Clearlake Shipping PTE Ltd. v. NuStar Energy Services, Inc.
Opinion
Interpleader defendant NuStar Energy Services, Inc. ("NuStar"), a physical supplier of marine fuel ("bunkers") to two vessels time-chartered by interpleader plaintiff Clearlake Shipping PTE Ltd. ("Clearlake"), appeals from orders and an April 18, 2017 partial final judgment of the United States District Court for the Southern District of New York, Valerie E. Caproni,
Judge
, denying NuStar's motion for summary judgment and dismissing its claims to maritime liens against the vessels. The district court ruled that, under the Commercial Instruments and Maritime Liens Act ("CIMLA"),
I. BACKGROUND
This case is one of the many resulting from the financial collapse of O.W. Bunker & Trading A/S ("O.W. Denmark") and its subsidiaries and affiliates (collectively the "O.W. Bunker Group"), an international operation that both supplied bunkers to ships and arranged the supply of bunkers by others.
See generally
Temara
,
In October 2014, Clearlake, charterer of the M/V HELLAS GLORY and the M/V VENUS GLORY (collectively the "Vessels"), acting through its agent AS Tarcona ("Tarcona"), placed orders for fuel bunkers for the Vessels with O.W. Bunker (Switzerland) SA ("O.W. Switzerland"). O.W. Switzerland, in turn, issued purchase orders to its affiliate O.W. Bunker USA, Inc. ("O.W. USA"). O.W. USA then issued purchase orders to NuStar. Local agents for the Vessels coordinated the deliveries by NuStar. In late October, NuStar delivered the ordered bunkers to the Vessels.
NuStar did not directly contract with Clearlake or with O.W. Switzerland. In early November 2014, NuStar invoiced O.W. USA for the bunkers; O.W. USA invoiced O.W. Switzerland; O.W. Switzerland invoiced Clearlake. On November 7, O.W. Denmark filed for bankruptcy; bankruptcy filings by other members of the O.W. Bunker Group followed. Neither NuStar nor any O.W. Bunker Group entity has been paid for NuStar's bunker deliveries to Clearlake's Vessels.
Clearlake brought the present interpleader action against NuStar, O.W. Switzerland, O.W. USA, and others. In the district court, this case and three others-one other involving NuStar and two involving U.S. Oil Trading LLC ("USOT")-were selected to serve as test cases for the efficient resolution of the various in rem claims. Following coordinated discovery, and summary judgment motions by NuStar, USOT, and O.W. Bunker entities that had dealt with the vessels' owners or charterers, the district court addressed these four cases in its opinion in Clearlake .
The court stated that maritime liens arise exclusively under CIMLA, that such liens are construed narrowly under the doctrine of
stricti juris
, and that CIMLA "typically require[s]" a finding of "a direct contractual or agency nexus between the supplier and the vessel or its agents."
Clearlake
,
Adverting to an exception to that general rule, the court noted that "'[a]n owner can still become responsible for the services of a subcontractor, if the owner has ordered the general contractor to retain that subcontractor,'"
id
. at 687 (quoting
Port of Portland v. M/V PARALLA
,
Accordingly, the district court denied NuStar's motion for summary judgment *650 and effectively granted summary judgment against NuStar on its maritime-lien claims against Clearlake, entering a partial final judgment dismissing those claims.
II. DISCUSSION
On appeal, NuStar contends principally that it was entitled to maritime liens against the Clearlake Vessels in light of CIMLA's plain text and purpose and as a matter of equity, regardless of a lack of contractual privity between NuStar and Clearlake or its agent. We reject these contentions substantially for the reasons stated by the district court in Clearlake .
We see no error in the district court's interpretation of CIMLA or its ruling that maritime liens may not properly be granted based on principles of equity. NuStar's contentions as to the proper interpretation of CIMLA are foreclosed by our recent decision in
Temara
, which involved events not substantially dissimilar to those here.
See generally
Nor do we see any error in the district court's conclusion that the exception to the general rule against a subcontractor's entitlement to a maritime lien did not apply to NuStar. As discussed in USOT ,
a subcontractor is not entitled to assert a maritime lien " unless it can be shown that an entity authorized to bind the ship controlled the selection of the subcontractor and/or its performance ."
"The sole exception to the rule against the subcontractor lien will occur where the subcontractor has been engaged by a general contractor in circumstances where the general contractor was acting as an agent at the direction of the owner to engage specific subcontractors " ....
USOT
,
As indicated in
Temara
and our other recent decisions in appeals involving fuel suppliers and O.W. Bunker Group entities, a subcontractor is not allowed to assert a maritime lien "without any indication that
a statutorily-authorized entity provided direction
" that that subcontractor be used.
Temara
,
*651 evidence that a statutorily authorized person controlled the selection of Chemoil as the physical supplier " (emphases added) ).
Thus, the subcontractor exception does not apply where there is no significant evidence "that the owner intended that [the physical supplier] be engaged as a subcontractor."
Farwest
,
Insofar as NuStar was concerned, the district court correctly applied these principles in Clearlake to conclude that NuStar did not fall within the subcontractor exception. The court viewed the record as showing
- that NuStar " d [ id ] not argue that the [ Clearlake/Tarcona] contracts required O.W. to use [NuStar] as supplier[ ],"239 F.Supp.3d at 688 n.11 (emphases added);
- that there was " no evidence that [Clearlake or Tarcona] required O.W. to use [NuStar] to satisfy its obligations," id . at 688 (emphases added);
- that, although "aware of [NuStar's] identit[y]," Clearlake/Tarcona only "tacitly 'selected' [NuStar]," id . at 688 n.11 ; and
- that "the undisputed evidence" was "that [Clearlake/Tarcona] did not require O.W. to use [NuStar]," id . at 690.
We see no error in these findings. Although we reach a different conclusion on the subcontractor-exception issue today in the appeals brought by USOT, we do so based on differences between the records in the NuStar and USOT cases.
In the USOT cases, Hapag-Lloyd Aktiengesellschaft ("Hapag"), the owner or charterer of the USOT-supplied vessels, issued to O.W. Bunker Germany GmbH ("O.W. Germany") purchase orders that named USOT as the physical supplier.
See
USOT
,
We see no similar evidence or admission by Clearlake in the present case. Whereas the record in the USOT cases contained copies of the purchase orders issued by the owner/charterer Hapag,
see
,
e.g.
,
Clearlake
,
The closest that NuStar came to claiming that Tarcona directed the use of NuStar was asserting (a) that, several days in *652 advance of delivery to the Clearlake Vessels, "Tarcona knew ... that NuStar was the designated physical supplier of the bunkers it had ordered" ( see NuStar Rule 56.1 Statement ¶¶ 11, 12 (emphasis added) ), and (b) that Tarcona " accepted NuStar as the physical supplier of the bunkers it had ordered" ( id . ¶ 13 (emphasis added) ). As discussed above, however, evidence merely of such awareness and acceptance is insufficient to show that the vessel owner/charterer or its agent controlled the selection of the physical supplier or that they ordered or directed that NuStar be used.
CONCLUSION
We have considered all of NuStar's arguments on this appeal and have found them to be without merit. The partial final judgment is affirmed.
Reference
- Full Case Name
- CLEARLAKE SHIPPING PTE LTD., Plaintiff-Counter-Defendant-Appellee, v. NUSTAR ENERGY SERVICES, INC., Defendant-Cross-Defendant-Cross-Claimant-Appellant, ING Bank N v. Defendant-Counter-Claimant-Cross-Claimant-Cross-Defendant-Appellee, O.W. Bunker (Switzerland) SA, O.W. Bunker USA, Inc., O.W. Bunker North America, Inc., O.W. Bunker Holding North America Inc., Defendants.
- Cited By
- 4 cases
- Status
- Published