In re Central Railroad
In re Central Railroad
Opinion of the Court
OPINION OF THE COURT
The perplexing problem of the priority applicable to personal injury claims of
The following table will illustrate the rather typical delay between date of liquidation of the claim by judgment or settlement and the date of final payment:
Name of Creditor Amount of Claim Obtained by Judgment or Settlement Date Date of of Final Liquidation Settlement
Dugan $57,150.24 J Apr. 6, 1971 Mar. 28, 1972
Koch 25,330.00 J Nov. 17, 1971 July 28, 1972
Hoak 30,000.00 J Motion for appeal withdrawn Aug. 4, 1972. No payment to date.
Paletsky 94,000.00 May 12,1972 Partial payment $11,000. Mar. 27, 1973; Balance unpaid.
Rydzewski 10,000.00 S May 26, 1972 Nov. 5, 1971
Horkan 15.000. 00 S Sept. 20, 1972 Jan. 7, 1972
Iveson 15.000. 00 s Aug. 2, 1972 Dec. 6, 1971
On October 13, 1967, in the early stages of the reorganization, the District Court signed Order No. 53 authorizing the trustees to settle and pay certain personal injury claims in amounts not exceeding $15,000.00 and to submit to the Court a list of pending cases every six months thereafter.
The Receiver established a system for paying claims of this nature by allocating $35,000.00 monthly, from income to payment of claims of less than $15,000.00 and paying seriatim, as funds become available, those cases over $15,000.00 which required Court approval.
On November 13, 1967 an order was entered permitting the trustees to pay all current freight and miscellaneous interline accounts.
The District Court was sympathetic with the plight of the personal injury claimants but was much concerned about the precarious financial position of the debtor which has continued to lose money in substantial amounts. Since the public interest required the operation of the railroad to continue, the Court felt that it had to be careful so that the trustees did not use the funds in such a manner as to curtail the functioning of the bankrupt line.
The general rule is that, unless it should develop that sufficient funds are available, no interest is payable thereafter on claims which have accrued on the date of bankruptcy. However, Congress has given special recognition to personal injury claims of employees of
“(n) In proceedings under this section, and in equity receiverships of railroad corporations now or hereafter pending in any court of the United States, claims for personal injuries to employees of a railroad corporation, claims of personal representatives of deceased employees of a railroad corporation, arising under State or Federal laws * * * shall be preferred and paid out of the assets of such railroad corporation as operating expenses of such railroad.”
As Collier
As further justification, it has been said, too, that claims for personal injuries which accrue after the receivership has commenced obtain a preference not because of any virtue of their own but because they are committed by the receiver and the receiver being an officer of the Court, the Court will pay its own obligations first. See Underhay, Tort Claims In Receiverships and Reorganizations, (1936) 22 Iowa Law Review 60.
Personal injury claims under the Federal Employers Liability Act when reduced to judgment accrue interest as a matter of right. There is no equitable rule which would require that the employees or their survivors be required to take less than the full amount of their claim in order to have funds available for other creditors whose transactions occurred in a purely commercial setting. If freight and interline claims are paid promptly and in full, there is no overriding consideration requiring injured employees to finance, even partially, the continued operation of the railroad to the benefit of investors, more particularly, the bondholders, however worthy their position. The Eighth Circuit Court of Appeals recognized this general proposition in Reconstruction Finance Corporation v. Missouri-Kansas-Texas R. Co., 122 F.2d 326 (8th Cir. 1941), when it gave priority to a personal injury claim over other operating expenses.
In Powell v. Link, 114 F.2d 550 (4th Cir. 1940), interest was awarded on a prereceivership judgment for personal injuries. There the Court emphasized that § 205(n) was remedial and should be liberally interpreted.
Similarly, in Bankers Trust Co. v. Florida East Coast Ry. Co., 31 F.Supp. 961 (S.D.Fla. 1940), interest was awarded from the date of judgment on a personal injury claim which had arisen before the reorganization took place. In that ease, however, the Court pointed out that there were sufficient funds to pay interest on other claims in the same class.
We recognize the difficult cash position of the debtor in this case and appreciate the concern of the reorganization court to serve the public interest by continuing the operation of the road. In order to do so it is of course necessary to meet payroll expenses as they accrue. Much of the claims in the category of the petitioners in this case do represent a loss of wages. Had they not been injured, the employees’ wages would have been paid as due and the men would have had the use of the funds. Since payment was postponed because of injury or terminated because of death in one instance, we see no equity in depriving the claimants of interest which merely represents a charge for the use of the money.
We are concerned, moreover, with the delay between the dates of judgment and satisfaction of the claims. As the Court indicated at the hearing on April 10, 1972, there was some question
In this suit the petitioners also ask that the bond of the Receiver-Trustee be increased. We find that it was not erroneous for the District Court to deny this request and see no further need to consider that issue.
The order of the District Court is reversed with instructions to award interest on personal injury claims of employees from the date of judgment or approval of settlement and the ease is remanded with directions to make appropriate determinations on what sum of money may realistically be allocated from operating funds on a monthly basis to expedite satisfaction of these claims.
. 5 Collier on Bankruptcy, 14th Ed. § 77.21, f.n. 25.
Reference
- Full Case Name
- In the Matter of The CENTRAL RAILROAD COMPANY OF NEW JERSEY, Debtor. Appeal of Frances A. DUGAN, Individually and as Administratrix ad Prosequendum of the Estate of Charles A. Dugan, Appeal of Lloyd HOAK
- Cited By