Bethpage Water Dist. v. Northrop Grumman Corp.
Opinion of the Court
*119This case involves drinking water contamination caused by the activities of defendants-appellees Northrop Grumman Corporation and Northrop Grumman Systems Corporation (together, "Northrop Grumman") in Bethpage, Long Island. Plaintiff-appellant Bethpage Water District (the "District") sued Northrop Grumman below for negligence, trespass, and nuisance based on groundwater contamination in Bethpage, and seeks damages for the cost of remediation.
Northrop Grumman filed a motion for partial summary judgment, arguing that the District's claims are barred by the three-year statute of limitations found in
On appeal, the principal question is when a cause of action for groundwater pollution accrues, so as to trigger the statute of limitations. Northrop Grumman argues that a cause of action accrues when the water provider learns that contamination threatens water quality to such an extent that remedial action must be promptly taken, even if the contamination has not yet reached the water source. The District argues that the statute of limitations does not accrue until contamination is actually detected in the water source itself. We affirm the decision of the district court and hold that the District's claims are time-barred.
BACKGROUND
A. Facts
1. The Pollution and Threat to the District
The District provides drinking water to the residents of the Town of Bethpage ("Bethpage") and its environs from the Long Island Aquifer System. Because the Long Island Aquifer System is the principal drinking water source for the area, it has been classified as a "sole source" aquifer under the Safe Drinking Water Act, 42 U.S.C. § 300f. Although the District employs eight different wells to provide drinking water, only two wells are at issue in this suit: Well 4-1 and Well 4-2 located at Plant 4.
Beginning in the 1930s, the Grumman Corporation ("Grumman") conducted manufacturing activities on its 600-acre property in Bethpage (the "Property"), including manufacturing heavy industrial and military equipment during World War II. In 1994, Grumman was bought by Northrop Corporation.
At some point, volatile organic compounds ("VOCs") from Grumman's property began to contaminate the groundwater *120in Bethpage. The primary VOC contaminating the water was trichloroethylene ("TCE"), which has been linked to liver problems and is a possible carcinogen.
a. Operable Units One and Two
In 1983, the New York State Department of Environmental Conservation ("DEC") listed the Property, known as the Grumman Aeropsace-Bethpage Facility Site, in the Registry of Inactive Hazardous Waste Disposal Sites.
In 1990, Grumman entered into a Consent Order with DEC to conduct a Remedial Investigation/Feasibility Study ("RI/FS") to analyze contamination at the Property.
In 1994, the District and Grumman entered into a tolling agreement (the "1994 Agreement") to address VOC contamination from OU1 and OU2 in Well 4-1 and Well 4-2 at Plant 4. In the 1994 Agreement, Grumman admitted that the "source of the contaminants" at Plant 4 was "located on property owned by Grumman." The Agreement also provided that:
(1) Grumman would pay $1.5 million for an air stripping tower ("AST")5 to remove VOCs and protect Plant 4, up to a concentration of 600 parts per billion ("ppb") total VOCs, and
(2) The District would not make any further demand for pollution remediation at Plant 4 for "contaminants identified to date." App. 16.
The following forms of damages were expressly excluded from the Agreement:
(1) any damages incurred by the District for migration of the existing contamination;
*121(2) any damages incurred by the District caused by the discovery of "new contaminants or an increase in the present levels of the already identified contaminants to a total of 600 [ppb], excluding pollution from sources other than Grumman," App. 15;
(3) any additional costs incurred by the District if the ASTs "become obsolete or require modifications" to address "new drinking water standards," App. 15;
(4) any damages from "the discovery of contaminants in any other part of the Water District not already described," App. 15; and
(5) any damages arising from contamination covered by the Agreement, incurred by the District as a result of "government remediation programs," App. 15.
b. Operable Unit Three
In October 1962, Grumman donated approximately 12 acres of land to the Town, including 3.75 acres that were used between 1949 and 1962 as settling ponds to "dewater ... sludge, including neutraliz[ing] chromic acid waste, from the waste water treatment facility" located at the Property. App. 635. After contamination from the area was found to threaten groundwater, DEC designated the parcel as Operable Unit ("OU 3") in 2005.
2. Remedial Actions
Northrop Grumman's argument turns on when the pollution was detected in the groundwater and the subsequent actions taken by the District to address the threat of pollution. Between June 2007 and February 2013, the threat of groundwater pollution generated a great deal of activity, much of it on the part of the District.
a. Soil Sampling
Beginning in 2007, soil samples taken by environmental consultants indicated the existence and extent of the contamination.
i. Vertical Profile Boring 104
In June 2007, Northrop Grumman's consultant Arcadis took groundwater samples from Vertical Profile Boring 104 ("VPB-104"),
ii. Vertical Profile Boring 116
In a letter to DEC dated April 28, 2008, H2M described VOC contamination found *122on April 8, 2008 in a new VPB test, VPB-116, as being in the "heart of the screen zone" for Well 4-1 and Well 4-2, and noted that contamination at 1,900 μg/L would "render the existing treatment system useless." App. 1274 ¶ 34. H2M also noted that because the contamination was "only 700 feet away from the plant and [wa]s in the zone of capture of the supply wells, it [wa]s only a matter of time until excessive contamination hit[ ] the supply wells. This time frame could be within the next 12 months."
b. Construction of Remediation Measures
i. The Second AST
In October 2008, H2M submitted an engineering report (the "2008 Engineering Report") to the Board of Commissioners for the District (the "Board of Commissioners"). The 2008 Engineering Report, which addressed the need for a second AST, stated that a VPB conducted 700 feet upgradient from Plant 4 showed concentrations of VOCs that "[we]re too great and would overcome the existing treatment system at Plant No. 4 and not allow for complete removal of VOC contamination." App. 764. It also stated that Plant 4 was expected to "be significantly impacted by extremely high VOC levels in the very near future." App. 816. Because the existing air stripping treatment system would be insufficient to address the expected increase, a second air stripping tower would be needed, at an estimated cost of $4.3 million. In February 2009, H2M submitted the 2008 Engineering Report to the Nassau County Department of Health ("NCDOH") for approval of the proposed AST at Plant 4. On June 30, 2009, NCDOH approved it and authorized the District to submit engineering plans for a second AST.
On July 23, 2009, the Board of Commissioners authorized the District to request bond financing for the construction of a second AST at Plant 4. On July 30, 2009, H2M prepared a Capital Improvement Plan ("CIP") which included (1) a new AST for Plant 4 designed to address VOCs "emanating from the former Grumman settling ponds [i.e., OU3]," App. 1277, and (2) a new supply well. The CIP stated that "[w]ith the existing treatment system incapable of treating the higher influent levels expected to impact this site, the District must immediately implement the upgrade of the treatment system to properly treat both wells on site to avoid the loss of the production wells." App. 959. On July 31, 2009, the District asked the Towns of Oyster Bay and Hempstead (the "Towns") for $15.5 million in public bond financing to pay for the actions recommended in the CIP, including a second AST costing $3.7 million, and a new Plant 4 supply well costing $3.3 million. App. 1281.
On November 18, 2009, counsel for the District demanded that Northrop Grumman pay for VOC treatment system improvements at Plant 4. Counsel also stated that the District had authorized "emergency implementation" of VOC treatment systems at Plant 4.
ii. The Granular Activated Carbon Polishing System
On November 25, 2009, the Board of Commissioners held a meeting, the notice for which stated that "[n]ew information obtained at District and H2M meeting with Grumman on 11/16 revealed a much greater threat to public supply wells at [Plant] 4. Immediate action is required for well head protection by the summer 2010 pumping season." App. 1035. At the meeting, the District determined that the second AST would not be sufficient to address *123the higher level of VOCs at Plant 4, and it would need to add a granular activated carbon polishing system ("GAC"). The GAC "constituted an interim emergency wellhead treatment proposal." App. 1302 ¶ 34.
Toward that end, in a letter to the NCDOH dated December 17, 2009, H2M stated that "[e]mergency action is recommended and warranted to have the treatment system improvements immediately in place to address th[e] imminent threat" that the OU3 plume posed to Plant 4. App. 1005-06. H2M asked NCDOH to recognize the need for a GAC system to be installed expeditiously in addition to a second AST, because there was "not enough time available to the District to wait for the completion of the new air stripping system." App. 1006. H2M stated that the contamination revealed by VPB-116 would overwhelm the Plant 4 treatment systems by spring 2010, and proposed that the GAC be operational by May 2010, and the additional AST be operational by May 2011.
iii. Declaration of Emergency
On December 23, 2009, H2M sent a letter to the District stating that "the contamination found at [VPB 116] will likely reach Plant 4 by this spring" and recommended "that the District declare an emergency and expedite the planned improvements at Plant No. 4." App. 1054. The letter also cited three bids received by H2M for the first phase of the project, and recommended accepting the lowest bid.
On December 29, 2009, the Board of Commissioners adopted a resolution declaring that "an emergency situation affecting the public health, safety and welfare exists" and authorizing a contract to begin construction on an emergency GAC and a second AST. App. 1059. That same day, H2M sent DEC a letter stating that "[r]ecent VOC detections have been found in the effluent of both Plant Nos. 4 and 6. The District is restricted to the use of only one well at a time at each facility." App. 1063. The letter also stated that, "based on the imminent threat that this plume has on the supply wells at Plant No. 4, one or more I[nterim] R[emedial] M[easures] are absolutely warranted." App. 1064. It stated: "[t]his is an emergency situation for the District, as it has restricted [Plant No. 4] to half capacity, and as the risk of losing Plant No. 4 for the peak pumping season will jeopardize the district's ability to meet peak domestic demand plus fire protection." App. 1068.
On January 5, 2010, the Town of Oyster Bay authorized a $13.95 million bond issuance for, among other things, "construction and equipping of water treatment facilities" at Plant No. 4. App. 1072. In February 2010, NCDOH approved the design and plan for the emergency GAC and the second AST. The GAC and AST were completed in January 2012.
iv. Well 4-1 and Well 4-2 Removed from Service
In February 2006, the District detected combined radium-226 and radium-228 in Well-2 at levels of 5.69 picocuries per liter ("pCi/L").
In December 2009, the District took Well 4-2 off line in preparation for the installation of "new VOC removal systems." App. 1103. In November 2010, the District took Well 4-1 off line in preparation *124for the installation of the GAC and AST. In February 2013, the District took Well 4-1 out of service because radium was detected at 5.87 pCi/L.
B. Proceedings Below
On November 18, 2013, the District filed this diversity suit against Northrop Grumman alleging negligence, trespass, and nuisance, and seeking to recover the costs of remediating pollution at Plant 4, as well as punitive damages.
On June 5, 2015, Northrop Grumman moved for partial summary judgment seeking dismissal of the District's claims related to Plant 4 as time-barred.
On June 15, 2016, the parties submitted a stipulation of voluntary dismissal without prejudice as to all of the District's claims not dismissed by the district court's March 31, 2016 order. On July 12, 2016, the district court entered final judgment as to all claims.
The District filed a timely notice of appeal on July 26, 2016. This appeal only addresses claims regarding Plant 4, as the District's remaining claims have been dismissed.
DISCUSSION
A. Standard of Review
This Court reviews a district court's decision on a motion for summary judgment de novo and reviews facts in the light most favorable to the losing party. See Watson v. United States ,
Two issues relating to the statute of limitations are presented: (1) VOC contamination and (2) radium contamination.
B. VOC Contamination
1. Applicable Law
The central issue is whether the District's claims for nuisance, trespass, and negligence based on VOC contamination are barred by the statute of limitations set forth in § 214-c(2). See Bano v. Union Carbide Corp. ,
the three year period within which an action to recover damages for personal injury or injury to property caused by the latent effects of exposure to any substance or combination of substances, in any form, upon or within the body or upon or within property must be commenced shall be computed from the date of discovery of the injury by the plaintiff or from the date when through the exercise of reasonable diligence such injury should have been discovered by the plaintiff , whichever is earlier.
Moreover, the claim accrues when the plaintiff first discovers its injury, regardless of whether the defendant's damaging conduct continues. See Bano ,
The District filed its complaint on November 18, 2013. Northrop Grumman argues that the District either sustained its injury or knew of its injury-the impact of contamination in the groundwater-more than three years prior to filing because it was aware of the imminent threat posed by contamination and took remedial action well before November 18, 2010. The District argues that its injury did not occur until sometime after November 18, 2010 because the contamination did not actually enter its wells until after November 18, 2010. It is undisputed that both Northrop Grumman and the District knew contamination existed in the vicinity of Plant 4 before November 2010. The question is when an "injury" sufficient to trigger the statute of limitations occurred.
This Court addressed a similar issue in In re Methyl Tertiary Butyl Ether ("MTBE") Prod. Liab. Litig. ,
MTBE was initially detected in the groundwater in wells in Queens at levels below the MCL. See In re MTBE ,
*126In re MTBE Prod. Liab. Litig. ,
The district court conducted an eleven-week jury trial, in three phases.
On appeal, Exxon argued that no reasonable juror could have reached such a conclusion, because the statute of limitations was triggered once the City learned that it would need to treat the water sometime in the future.
In upholding the verdict for the City, we held that the statute of limitations began to run only when "a reasonable water provider would have treated [the contaminated] groundwater."
[A]nticipat[ing] a future need to remediate MTBE does not prove that the City knew in 1999 [before the statute began to run] that Station Six had already been contaminated or that the contamination was significant enough to justify an immediate or specific remediation effort.
We also held that the mere presence of contamination in the water, i.e., at low levels, was not enough to trigger the statute of limitations. The City conceded that MTBE was first detected in the City's water before the start of the statute of limitations period.
*127(holding that because "New York, like other states, does not have a zero-tolerance policy on contaminants in drinking water .... the mere detection of MTBE in wells at very low levels would not make a reasonable person aware of a legally-cognizable injury sufficient to trigger the statute of limitations").
In MTBE , the contaminant was already in the water source. The question was whether low levels would trigger the statute of limitations. We held that low levels would not, but we made clear that at some point before the MCL was exceeded, the statute of limitations could be triggered-when the water source was sufficiently contaminated or the threat of contamination was sufficiently significant to justify immediate or specific remediation. See In re MTBE Prod. Liab. Litig. ,
2. Applicable Law
With these principles in mind, we turn to this case. Northrop Grumman argues that the statute of limitations began to run when the District learned of the potential need to remediate, or at least when a reasonable water provider would have taken action to protect the water. The District argues that the statute of limitations should not begin until an "actual injury" is sustained, which it contends would be when contamination was actually detected in the water in the wells.
Two inquiries are required, one legal and one factual: First, as a legal matter, may a water provider bring suit for remediation damages before the water source is polluted, that is, when there is a threat of pollution? And second, assuming so, as a factual matter, did the threat of pollution reach the point where the water provider should have taken immediate and specific action?
a. The Legal Question
The District argues that state law cases support their reading that an "actual injury" is required to trigger the statute of limitations. See, e.g., Germantown Cent. Sch. Dist. v. Clark, Clark, Millis & Gilson, AIA ,
In considering this issue, we must consider the purpose of a statute of limitations. As the Supreme Court noted in California Public Employees' Retirement System v. ANZ Sec., Inc. , --- U.S. ----,
With this purpose in mind, we reject the argument that the statute of limitations begins to run only after contamination is actually detected in an intake well. If a cause of action does not accrue until contamination is found in a well, a claim might never accrue, as contaminated portions of a nearby aquifer might not ultimately reach a well, or might be so toxic as to require shutting down an intake well before contact is made. Furthermore, a diligent water provider may take action to prepare its intake wells to treat incoming contaminants prior to actual contact. The approach advocated by the District would lead to the odd result of encouraging water providers to allow contamination to reach the wells so that a cause of action could accrue. A diligent water provider that successfully prepares its wells to treat increased levels of incoming contaminants is still injured if it has to expend resources to prevent the pollution from reaching the drinking water.
We do not, however, hold that the statute of limitations commences when a reasonable water provider takes any action in anticipation of future contamination or has any knowledge of potential contamination. Such a holding could deter water providers from investigating leaks or taking steps to address future contamination for fear of triggering the statute of limitations. See Hanna,
b. The Factual Inquiry
Accordingly, we must consider whether the District was aware that the threat of contamination was sufficiently significant to warrant "immediate or specific remediation efforts." We agree with the district court that the record here establishes as a matter of law that the District had suffered injury and was aware of that injury before November 2010. Indeed, the indisputable facts show that before November 2010, the District took a myriad of substantial *129and specific steps to address the contamination, including:
• The District took numerous steps in 2008 and 2009 toward building a second AST for Plant 4 and a new supply well, steps that would require the expenditure of millions of dollars;
• In doing so, the District recognized in a CIP that "the existing treatment system [is] incapable of treating the higher influent levels expected to impact this site, [and the District] must immediately implement the upgrade of the treatment system," App. 959 (emphasis added);
• In 2009, the District proposed an additional emergency GAC system, to be operational by May 2010, and in January 2010, the Town of Oyster Bay authorized a $13.95 million bond issuance for additional treatment facilities at Plant 4, App. 1054;
• On December 23, 2009, H2M sent a letter to the District stating that "the contamination found at [VPB 116] will likely reach Plant 4 by this spring" and recommended that the District "declare an emergency and expedite the planned improvements at Plant No. 4," App. 1054;
• On December 29, 2009, the Board of Commissioners declared such an emergency; and
• In December 2009, the District took Well 4-2 off line in preparation for the installation of the GAC/AST.
A reasonable jury could only conclude that these actions taken by the District prior to November 2010 constituted "immediate and specific remediation efforts" by a reasonable water provider to address pollution. As a result, the District's claims for damages arising from contamination of Plant 4 accrued before November 18, 2010, and thus are barred by the statute of limitations.
C. Radium Contamination
The District alleges that radium was detected in Well 4-1 and Well 4-2 in 2013, and therefore its suit against Northrop Grumman in November 2013 was timely. Northrop Grumman argues that the District knew of the radium contamination in 2006, and therefore the claim is barred by the statute of limitations.
It is undisputed that the District detected radium in its wells at the following levels at the following times:
February 2006 5.69 pCi/L in Well 4-2 May 2006 5.55 pCi/L in Well 4-1 September 2010 7.03 pCi/L in Well 4-1 January 2013 5.87 pCi/L in Well 4-1
The R&R recommended dismissal of the District's radium claims because the record established that: (1) the District could not "determine the source and seriousness of any radium contamination," in part because radium is naturally occurring in the water on Long Island, and (2) the District was aware of radium in 2006, and the level in 2013 was lower than the level in 2006, more than three years prior to suit. The district court adopted the R&R concluding that the radium claim was barred by CPLR § 214-c(2) because the District had knowledge of the contamination before November 2010.
On appeal, the District does not deny the earlier knowledge of the presence of radium, but argues that it did not know *130that the source of the radium was the Grumman site, rather than merely naturally occurring, until it filed this suit in 2013 and obtained information about the source from DEC.
Northrop Grumman argues that the District waived its argument concerning the timeliness of this claim by failing to raise that point in its objections to the R&R. It argues that the only objection raised by the District was an assertion that the district court should have considered new radium sampling results from a former Northrop Grumman property as a factual basis to establish causation.
The District's argument fails. Even if the District did not know the source of the radium until 2013 at the earliest, its claim is still barred by the statute of limitations because suit was filed more than five years after the District discovered the injury. While CPLR § 214-c(2) does not carve out an exception for delay in discovering the source of the injury, CPLR § 214-c(4) extends the limitations period to one year after the discovery of the cause of the injury in these circumstances:
[n]otwithstanding the provisions of subdivisions two and three of this section, where the discovery of the cause of the injury is alleged to have occurred less than five years after discovery of the injury or when with reasonable diligence such injury should have been discovered, whichever is earlier, an action may be commenced or a claim filed within one year of such discovery of the cause of the injury.
Here, the District first learned of radium contamination in 2006. It claims it did not learn of the source of the contamination until discovery began in this suit in 2013. There was a seven-year gap between the discovery of the injury in 2006 and the discovery of the source of the injury in 2013. As a result, the District's claims regarding radium are also time-barred.
CONCLUSION
For the reasons set forth above, we AFFIRM the decision of the district court.
See EPA, National Primary Drinking Water Regulations (2009), https://www.epa.gov/sites/production/files/2016-06/documents/npwdr_complete_table.pdf.
"Maximum Contaminant Levels" are federally set maximum allowable concentrations of contaminants in drinking water and are set "as close to the health goals as possible, considering cost, benefits and the ability of public water systems to detect and remove contaminants using suitable treatment technologies." EPA, What are EPA's Drinking Water Regulations for Trichloroethylene? , https://safewater.zendesk.com/hc/en-us/articles/212075407-4-What-are-EPA-s-drinking-water-regulations-for-trichloroethylene (last visited Feb. 28, 2017).
An Operable Unit "represents a portion of a remedial program for a site that for technical or administrative reasons can be addressed separately to investigate, eliminate or mitigate a release, threat of release or exposure pathway resulting from the site contamination." App. at 636.
A Remedial Investigation is conducted to ascertain the nature and extent of the contamination, and a Feasibility Study is designed to determine remedies for the contamination. See N.Y. Dep't of Envtl. Conservation, Remedial Investigation/Feasibility Study , http://www.dec.ny.gov/chemical/8658.html (last visited Dec. 7, 2017).
Air stripping is the process of removing VOCs from contaminated groundwater or surface water by moving air through the water. Because VOCs evaporate easily, the air passing through the contaminated water accelerates the removal of the VOCs. Air stripping is usually performed by use of an air stripper or an aeration tank. See EPA, A Citizen's Guide to Air Stripping , https://www3.epa.gov/region9/superfund/montrose/pdf/outreach/air-stripping.pdf.
Vertical profile boring involves drilling holes into the ground to obtain groundwater and soil samples used to determine the presence of contamination. See generally Minn. Stormwater Manual, Understanding and Interpreting Soils and Soil Boring Reports for Infiltration BMPs , https://stormwater.pca.state.mn.us/index.php?title=Understanding_and_interpreting_soils_and_soil_boring_reports_for_infiltration_BMPs (last modified Feb. 13, 2017).
The federal standard for combined radium-226 and radium-228 in drinking water is an MCL of 5 pCi/L. EPA, Radionuclides Rule , https://www.epa.gov/dwreginfo/radionuclides-rule (last visited Dec. 7, 2017).
The operative complaint here is the Second Amended Complaint, filed on March 20, 2015. On March 24, 2014, Northrop Grumman filed a motion to dismiss the original complaint, arguing that it was barred by the statute of limitations. The district court permitted limited discovery on the statute of limitations issue. By Order dated December 3, 2014, the district court allowed Northrop Grumman to convert the motion to dismiss into a motion for summary judgment.
On September 6, 2016, the district court granted the District's Rule 54(b) motion, and final judgment was entered with respect to the "Plant 4" claims dismissed pursuant to the Partial Motion for Summary Judgment.
Reference
- Full Case Name
- BETHPAGE WATER DISTRICT v. NORTHROP GRUMMAN CORPORATION, Northrop Grumman Systems Corporation
- Cited By
- 8 cases
- Status
- Published