Petitioner, Southern California Edison Company, pursuant to Section 19(b) of the Natural Gas Act, 15 U.S.C.A. Section 717r(b), seeks to set aside the July 26, 1966 Order of respondent, Federal Power Commission, which certificated proposals by El Paso Natural Gas Company and Transwestern Pipeland Company to increase the supplies of natural gas to distributors in southern California for resale to customers, including petitioner and the Los Angeles Department of Water and Power (L.A.D.W.P.), and denied certification of a proposal by Gulf Pacific Pipeline Company for direct sales exclusively to petitioner and L.A. D.W.P.
Gulf Pacific Pipeline Company has now been dissolved. L.A.D.W.P. has not filed a petition for review nor sought to intervene herein. Humble Oil & Refining Company, the major gas supplier for the Gulf Pacific project, has terminated its gas supply contract with the petitioner, as have the other producers for this project. They have not filed petitions to intervene here. El Paso and Transwestern Pipeline have intervened in support of the Federal Power Commission’s challenged Order.
On review of the record we are of the opinion that the questions compel answers in the affirmative. The record discloses that the Commission complied with procedures required by law and that it reasonably exercised its discretion on substantial and sufficient basis in fact and law. Once the existence of a rational basis for the Commission’s action is ascertained the reviewing power is estopped from further consideration of the Commission’s action. See Dorchester Gas Producing Company v. Federal Power Commission, 353 F.2d 162 (3 Cir. 1965), cert. den. 383 U.S. 969, 86 S.Ct. 1276, 16 L.Ed.2d 310 (1966). And see, Community Broadcasting Service, Inc. v. Federal Communications Commission, 126 U. S.App.D.C. 258, 377 F.2d 143, 144 (1967), where it was held that the choice of competing applicants for a broadcasting license “rests within the sound judgment of the Commission”.
For the reasons stated the July 26, 1966 Order of the Federal Power Commission will be affirmed.