City of New York v. Third Nat. Bank
City of New York v. Third Nat. Bank
Opinion of the Court
The Waterfront Improvement Company had a contract for five years with the city 'of New York for furnishing scows and carrying away ashes and street sweepings. By its terms the company was to be paid monthly 90 per cent, of the prices specified for work done during the preceding month. Certificates of the amount of such work were to be given by the department of street cleaning on the 5th day of the month ensuing that in which the work was done and payment of the 90 per cent, was to be made 10 days thereafter: The remaining 10 per cent, was to be paid within 30 days after December 31st of the year in which work was done.
The Third National Bank held assignments of moneys earned by the contractor for the months of January, February, March, and April, 1911. That work was done during those months is not disputed. Certificates of the amount of work done, and of amount due for each of these months were signed by the commissioner of street cleaning on May 24, 1911, for January, February, and March, and on June 15, 1911, for April. The first three of these certificates were dated February 1st,- March 1st, and April 1st, and the fourth April 13th. _
_ Plaintiff brought suit to recover for the work done between January 1 and April 13, 1911, on which latter date the contractor was put off the work by the city. There seems to be no conflict as to the amounts claimed; the defense being delay by the contractor and consequent abrogation of the contract by the city under a clause of the contract numbered O. After having terminated the contract the city procured the work to be done elsewhere at a greatly increased expense, which exceeded the amounts at contract prices of the work done by the contractor between January 1st and April 13th.
“(O) If the work to be done under this contract shall be abandoned by the contractor, or if this contract shall be assigned, or the work sublet by him, otherwise than is herein specified, or if at any time the superintendent shall*177 be of the opinion and shall so certify in writing to the commissioner that the performance of the contract is unnecessarily or unreasonably delayed, or that the contractor is willfully violating any of the conditions or covenants of this contract, or specifications, or is executing the same in bad faith, or not in accordance with the terms thereof, the commissioner shall have the power to notify the contractor to discontinue all work, or any part thereof, under this contract, by a written notice to be served upon the contractor, either personally or by leaving said notice at his residence, or with his agent in charge of the work, or with any employe found on the work, and thereupon the contractor shall discontinue the work, or such part thereof as the commissioner shall designate, and the commissioner shall thereupon have the power and is hereby authorized to procure in the manner prescribed by law such and so much of the work to be performed as may be necessary to fulfill this contract, and to charge the costs and expenses thereof to the contractor and the costs and expenses so charged shall be deducted and paid by the city out of such moneys as may be due or may at any time thereafter grow due to the contractor under and by virtue of this contract; and in case such costs and expenses shall exceed the amount which would have been payable under the contract if the same had been completed by the contractor, then the contractor shall and will pay the amount of such excess to the city; and in case such costs and expenses shall be less than the sum which would have been payable under this contract if the same had been completed by the contractor, then the contractor shall forfeit all claim to the difference.”
Certificates in the form prescribed by this clause, signed by the superintendent and by the commissioner of street cleaning, were put in evidence, and it was contended by the defendant that as a consequence the contract was discontinued and moneys earned under it forfeited.
Judgment affirmed.
Reference
- Full Case Name
- CITY OF NEW YORK v. THIRD NAT. BANK OF JERSEY CITY
- Cited By
- 2 cases
- Status
- Published
- Syllabus
- 1. Trial 177—Directed Verdict—Effect. Where both parties moved for a directed verdict, all controverted issues of fact are conclusively determined in favor of that party for whom the verdict was directed. [Ed. Note.—For other cases, see Trial, Cent. Dig. § 400; Dec. Dig. 177. Operation and effect of motions by both plaintiff and defendant for direction of verdict, see note to Bare v. Scatcherd, 77 C. C. A. 8.] 2. Municipal Corporations 364—Improvements—Contracts—Forfeiture —Breach by Other Party. Where a city had failed to observe the requirements of the contract for payments to be made toithe contractor on certain dates, it could not avail itself of the right given it by the contract to declare it forfeited for delinquency by the contractor. [Ed. Note.—For other cases, see Municipal Corporations, Cent. Dig. § 897; Dec. Dig. 364.] 3. Municipal Corporations 364—Contracts—Forfeiture—Breach by Other Party—Excuse. The fact that the statutes regulating the payment of money by the city were such that the payments could not he made within the time called for by tbe contract, while it might relieve the city from liability for damages for the delay, does not excuse its breach, so as to entitle it to enforce the forfeiture provision against the contractor. [Ed. Note.—For other cases, see Municipal Corporations, Cent. Dig. § 897; Dec. Dig. 364.] 4. Municipal Corporations 374—Contracts—Modification—Course of Business. The fact that a contractor had for several years past received payment from the city on his contracts at dates later than-those provided in the contracts does not show a course of business modifying the contract, where there was evidence that the contractor frequently urged the city authorities to make the payments more promptly, as he needed the money to perform his contract. [Ed. Note.—Ifor other cases, see Municipal Corporations, Cent Dig. §§ 905, 910; Dec. Dig. 374.] 5. Municipal Corporations 373—Improvements—Liens for Labor and Materials—Priority—Assignments. Liens claimed for labor and materials furnished to a city contractor are subject to assignments of amounts due under the contract, which were filed before the lien claims. [Ed. Note.—For other cases, see Municipal Corporations, Cent. Dig. § 913; Dec. Dig. 373.] 6. Municipal Corporations 374—Contracts—Actions for Breach— Pleading- Liens. A city must specially plead a provision of the contract authorizing it to retain money to pay liens, if it intends to rely thereon as a defense to an action on the contract. [Ed. Note.—For other cases, see Municipal Corporations, Cent. Dig. §§ 905, 910; Dee. Dig. 374.] I