Coalition for Responsible Growth & Resource Conservation v. United States Federal Energy Regulatory Commission

U.S. Court of Appeals for the Second Circuit
Coalition for Responsible Growth & Resource Conservation v. United States Federal Energy Regulatory Commission, 485 F. App'x 472 (2d Cir. 2012)

Coalition for Responsible Growth & Resource Conservation v. United States Federal Energy Regulatory Commission

Opinion

SUMMARY ORDER

We assume the parties’ familiarity with the facts and procedural history, which we reference only as necessary to explain our decision to deny the petition.

Petitioners Coalition for Responsible Growth and Resource Conservation, Damascus Citizens for Sustainability, and Sierra Club (collectively, the “Coalition”) seek review of: (1) a Certificate of Public Convenience and Necessity (the “Certificate Order”) granted by FERC pursuant to Section 7(c) of the Natural Gas Act, 15 *474 U.S.C. § 717f(c), to the Central New York Oil and Gas Company (“Central NY Oil”) and (2) an order denying the Coalition’s Request for Rehearing of the Certifícate Order (the “Rehearing Order”).

The Certifícate Order authorizes Central NY Oil to build and operate the MARC I Hub Line Project natural gas pipeline-39 miles long and 30 inches in diameter-to run through Bradford, Sullivan, and Lycoming Counties, Pennsylvania, and to build and operate related facilities.

Under the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321-4347, a federal agency proposing a “major Federal action[ ] significantly affecting the quality of the human environment” must prepare a detailed statement about the environmental impact of the proposed action-an environmental impact statement (“EIS”). 42 U.S.C. § 4332(2)(C)(i); Nat’l Audubon Soc’y v. Hoffman, 132 F.3d 7, 12 (2d Cir. 1997). If an agency is uncertain as to whether the action requires an EIS, it must prepare an environmental assessment (“EA”) that [“bjriefly provide[s] sufficient evidence and analysis for determining whether to prepare an [EIS].” 40 C.F.R. §§ 1501.3, 1508.9(a)(1). If the agency finds that an EIS is not necessary, the agency will issue a finding of no significant impact (“FONSI”). 40 C.F.R. § 1508.9(a)(1).

In reviewing a decision whether to issue an EIS, this Court must consider: (1) “whether the agency took a ‘hard look’ at the possible effects of the proposed action” and (2) if the agency has taken a “hard look,” whether “the agency’s decision was arbitrary or capricious.” Nat’l Audubon Soc’y, 132 F.3d at 14; see also 5 U.S.C. § 706(2)(A) (court may set aside an agency’s decision not to require an EIS only upon a showing that it was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law”). Under NEPA, this Court’s role is to “insure that the agency considered the environmental consequences” of the federal action at issue. Town of Orangetown v. Gorsuch, 718 F.2d 29, 35 (2d Cir. 1983) (citation omitted); see also Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 351, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989) (“NEPA merely prohibits uninformed-rather than unwise-agency action”).

Here, in considering Central NY Oil’s application, FERC prepared an EA, issued a FONSI, and concluded that an EIS was not required. We conclude, based on our review of the administrative record, that FERC took a “hard look” at the possible effects of the Project and that its decision that an EIS was not required was not arbitrary or capricious. Its 296-page EA thoroughly considered the issues. The Certificate Order carefully reviewed the concerns raised by the comments. The Rehearing Order addressed petitioners’ concerns and further explained FERC’s basis for issuing the FONSI.

The Coalition argues that FERC’s cumulative impact analysis was inadequate. We disagree. FERC’s analysis of the development of the Marcellus Shale natural gas reserves was sufficient. FERC included a short discussion of Mar-cellus Shale development in the EA, and FERC reasonably concluded that the impacts of that development are not sufficiently causally-related to the project to warrant a more in-depth analysis. In addition, FERC’s discussion of the incremental effects of the project on forests and migratory birds was sufficient. FERC addressed both issues in the EA and has required Central NY Oil to take concrete steps to address environmental concerns raised by petitioners and others. For example, in the Certificate Order, FERC required Central NY Oil to comply with its Riparian Forested Buffer Enhancement Plan to address forest fragmentation. In *475 Environmental Condition 17 of the EA, FERC required Central NY Oil to prepare and execute a Migratory Bird Impact Assessment and Habitat Restoration Plan. The environmental concerns identified by commenting parties, including the Environmental Protection Agency, were considered and addressed by FERC in the EA and the Rehearing Order.

Accordingly, we hold that FERC properly discharged its responsibilities under NEPA. We have considered all of petitioners’ remaining arguments and conclude that they are without merit. The petition for review is DENIED.

Reference

Full Case Name
COALITION FOR RESPONSIBLE GROWTH AND RESOURCE CONSERVATION, Damascus Citizens for Sustainability, and Sierra Club, Petitioners, v. UNITED STATES FEDERAL ENERGY REGULATORY COMMISSION, Respondent, Central New York Oil and Gas Company, Intervenor
Cited By
2 cases
Status
Unpublished