American Mfg. Co. v. United States Shipping Board Emergency Fleet Corp.
Cases that cite this one
55 later published cases cite this decision. The 25 that cite it most often are listed here.
- Armco Steel Corp. v. Isaacson Structural Steel Co. (Alaska 1980)
- Patane v. Nestle Waters North America, Inc. (United States District Court for the District of Connecticut 2025)
- James Bunn v. Navistar, Inc. (6th Cir. 2020)
- O'Connor v. Ford Motor Company (District Court, N.D. Illinois 2020)
- Exim Brickell LLC v. PDVSA Services Inc. (11th Cir. 2013)
- Connick v. Suzuki Motor Co., Ltd. (Ill. 1996)
- K & M Joint Venture v. Smith International, Inc. (6th Cir. 1982)
- Sherkate Sahami Khass Rapol v. Henry R. Jahn & Son, Inc. (District Court, S.D. New York 1982)
- In re Gotham Silver Co. (District Court, S.D. New York 1950)
- Whitfield v. Jessup (Cal. 1948)
- Silvera v. Broadway Department Store, Inc. (United States District Court for the Southern District of California 1940)
- Dart Transit Company v. Paccar, Inc. (D. Minn. 2025)
- Merritt v. Target Corporation (District Court, E.D. Missouri 2025)
- Gibson v. Albertsons Companies, Inc. (District Court, N.D. Illinois 2024)
- Adams v. Jackson (District Court, E.D. Washington 2024)
- Hellige v. Wal-Mart, Inc. (District Court, S.D. Illinois 2023)
- Cerretti v. Whole Foods Market Group, Inc. (District Court, N.D. Illinois 2022)
- Kinman v. The Kroger Co. (District Court, N.D. Illinois 2022)
- Smith-Brown v. Ulta Beauty, Inc. (District Court, N.D. Illinois 2019)
- Parrott v. Family Dollar, Inc. (District Court, N.D. Illinois 2019)
- Podpeskar v. Makita U.S.A. Inc. (D. Minn. 2017)
- Valley Air Service v. Southaire, I (7th Cir. 2011)
- Valley Air Service, Inc. v. Southaire, Inc. (7th Cir. 2011)
- Daigle v. Ford Motor Co. (D. Minn. 2010)
- Drobnak v. Andersen Corp. (8th Cir. 2009)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion
This was an ac-_ tion at law upon a contract for the sale of about 800 tons of steel framing, anchor bolts, and reinforcing rods at $60 a ton, and for certain steel sash at a gross sum of $3,200. The contract was made by correspondence and specified no date for delivery, but the plaintiff, who was the buyer, had made known its immediate use for the articles sold. The contract was concluded on December 1, 1919, and the plaintiff paid the full purchase price at once. The defendant was remiss in making delivery; the location of the steel being in fact unknown, although the contract called for delivery f. o. b. at the “present location” of the goods, which was specified. It turned out that they were not at the places supposed, and a long delay ensued. During this time the plaintiff sent out an assistant to find the steel, which eventually was in part discovered in California. Although the plaintiff had sent shipping instructions on December 8, 1919, the material was not finally delivered until October 20, 1920, at which time it was accepted. At no time, either at or before acceptance, or until the action was brought on February 19, 1921, did the plaintiff mako any claim for delay in delivery. The defendant never delivered the steel sash at all.
The action was for special damages for the delay in delivery, and the expense of sending to California, and also for the market price of the sash. At the trial the District Judge allowed the plaintiff to recover, not for the market price of the sash, which it proved, but only for the price paid, $3,200. He also refused to allow any damages for the delay, except the sums expended in tracing the goods. The plaintiff took out this writ, because it had not been allowed these amounts.
The District Judge erred in the measure of damages upon the steel sash. The case is the usual one in which the buyer’s damages are the difference between market value and the contract price. We are not altogether clear on what theory a different rule was adopted. The ease of Western Union Telegraph Co. v. Hall, 124 U. S. 444, 8 S. Ct, 577, 31 L. Ed. 479, on which the defense now relies, is not in point. It concerned damages recoverable for a failure to send a telegram ordering the purchase of stock. The plaintiff tried to recover for the rise in value of the stock on the next day, and this was refused, on the theory that the plaintiff could not show that he would have sold at the higher price. The court recognized the usual rule, which is so well settled both by decision and statute that it seems to us unnecessary to do more than refer to it. As the plaintiff proved the market *566 value of the sash, it should have been allowed so much.
The larger part of the damages claimed was for the delay in delivery. We shall assume that delivery was due within a reasonable time, no time being mentioned, and that the delivery was too late. Even so, it is now settled by statute (section 130, Personal Property Law N. Y. [Consol. Laws, c. 41]) that acceptance of the goods bars any recovery “for breach of any promise * * * in the contract to sell or the sale,” unless the buyer shall “give notice to the seller of the breach * *' * within a reasonable time after the buyer knows * * * of such breach.” Delay in delivery, of course, is a breach, and the plaintiff was obliged to give notice within a reasonable time after October 20, 1920.' It did nothing till February 19,1921, and four months is more than a reasonable time, as the District Court correctly held.
The plaintiff replies that the buyer is not required to give notice of what the seller already knows, but this confuses two quite different things. The notice “of the breach” required is .not of the facts, which the seller presumably knows quite as well as, if not better than, the buyer, but of buyer’s claim that they constitute a breach. The purpose of the notice is to advise the seller that he must meet a claim for damages, as to which, rightly or wrongly, the law requires that he shall have early warning.
The Court of Appeals of New York, in Henderson, etc., Co. v. P. K. Wilson & Son, 235 N. Y. 489, 139 N. E. 583, has so ruled under this section of the act, and there-seems to us no room for doubt. We do not find it necessary to decide whether that decisi.on is conclusive upon us, though it construed a New York statute. The rule of compulsory conformity in such eases perhaps does not apply to a statute codifying a-part of the commercial law, as to which we in general follow our own notions;
'Nor do we decide whether the plaintiff might recover damages for delay in any event. Its contention is that, as it had advised the defendant that it had immediate use for the steel frames, its losses due to delays in the erection of its factory were within the contemplation of the parties. Finally, we say nothing as to the allowance for the expenses of sending a representative to California to hunt up the goods. On what theory this was granted we are not advised, but, as the defendant does not challenge it, its propriety is not before us.
The “order” directing the writ of error to issue has nothing to do with the scope of our review. It is the writ which brings the whole record into this court. The extent of our review is determined by the assignments of error, and the petition for the writ, together with its allowance (no order is proper), are merely means to secure the initial process, which is the writ itself.
Judgment reversed.