Brockenbrough v. Champion Fibre Co.

U.S. Court of Appeals for the Fourth Circuit
Brockenbrough v. Champion Fibre Co., 176 F. 840 (4th Cir. 1910)
100 C.C.A. 310; 1910 U.S. App. LEXIS 4305

Brockenbrough v. Champion Fibre Co.

Opinion of the Court

DAYTON, District Judge

(after stating the facts as above). In our judgment the controversy in this case, under the pleadings, narrows itself to a single question of law and fact. It is undisputed that the plaintiff in error had a five-year contract to deliver to defendant in error cordwood within fixed minimum and maximum limits each year for prices increasing in amount from year to year; that he was to commence delivery July, 1908, but, at the request of the defendant company, without objection postponed the beginning of delivery until October 1, 1908; that about October 14th he went from his contract work in Virginia to the defendant’s place of business at Canton, N. C., to see Oma Carr, the manager of the defendant’s wood and extract departments, in regard to this contract and the delivery of this wood; that he found that, by reason of the overstocking and congestion of the company’s woodyards, it had sought and obtained from the railroad company the promulgation of a temporary embargo upon delivery to it of chestnut wood; that, not finding Carr, on the next day he sent Garst back with a letter to him in which he stated:

“I’m again ready to commence shipments & urge yon not to delay the performance of this contract longer, having already lost nearly, 4 months of best weather. Kindly answer this by Mr. Jack Garst as I will be here this P. M.”

Garst saw Carr, who explained the condition of the company’s yards to which had been shipped 1,200 cars of wood in September and 3,100 in October, and the reason for the embargo, and sent back to plaintiff a reply to his letter, as follows:

*842“Suggest that in view of short time until roads get had, and our difficulties here in being able to handle incoming shipments regularly, you wait until spring before' opening your territory. As an alternative, suggest that you look over S. & W. territory for hemlock to work this winter. Can fix this so that you can get $6.00 on cars at Marion.”

Plaintiff made no reply to this, but went immediately to two stations of the railroad company ,and asked for cars to be placed for the purpose of shipping chestnut wood to defendant at Canton. At one of these places he was informed by the railroad agent that his request could not be granted because of the embargo. At the other the agent, not having received notice of the embargo, informed him that the car would be placed for him when he had wood there with which to load it. Plaintiff then informed this agent of the embargo, and indicated his purpose was to “test the matter.” He in fact had made no preparation to cut and haul any wood, owned no timber in the territory to which-his contract limited him from which to cut and haul it, and had made no effort to buy any such wood from' others. The embargo declared October 1st was lifted on October 28th following. Plaintiff on October 26th, 12 days after his arrival from Virginia at Canton, instituted this suit for the purpose of recovering $61,-000 damages for the alleged breach on the part of defendant of the contract. The sole question is whether the action of the defendant under the circumstances constituted in law a repudiation of the contract in its entirety. We think not. In support of this conclusion we cite Sitterding v. Grizzard, 114 N. C. 108, 19 S. E. 92; May v. Getty, 140 N. C. 310, 53 S. E. 75; Redding v. Vogt, 140 N. C. 562, 568, 53 S. E. 337; Dingley v. Oler, 117 U. S. 490, 6 Sup. Ct. 850, 29 L. Ed. 984; Smoot’s Case, 15 Wall. 36, 21 L. Ed. 107; Roehm v. Horst, 178 U. S. 1, 20 Sup. Ct. 780, 44 L. Ed. 953.

But it is insisted that, if the contract was not wholly repudiated, the plaintiff was entitled to recover damages because of defendant’s action in delaying its execution, in the deliveries for the first year, and this under the liberality allowed in North Carolina practice and pleading. We do not think so. The whole theory of plaintiff’s case as set forth in his complaint was that the contract had been by the company wholly repudiated, and that it was thereby wholly terminated. The whole case was tried upon this theory. The issues to be submitted to the jury were agreed and settled, and no such issue as to whether plaintiff was entitled to damage by reason of delay in execution of the contract was asked to be submitted. Had plaintiff desired to raise an issue of this kind, the way was open for him to have done so by amending his complaint before or at any time before the issues were submitted to the jury. This he did not ask to do, but tried his case upon the sole theory that defendant’s acts had wholly terminated the contract. Under such circumstances, he cannot come here and ask for a reversal because he was not allowed -to recover in the court below something that he did not there seek to recover. It is true that the North Carolina practice is liberal, but we have no question but what it is in strict accord with this ruling; for in Moss v. Railroad Co., 122 N. C. 889, 29 S. E. 410, it is held:

*843"A complaint proceeding apon one theory will not authorize a recovery upon another and entirely different theory.”

And it is further held in this case to be “a settled maxim of law that, proof without allegation is as unavailable as allegation without proof.” To the same effect is McCoy v. Railroad, 142 N. C. 383, 55 S. E. 270, and Conley v. Railroad, 109 N. C. 692, 14 S. E. 303.

In Sloan v. Hart, 150 N. C. 269, 63 S. E. 1037, 21 L. R. A. (N. S.) 239, it is said:

“Such specific damages as inay have reasonably been within the contemplation of the parties are allowed in this class of cases, but they must be both pleaded and proven before the court can submit them to the consideration of the jury.”

If plaintiff had a just cause of action based upon the theory of a partial breach of the contract and not an entire repudiation of it, about which we express no opinion, it is to be borne in mind that the action of the court below in directing a nonsuit does not estop, him under certain well-defined rules and limitations from asserting said right.

We therefore find no error in the judgment of the court below, and it will be affirmed.

Reference

Full Case Name
BROCKENBROUGH v. CHAMPION FIBRE CO.
Status
Published