United States v. Adams Construction Co.

U.S. Court of Appeals for the Fourth Circuit
United States v. Adams Construction Co., 20 F. App'x 253 (4th Cir. 2001)

United States v. Adams Construction Co.

Opinion

PER CURIAM.

Tri-M Electrical Contractors, Incorporated (“Tri-M”) appeals a district court order granting partial summary judgment to Adams Construction Company Incorporated and United States Fidelity & Guaranty Company dismissing Tri-M’s claim under the Miller Act, 40 U .S.C.A. §§ 270a et seq. (West 1986 & Supp. 2001), and dismissing the remaining claims without prejudice. We have reviewed the record and the district court’s oral findings and find no error. See United States f/u/b Interstate Mechanical Construction v. International Fidelity Ins. Co., 200 F.3d 456 (6th Cir. 2000); United States f/u/b Noland Co. v. Andrews, 406 F.2d 790 (4th Cir. 1969). Accordingly, we affirm on the reasoning of the district court. See United States f/u/b v. Adams Constr. Co., No. CA-99-799-9-8 (D.S.C. filed Mar. 26, 2001; entered Mar. 28, 2001). We dispense with oral argument because the facts and legal contentions are adequately presented in the materials before the court and argument would not aid the decisional process.

AFFIRMED.

Reference

Full Case Name
UNITED STATES of America, for the Use and Benefit of Tri-M Electrical Contractors, Incorporated, Plaintiff-Appellant, v. ADAMS CONSTRUCTION COMPANY, Incorporated; United States Fidelity and Guaranty Company, Defendants-Appellees
Status
Unpublished