction.
This initial jurisdictional inquiry is distinct from a determination of whether the parties are bound to arbitrate.
Bautista v. Star Cruises
,
Accordingly, upon removal the district court shall engage in a two-step inquiry to determine jurisdiction, limiting its examination to the pleadings and the removal notice.
The district court held that Outokumpu's claims relate to an arbitration agreement falling under the Convention. The parties concede that the second and third Bautista factors are met, and thus we need only examine the first and fourth factors. As to the first factor, GE Energy has identified the arbitration clauses in the Outokumpu-Fives Contracts. Because the Contracts are signed by Outokumpu and Fives, the Contracts satisfy the first factor.
As to the fourth factor, on the face of the complaint and removal notice, the Outokumpu-Fives Contracts govern a commercial relationship that has a reasonable relation to one or more foreign states. The Contracts contemplate performance by certain foreign subcontractors in foreign states. Moreover, the initial negotiations regarding the Outokumpu-Fives Contracts occurred in Germany. While these arguments may not prevail on a motion to compel arbitration between the parties before the district court, they are sufficient to meet GE Energy's burden opposing remand.
*1325 And this lawsuit sufficiently "relates to" the arbitration agreement in the Outokumpu-Fives Contracts. As alleged in the pleadings, the present lawsuit against GE Energy concerns the performance of the Outokumpu-Fives Contracts, and the arbitration agreement contained in those Contracts is sufficiently related to the instant dispute such that it could conceivably affect the outcome of this case.
This approach is consistent with our removal jurisprudence, which confines its analysis to the face of the pleadings.
Bautista
,
V. THE MOTION TO COMPEL ARBITRATION
Having found that the district court properly exercised jurisdiction, we now turn to the question of whether Outokumpu may be compelled to arbitrate its dispute with GE Energy. Under
Again, a party may compel arbitration under the Convention only if:
(1) there is an agreement in writing within the meaning of the Convention; (2) the agreement provides for arbitration in the territory of a signatory of the Convention; (3) the agreement arises out of a legal relationship, whether contractual or not, which is considered commercial; and (4) a party to the agreement is not an American citizen, or that the commercial relationship has some reasonable relation with one or more foreign states.
Bautista
,
The district court determined that GE Energy and Outokumpu were parties to the Contracts by tracing the definitions of "Buyer" and "Seller," which included subcontractors unless explicitly stated otherwise, and the definition of "parties" as "Buyer" and "Seller." Inserting these definitions into the arbitration clause, the district court found that there was an agreement in writing under the meaning of the Convention which required Outokumpu and GE Energy to arbitrate.
However, GE Energy is undeniably not a signatory to the Contracts. At the time the Contracts were signed by Outokumpu and Fives, GE Energy was a stranger to the Contracts and, at most, a potential subcontractor. Private parties-here Outokumpu and Fives-cannot contract around the Convention's requirement that the parties
actually sign
an agreement to arbitrate their disputes in order to compel arbitration. New York Convention, Article II, ¶ 1;
see also
Czarina, L.L.C. v. W.F. Poe Syndicate
,
This requirement is consistent with our prior decisions. In
Czarina
,
The fact that non-signatory GE Energy, and not signatory Outokumpu, seeks to enforce the arbitration provision does not alter our analysis. While the FAA "places arbitration agreements on equal footing with all other contracts and sets forth a clear presumption-'a national policy'-in favor of arbitration,"
Parnell v.CashCall, Inc.
,
GE Energy's argument that it may compel arbitration based on the Consortial Agreement fares no better. Even if GE Energy had agreed with Fives and the third subcontractor DMS that it would arbitrate any disputes arising out of the Consortial Agreement or the Contracts, or that GE Energy would be bound to any arbitration agreement in the Contracts, these agreements were entered into unbeknownst to Outokumpu. GE Energy's unilateral acquiescence to arbitrate with Outokumpu is not an agreement "signed by [ ] parties" Outokumpu and GE Energy. And though the Consortial Agreement may have established that Fives could act as an agent of GE Energy in its dealings with Outokumpu, Fives did not become GE Energy's agent until after Fives and Outokumpu had already signed the Outokumpu-Fives Contracts. As such, Fives did not sign the Contracts on behalf of GE Energy as GE Energy's agent. Altogether, in the absence of a signed agreement, Outokumpu cannot be compelled to arbitrate its dispute with GE Energy under the Convention.
In its supplemental briefing on appeal, GE Energy raises for the first time the argument that it is entitled to compel arbitration under Chapter 1 of the FAA. This issue was not raised before the district court and was not presented in the parties' initial appellate briefing. Accordingly, we decline to consider it now.
VI. MOTION FOR LIMITED DISCOVERY
Outokumpu also appeals the district court's denial of its motion for limited discovery into the corporate relationship between GE Energy, Converteam, and the Consortial Agreement. "[A] district court is allowed a range of choice in such matters, and we will not second-guess the district court's actions unless they reflect a clear error of judgment."
Holloman v. Mail-Well Corp.
,
VII. CONCLUSION
Based on the foregoing, we AFFIRM the district court's denial of the motion to remand and denial of limited discovery, but REVERSE and REMAND the district court's order compelling arbitration for further proceedings consistent with this opinion.
SO ORDERED.
Nothing in this opinion disturbs our holdings that an arbitration agreement is "signed by the parties" when signed by a party's privy or incorporated by reference in an arbitration agreement.
Bautista v. Star Cruises
,
Reference
- Full Case Name
- OUTOKUMPU STAINLESS USA, LLC, Sompo Japan Insurance Company of America, as Subrogee of Outokumpu Stainless USA, LLC, Pohjola Insurance Limited, Aigel Europe Limited, as Subrogee of Outokumpu Oyj, Tapiola General Mutual Insurance Company, as Subrogee of Outokumpu Oyj, AXA Corporate Solutions Assurance SA UK Branch, as Subrogee of Outokumpu Oyi, HDI Gerling UK Branch, as Subrogee of Outokumpu Oyj, MSI Corporate Capital LTD., as Sole Corporate Member of Syndicate 3210, as Subrogee of Outokumpu Oyj, Royal & Sun Alliance, PLC, as Subrogee of Outokumpu Oyj, Plaintiffs - Appellants, Sompo Japan Insurance Company of America, Et Al., Plaintiffs, v. CONVERTEAM SAS, a Foreign Corporation Now Known as GE Energy Power Conversion France SAS, Corp., Defendant - Appellee
- Cited By
- 24 cases
- Status
- Published