Illinois Surety Co. v. Standard Underground Cable Co.
Illinois Surety Co. v. Standard Underground Cable Co.
Opinion of the Court
In this action the Cable Company, a Pennsylvania corporation, recovered a judgment against the Surety Company, a corporation of Illinois, on a bond of suretyship. The facts are as follows:
On June 12, 1911, David Dick & Sons, Limited, a Canadian corporation, agreed in writing to erect a building for the Cable Company in the city of Hamilton, Ontario. All the labor was to be done by the Dick Company, and all the matérial furnished, except the structural steel; this the Cable Company itself was to obtain from some steel maker, and deliver on the ground. The building was to be finished by October IS under penalty for delay. The price was $69,250, and 80 per cent, in value of the work and of the material delivered was to be paid monthly on the architect’s estimate, and the balance was payable not long after completion of the job. The agreement also provided in effect that the Cable Company should not be held liable to any contractor for the delay of a prior contractor, but, in case such delay should keep the subsequent contractor out of possession, the architect should allow him additional time to complete his own contract. The Cable Company was to supply the steel complete by August 7. In compliance with this obligation the Cable Company contracted with the Hamilton Bridge Works for the manufacture of the steel, b.ut deliveries were delayed beyond the contract time. About 90 per cent, of it, however, was on the ground by October 12, and all except 35 pounds by November 10, and the architect in charge testified that, even if all of it had been available by August 7, the Dick Company would not have been ready to erect it, and would not have suffered more than a week’s postponement. The manager of the Dick Company denied this, and testified that if the steel had been delivered in due time the building could have been erected by October 15. According to the Cable Company’s evidence, the default in delivery was due, at least in part, to the Dick Company’s success in urging the Hamilton Company to make and deliver first the steel needed for a job at Welland, on which also the Dick Company was the contractor.
As just stated, only part of the steel had been delivered by August 7 — about one-fifth, in fact — and the bond in suit was given in that condition of affairs, the Dick Company and both parties to this suit either having actual knowledge thereof or being chargeable with knowledge. The instrument is dated August 11, and — after reciting that “the
While the Dick Company was still going on with the contract, it received four certificates from the architect, dated August 1, September 1, October 2, and November 1, respectively, and upon these was paid $54,842. The architect testified without contradiction that this amount represented 80 per cent, .in value of the work done and of the materials on tire premises.' There was no dispute that (after the contract price had been properly reduced by several items) the amount thhs paid was about $1Q0 less than 80 per cent, of the reduced price. The Cable Compairy sought to recover several items of loss, aggregating more than $30,000, but the verdict is evidently confined to the sum paid out in excess of the full contract price.
The Surety Company’s chief defenses were: (1) Overpayment to the Dick Company; and (2) tire delay in delivering the steel. The court charged that there was no evidence of overpayment, as the architect’s estimates were not attacked, and as the Cable Company had accepted them as correct, but submitted nevertheless the question whether the payments had in fact done the surety harm. The court also charged that under thfe contract the delay in delivery would entitle the Dick Company to an extension of time, but that the Surety Company would not be discharged merely by such delay. The verdict was for $15,000, with interest, and the judgment is for $18,507.50.
[ 1 ] Two or three questions of minor importance are raised by the Surety Company, but as they are not much insisted on we shall consider only the defenses already referred to. With regard to the contractor’s overpayment, we find nothing in the record to contradict the architect’s estimate. Indeed, nothing is suggested except the argument that, as it cost a large sum to finish the building, the architect must have put much too high an estimate on the value of the work already done and the material already furnished. But we discover no facts to support the argument, and. we cannot agree that direct and positive testimony whose good faith is undisputed may be displaced by inferences of the most general character unsupported by a single detail.
We find no reversible error, and direct the judgment to be affirmed.