Ernst v. Fidelity & Deposit Co. of Maryland
Opinion of the Court
This is an appeal from a decree of the District Court for the Southern District of New York for $50,000 in favor of the plaintiff, as trustee in bankruptcy of the McCord Contracting
The defendant, the Fidelity & Deposit Company, a corporation of the state of Maryland, agreed to give the bond, provided the $300,000 of bonds were deposited with it, to be delivered to McCord in payment for work done at 85 per cent, of their par value upon certificates of the ráilway company’s chief engineer, and provided, also, that $50,000 in cash be deposited with it as an indemnity against any loss under the bond. On the same day, to carry out the negotiation, the railway company advanced $70,000 in cash to McCord, and delivered to him $120,-000 of its capital stock and $300,000 of its first mortgage bonds. Fie deposited the bonds with the surety company, accompanied by a letter directing it to deliver the same in the manner above stated, any bonds remaining after the completion of the road to be delivered to the railway company. This letter will be called Exhibit B. At the same time McCord paid $50,000 to the McCord Contracting Company, which immediately deposited the same with-the surety company as collateral, to be returned, so far as not needed as indemnity, to it, in accordance with the terms of an indemnity bond executed by it to the surety company. This bond will be called Exhibit C.
On the same day the surety company delivered its bond in the sum of $80,000 to the railway company. This bond will be called Exhibit D.
On the same day McCord and the railway company entered into an agreement, of which the surety company had no notice, which ratified and confirmed Exhibit A, recited the advance by the railway company to McCord of $70,000, and the deposit of the $300,000 of bonds with the surety company as above stated. This' contract will be called Exhibit E. Article 4 reads as follows:
“Fourth. It is mutually understood and agreed that, upon the completion of the undertaking of the contractor under the said construction contract, a statement shall be rendered by the contractor to the company, showing the actual cost of all labor, materials, and incidentals entering into and pertaining to the cost of the construction and equipment of the said part of the company's railroad, to which shall be added a profit to the contractor of fifteen per cent. (15%). The sum thus arrived at shall be taken as the actual cost of the construction and equipment of said part of said railway.
“From the cost of said part of said railway, arrived at in the manner stated, the contractor shall deduct the sum of seventy thousand dollars ($70,000), and for the remainder of said cost the contractor shall retain a sufficient amount of the first mortgage bonds of the company which, at 85% of the par value thereof shall equal the said remainder of construction cost, and all other first mortgage bonds of the company shall be forthwith returned to the company, or delivered upon its order.”
The surety company thereupon did complete contract Exhibit A to the entire satisfaction of the railway company. March 24, 1913, the plaintiff, as trustee in bankruptcy, began this suit to recover the $50,000 deposited from the surety company. The surety company having moved to dismiss the complaint, Judge Noyes held that it had made a new and different contract from Exhibit A in Exhibit H, and so had discharged the McCord Company, its indemnitor, and lost its right to retain the $50,000 deposited with it. He said:
“As already shown, the real contract between the parties was that contained in Exhibit A, as changed by Exhibit E. This is recognized expressly in Exhibit H. Under this modified contract payment was — as we have seen— to be made on a cost and percentage basis. But under the agreement, Exhibit H, by which the defendant undertook to complete the work, the performance of Exhibit E was waived, and the defendant agreed to do the work for a fixed price, viz., 515,000 in stock and $300,000 in bonds. This in my opinion was a new and independent contract. I am unable to reach any other conclusion than that Exhibit A was modified by -Exhibit E, and that Exhibit E was none the less modified by Exhibit H, because the provisions of the last agreement approximated those of the first.”
At final hearing Judge Mayer, following this view, entered judgment in favor of the complainant.
The decree is reversed, with costs, and without prejudice to further proceedings in accordance with this opinion.
Reference
- Full Case Name
- ERNST v. FIDELITY & DEPOSIT CO. OF MARYLAND
- Status
- Published