Opinion

SUMMARY ORDER

Plaintiff-appellant Edith Richmond (“plaintiff’) brought this action against defendants U.S. Energy Savings d/b/a Just Energy of New York (“Just Energy”) and Brooklyn Union Gas Company d/b/a National Grid N.Y. (“National Grid”). Plaintiff asserted the same six claims against both entities, seeking damages arising from her natural gas supply agreement with Just Energy, which was later transferred to National Grid. On April 19, 2012, National Grid moved to dismiss plaintiffs claims against it pursuant to Rules 12(b)(6) and 9(b) of the Federal Rules of Civil Procedure. Rather than moving to dis *16 miss the claims asserted against it, Just Energy answered plaintiff’s complaint on June 8, 2012. The District Court granted National Grid’s motion in its entirety on March 29, 2013, dismissing all claims against National Grid. See Richmond v. Nat’l Grid, No. 12-cv-1319, 2013 WL 1338870 (E.D.N.Y. Mar. 29, 2013). In a text order accompanying the written ruling, the District Court made clear that “this action is dismissed as to defendant National Grid ONLY” and that “[t]his action shall continue as to the remaining defendant.” Joint App’x 5. On April 29, 2013, plaintiff filed a notice of appeal as to the District Court’s grant of National Grid’s motion to dismiss.

As relevant here, our appellate jurisdiction is limited to review of final judgments, see 28 U.S.C. § 1291, 3 clarified by Rule 54(b) of the Federal Rules of Civil Procedure. 4 We have explained that Rule 54(b) sets out the requirements for the entry of a partial final judgment in multi-party actions. A final judgment may be entered as to some — but fewer than all — parties “only if the court expressly determines that there is no just reason for delay.” Fed. R.Civ.P. 54(b). The Rule makes clear that if the District Court does not both direct entry of judgment and expressly determine that there is no just reason for delay, then its order or decision is not final, whether or not it is labeled a “judgment.” HBE Leasing Corp. v. Frank, 48 F.3d 623, 631-32 (2d Cir. 1995) (“The requirement of an express determination cannot be met if the District Court does not make clear that such determination is for the purpose of certifying a final judgment [under Rule 54(b)].”).

In this case, the District Court did not direct the entry of judgment as to National Grid, but merely granted National Grid’s motion to dismiss all claims against it. In fact, proceedings in this action have been ongoing against Just Energy since plaintiff filed her notice of appeal. Although the District Court directed the clerk to terminate National Grid on the docket, the order does not mention Rule 54(b), much less provide a certification “accompanied by a reasoned ... explanation of the basis for the court’s determination that there is no just cause for delay,” L.B. Foster Co. v. Am. Piles, Inc., 138 F.3d 81, 86 (2d Cir. 1998). Such an order does not amount to the express determination required under Rule 54(b). See HBE Leasing, 48 F.3d at 631 (“[T]here is simply no evidence that the District Court intended its ruling ... to constitute a Rule 54(b) certification.”).

Accordingly, we must dismiss this appeal for lack of jurisdiction. Should the plaintiff so choose, she may file a motion in the District Court requesting the appropriate certification under Rule 54(b) and, if granted, reinstate her appeal. 5 Cf. In re *17 Chateaugay Corp., 922 F.2d 86, 91-92 (2d Cir. 1990).

CONCLUSION

For the foregoing reasons, this appeal is DISMISSED for lack of appellate jurisdiction.

3

. 28 U.S.C. § 1291 provides, in relevant part: "The courts of appeals ... shall have jurisdiction of appeals from all final decisions of the district courts of the United States.”

4

. Rule 54(b) provides, in full:

When an action presents more than one claim for relief — whether as a claim, counterclaim, crossclaim, or third-party claim— or when multiple parties are involved, the court may direct entry of a final judgment as to one or more, but fewer than all, claims or parties only if the court expressly determines that there is no just reason for
delay. Otherwise, any order or other decision, however designated, that adjudicates fewer than all the claims or the rights and liabilities of fewer than all the parties does not end the action as to any of the claims or parties and may be revised at any time before the entry of a judgment adjudicating all the claims and all the parties’ rights and liabilities.
5

.We in no way intimate that such a certification would necessarily be valid. We have long held that district courts "should not, as a general matter, direct the entry of a final *17 judgment pursuant to Rule 54(b) if the same or closely related issues remain to be litigated against the undismissed defendants.” Hogan v. Consol. Rail Corp., 961 F.2d 1021, 1025 (2d Cir. 1992).