East Coast Repair v. United States
East Coast Repair v. United States
Opinion
PUBLISHED
UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT
No. 20-2146
EAST COAST REPAIR & FABRICATION, LLC,
Plaintiff – Appellant,
v.
UNITED STATES OF AMERICA, THROUGH THE DEPARTMENT OF THE NAVY, and its activity, the Mid-Atlantic Regional Maintenance Center,
Defendant – Appellee.
Appeal from the United States District Court for the Eastern District of Virginia, at Norfolk. Arenda L. Wright Allen, District Judge. (2:20-cv-00057-AWA-DEM)
Argued: September 22, 2021 Decided: October 14, 2021
Before MOTZ and AGEE, Circuit Judges, and KEENAN, Senior Circuit Judge.
Affirmed by published opinion. Judge Motz wrote the opinion, in which Judge Agee and Senior Judge Keenan joined.
ARGUED: Dustin Mitchell Paul, VANDEVENTER BLACK, LLP, Norfolk, Virginia, for Appellant. Michael Anthony DiLauro, UNITED STATES DEPARTMENT OF JUSTICE, Washington, D.C., for Appellee. ON BRIEF: Brian M. Boynton, Acting Assistant Attorney General, Civil Division, UNITED STATES DEPARTMENT OF JUSTICE, Washington, D.C., for Appellee. DIANA GRIBBON MOTZ, Circuit Judge:
This case arises from a dispute between East Coast Repair and the United States
over contracts for the repair of three Navy ships. East Coast seeks to recover $473,600 that
the Government withheld from payment under one of these contracts. Because the parties’
settlement agreement precludes East Coast’s claims, we affirm the judgment of the district
court rejecting these claims.
I.
East Coast, a ship repair company, contracted with the U.S. Navy to repair three
ships: the USS Thunderbolt, the USS Tempest, and the USS Hurricane. Though East Coast
brought this suit under the Hurricane contract, the Tempest contract is central to it. In
2013, the Navy claimed it was entitled to $474,600 in liquidated damages under the
Tempest contract because East Coast delivered the Tempest late. Because the Navy had
already paid all but $1,000 for East Coast’s work on the Tempest, it withheld a $473,600
setoff from payment to East Coast under the Hurricane contract.
East Coast claimed the Navy caused the complained-of delay in delivery and sent a
letter to the government contracting officer disputing the Navy’s assessment of liquidated
damages under the Tempest contract and requesting additional compensation for
unanticipated work on the Tempest. In 2014, after the contracting officer denied that
request, East Coast sued the United States under the Tempest contract in federal district
court (the “Tempest suit”). In its complaint, East Coast referred specifically to the
$473,600 setoff, stating that it “included those liquidated damages as part of its [request to
2 the government contracting officer] and as part of the calculation of the damages requested
hereunder since they were assessed on the TEMPEST.”
In 2014, while the litigation proceeded, East Coast submitted to the contracting
officer a request for additional compensation under the Hurricane contract for its assertedly
unexpected work on that ship. After six months without response, East Coast appealed to
the Armed Services Board of Contract Appeals (the “Board”) and ultimately moved for
summary judgment before the Board seeking payment of the $473,600 “withheld from
payments due under [the Hurricane] contract.” For reasons unclear from the record, East
Coast later withdrew the summary judgment motion.
East Coast and the Government settled the Tempest suit in 2017. In the settlement
agreement, each party released the other from liability in broad, but not identical, terms.
East Coast released the Government “from any and all actions, claims, . . . and liabilities
of any type, whether known or unknown, suspected or unsuspected, foreseen or unforeseen,
or open or hidden, which have existed, presently exist, or may exist in the future, arising
out of or in any way relating to the [Tempest] Contract.” The Government released East
Coast from “any and all” claims “arising out of or in any way relating to the issues that
were raised in the pleadings or could have been raised in the pleadings.” Both releases
contain an exception for retainage (a portion of the contract price the Government typically
withholds from payment to ensure contractors complete their work). The district court
dismissed the Tempest suit with prejudice.
In 2019, East Coast asserted a right to the same $473,600 in a third request to the
government contracting officer. And in 2020, East Coast filed this action, claiming the
3 Government’s refusal to pay the $473,600 breached the Hurricane contract. After the
parties filed cross motions for summary judgment, the district court granted the
Government’s motion and denied East Coast’s. The court held that (1) it lacked subject
matter jurisdiction because East Coast made a binding choice to raise the setoff issue before
the Board, and (2) the settlement agreement barred East Coast’s claims. East Coast then
filed this appeal.
II.
We first address the district court’s jurisdictional holding. We review a court’s
dismissal for lack of subject matter jurisdiction de novo. Ripley v. Foster Wheeler LLC,
841 F.3d 207, 209(4th Cir. 2016).
The district court based its conclusion that it lacked subject matter jurisdiction on
Section 7104(b) of the Contract Disputes Act,
41 U.S.C. §§ 7101, et seq. That provision
states that a contractor “may” — after first raising a claim with the designated “contracting
officer” — bring the claim before a federal district court “in lieu of” appealing to the agency
board. * The Federal Circuit has interpreted Section 7104(b) to make binding a government
contractor’s choice to bring a claim before either the agency board or a federal district
court. See Nat’l Neighbors, Inc. v. United States,
839 F.2d 1539, 1541–42 (Fed. Cir. 1988).
Thus, once a contractor elects to bring its claim before one forum with jurisdiction, the
other forum lacks subject matter jurisdiction over the same claim. Bonneville Assocs. v.
* A contractor usually must choose between an agency board and the U.S. Court of Federal Claims. But in maritime cases like this one, a contractor may choose a federal district court. See
41 U.S.C. § 7102(d); Suits in Admiralty Act,
46 U.S.C. § 30901, et seq. 4 United States,
43 F.3d 649, 653(Fed. Cir. 1994). The Federal Circuit commonly refers to
this rule as the “Election Doctrine.”
Id. at 651. Relying on this doctrine, the district court
concluded that East Coast made a binding choice of forum when it filed a motion for
summary judgment raising the setoff issue before the Board in 2016. For this reason, the
court held it lacked jurisdiction.
We have some question as to this holding. The district court did not consider the
significance of the Tempest suit. The Government asserted before the district court that
East Coast had earlier chosen federal district court as its preferred forum when it filed a
complaint raising the setoff issue in the Tempest suit in 2014. If so, the filing of a summary
judgment motion raising the same issue before the Board two years later would not
constitute a binding election of forum.
Id. at 653. Nor is it at all clear that the mere filing
of a summary judgment motion constitutes a binding choice of forum under the governing
statute, which states that a contractor may either “appeal[] the decision of a contracting
officer . . . to an agency board” or “bring an action directly” in federal court.
41 U.S.C. § 7104(b) (emphasis added).
Rather than determine the answer to these difficult jurisdictional questions —
questions that turn on principles never before applied in this Circuit — we take the “less
burdensome course” and resolve this case on res judicata grounds. See Sinochem Int’l Co.
v. Malaysia Int’l Shipping Corp.,
549 U.S. 422, 436(2007). Where a court conclusively
determines it lacks jurisdiction, it must dismiss the case on that basis. Sinochem Int’l Co.,
549 U.S. at 434. But a court may bypass a difficult jurisdictional question and “choose
among threshold grounds for denying audience to a case on the merits . . . when
5 considerations of convenience, fairness, and judicial economy so warrant.”
Id.at 431–32;
Hicks v. Ferreyra,
965 F.3d 302, 309 n.2 (4th Cir. 2020). Res judicata is one such threshold
ground. See Hoffman v. Nordic Naturals, Inc.,
837 F.3d 272, 277(3d Cir. 2016).
III.
Accordingly, we now turn to the district court’s grant of summary judgment on the
basis that res judicata bars East Coast’s claims because East Coast released them in the
2017 settlement agreement. We review summary judgment decisions de novo. Wilson v.
Prince George’s Cnty.,
893 F.3d 213, 218(4th Cir. 2018). Summary judgment is
appropriate if, construing all evidence in favor of the non-moving party, “there is no
genuine dispute as to any material fact and the movant is entitled to judgment as a matter
of law.” Fed. R. Civ. P. 56(a).
Res judicata traditionally bars a party from asserting a claim in a later suit once a
court has reached a final judgment on the merits of the same claim in an earlier suit. Martin
v. Am. Bancorp. Ret. Plan,
407 F.3d 643, 650 (4th Cir. 2005). If a claim is resolved in a
settlement agreement, we look to the intent of the parties to determine whether the
settlement agreement bars later claims. Ohio Valley Envt’l Coal. v. Aracoma Coal Co.,
556 F.3d 177, 211(4th Cir. 2009) (citing 18A Charles Alan Wright, Arthur R. Miller, &
Edward H. Cooper, Federal Practice & Procedure § 4443 (2d ed. 2002)). We use contract
interpretation principles to discern the parties’ intent. Keith v. Aldridge,
900 F.2d 736,
740–41 (4th Cir. 1990).
Here, East Coast released the Government from liability for “any and all” claims
“arising out of or in any way relating to the [Tempest] Contract.” The $473,600 setoff
6 clearly “relates” to the Tempest contract because the Navy withheld that amount as
liquidated damages on the Tempest contract. We cannot read such a broad release to
exclude a claim for a setoff taken as liquidated damages under the Tempest contract. Cf.
United States v. Gonzales,
520 U.S. 1, 5(1997) (“Read naturally, the word ‘any’ has an
expansive meaning . . . .”); Am. Recovery Corp. v. Comput. Thermal Imaging, Inc.,
96 F.3d 88, 93 (4th Cir. 1996) (describing “arising out of or related to” formulation in an arbitration
clause as “capable of an expansive reach”). And if we had any doubt as to whether East
Coast believed the setoff relates “in any way” to the Tempest contract, we need only look
to East Coast’s complaint in the Tempest suit, which states that East Coast factored the
$473,600 into its calculation of damages because the damages “were assessed on the
TEMPEST.”
East Coast insists, however, that we read its release to give meaning to the difference
in wording between its release and the Government’s. East Coast regards it as significant
here that while it released any claims against the Government “arising out of or in any way
relating to the [Tempest] Contract,” the Government released any claims against East Coast
“arising out of or in any way relating to issues that were raised in the pleadings or could
have been raised in the pleadings” in the Tempest action. East Coast argues we must
construe this difference to mean that “the parties intentionally omitted” a release of a claim
for the setoff. Appellant’s Br. at 25. But as it conceded at oral argument before us, East
Coast offers no evidence of the parties’ intent to do this in drafting the two releases. The
difference in the language of the two releases alone does not require us to accept this
“strained interpretation” of the text. See Goodman v. Resolution Tr. Corp.,
7 F.3d 1123,
7 1126–27 (4th Cir. 1993). And when a settlement agreement’s text is unambiguous, as it is
here, we simply cannot rewrite its terms based on a party’s protestation that it meant
something other than what it said.
The absence of any reservation in the settlement agreement for the setoff further
supports the conclusion that the settlement agreement bars East Coast’s claims. See
Coakley & Williams Constr., Inc. v. Structural Concrete Equip.,
973 F.2d 349, 353(4th
Cir. 1992) (“[B]ecause [a] release was very broadly phrased, it seems that if the parties
intended to allow any future claims against each other, they would have done so
specifically.”). As the district court noted, the parties specifically included an exception in
the settlement agreement for retainage and could have done the same for the setoff.
Accordingly, we agree with the district court that the settlement agreement bars East
Coast’s claims.
IV.
For the foregoing reasons, the judgment of the district court is
AFFIRMED.
8
Reference
- Cited By
- 46 cases
- Status
- Published