U.S. Court of Appeals for the Fourth Circuit, 1974

Clifton D. Mayhew, Inc. v. Blake Construction Co., Inc.

Clifton D. Mayhew, Inc. v. Blake Construction Co., Inc.
U.S. Court of Appeals for the Fourth Circuit · Decided July 24, 1974 · Boreman, Winter, Craven
499 F.2d 550 (Federal Reporter, Second Series)

Clifton D. Mayhew, Inc. v. Blake Construction Co., Inc.

Opinion

PER CURIAM:

Following remand from this court, Clifton D. Mayhew, Inc. v. Blake Construction Co., 482 F.2d 1260 (4th Cir. 1973), the district court proceeded to determine Mayhew’s claim for damages on its merits. Having fully and carefully considered the briefs, record and oral arguments, we find ourselves in agreement with the district court’s disposition of the case, and we affirm the judgment on the basis of the district judge’s memorandum opinion. Clifton D. Mayhew, Inc. v. Blake Construction Co., No. 440-72-A (E.D.Va., Nov. 14, 1973). Accord, Merando, Inc. v. United States, 475 F.2d 598 (Ct.Cl. 1973); HRH Construction Corp. v. United States, 428 F.2d 1267, 192 Ct.Cl. 912 (1970).

Affirmed.