Bain v. White
Opinion of the Court
A contract between White, of one part, and Bain and Knott of the other, provided for the drilling by the latter of a well in Hockley county, Tex. The parts of the contract having bearing upon the present controversy are:
Section 3, which provicies that the well should be sunk to a depth of 2,000 feet, unless a flow of oil, gas, or water is secured before that depth is reached; section S, which recites that J. M. Mook & Son had undertaken to drill a well that had not been carried to completion, and provides that Bain and Knott might use this hole, if they thought
The questions necessary for determination were: (1) Was the well when completed to a depth of 2,000 feet, a good clean hole? (2) If there was_a faíluré to deliver a “good clean hole” 2,000 feet deep, was this the result of White’s failure to furnish necessary piping? (3) Assuming the failure of the first well, 'did the drillers have a right to drill another, the piping to be furnished by White, and did the refusal of White to furnish additional piping, whereby the drilling of another, hole was prevented, result in loss and damage to the drillers ?
Even if the testimony of all the witnesses tendered by defendant be eliminated, it would be possible, under the rule announced, to 'sustain the finding of the court. All of the evidence which was introduced to show that the plaintiff was at any time in a position to deliver, “a good clean hole” 2,000 -feet deep is that of the plaintiff Bain and his employé, Philip Cezeaux. Both o'f these witnesses unequivocally testified that on the 18th of December, 1914, the contractors had ready for delivery to White “a good clean hole” 2,000 feet deep. If they had not testified further, and if no other evidence had been introduced, the statements would doubtless have required a judgment for plaintiffs. The effect, however, of the testimony of both witnesses, is, in large measure, destroyed by their subsequent statements. Bain testified (Record, 96): '
“About the 12th or 15th, I got a note from the driller, and he wrote roe to come out on the 18th, and he would measure the well out to me.
“Q. This pipe was still in there when you went back? . A. When I went back when? ■ - . . : .
“Q. When you went back on the 18th of September? A. They had sidetracked it. then.. :
*431 “Q. Now, yon stated that the condition of the well was such that, to leave it a few hours' with the drill stem, this pipe might run over again and obstruct tho well? A. Yes.
“Q. That was the condition when Mr. White was there in December? A. Why, I suppose it was. We had ptilled the pipe on the 18th, and he was up there on the 20th. We had the hole in good shape on the 18th.
“Q. Well, you could have measured it out to him on the 18th? A. Yes, sir.
“Qt And within an hour or two, or perhaps three or four hours, it would have been in a condition that you couldn’t have measured it. A. Well, it might. Then, again, I have known them to stand there for three months, and you go right back to the bottom. This well had a cave in it at the bottom of the 634"-”
Again he testified (Record, 104):
“Q. Then, when you reported that you were down 2,000 according to the contract, the well at that time was not a good hole on account of this casing, was It? A. It was a good hole, good and clean and down 2,000 feet.
“Q. Well, it was clean, but would you call It a good hole? A. Well, it is a good deal better hole than I drilled in lots of other places.”
Again he testified (Record, 104):
“Q. Now, when you claimed to have this contract completed, the condition of the well was such that there was a broken pipe, that had been sidetracked, that was liable to lean over in the well and obstruct it at any time? A. Well, it did do it; yes, sir.
“Q. You found that obstruction in there when you went back in January? A. Yes, sir.
“Q. It might have been in there when Mr. White came over, might it not? A. It might have been, yes, sir; but it wasn’t in there—
“Q. Now, when you pulled your drill out and stopped your drilling, it is possible that pipe leaned right back into the hole at that time? A. No, sir; I don’t think so. We had pulled It out to put on a new bit.
“Q. You had some trouble with that pipe in there before, had you? A. No, sir.
“Q. The next time you attempted to put your drill stem in, why you found it obstructed with this pipe you had sidetracked? A. After the well had stood for 10 days without any work.”
Mr. Bain testified (Record, 81):
“Well, we went on down with the well, and got down 2,000 feet We had two measurements; one measurement was .1,973 feet, and one measurement was 2.018 feet.
“Q. When was that? A. That was, I think, the 3d day of November.
“Q. Third day of November, 1914? A. 1914. Mr. White sent Mr. Walker out there to receive the well, and I told Mr. Walker I couldn’t deliver it to him; that I had twisted some pipo off.”
Philip Cezeaux, after having testified (Record, 143 et seq.) that, on the 18th of December, 1914, there was a “good clean hole,” ready for delivery, further testified (Record, 151):
“Q. Now, you were speaking about this being a good clean hole. It had a drill hit and stem in it, did it not? A. Yes, sir.”
Again (Record 152):
“Q. Were you the drill or that broke the drill stem in the hole? A. I broke it off on the 2d or 3d of November.”
The statement of plaintiff and one of his employes that, having reached a depth of 2,000 feet or more on the 18th of December, they had a clean open hole at that time, must he taken in connection with the other
When Mr. White was at the well on the 20th of December, to measure and receive the well, it was not practicable for the measurements to be made. The drill stem had been pulled up, and it would have been necessary to raise steam and do a number of hours of work before it could have been again forced to the bottom of the well. The only practicable way to measure the well was by measuring the drill stem. It was not practicable to measure it with a cord and weight. The method by which, under the rotary' process, a well is drilled, requires the presence in the well of mud, introduced from the top through the drill stem, and this mud is not totally removed until the well is finished and washed out. An ordinary plumb bob could not have penetrated this mud to the bottom, nor could a suspended joint of pipe. On account of the delay which would have been occasioned in getting the drill stem to the bottom, and then taking it out for measurement, it was agreed that the measuring of the well should be postponed until the 1st of January. When an effort was made about_that date to prepare the well for measurement, it was found that the piece of pipe which had been sidetracked had fallen into the well. Whether this was the result of the withdrawal of the drill stem, or came from some other cause, does not appear; but it was apparent that, on the 18th of December, the time plaintiff and his employé fixed as a date upon which the well was down to 2,000 feet, with a good, clean hole, the conditions were either that the sidetracked pipe had already fallen back into the hole, or that the hole could be obstructed by the falling back into it of the sidetracked pipe.
At no time thereafter was the contractor in a position to make a delivery of a good clean hole, 2,000 feet deep. When the drill stem was again put down, the obstructing pipe made it impossible for the bottom of the hole to be reached; and, notwithstanding the fact that work continued for some time thereafter, the obstruction was never passed.
The evidence fails to show that, at any time prior to the time when the contractors assumed the well to have been finished, was there any effort to secure additional casing, other than that wanted for a reduced hole. At all events, if there is evidence which may be so construed, it is in direct conflict with the testimony of White. At no time during the efforts to carry out the contract was all the available piping used. There is evidence that one or more joints twisted in two,
While the record shows that there was a cave-in, it does not indicate that the cave-in was the cause of the inability to finish the well. Apparently the difficulty was with pipe which was stuck in shale; and the shale, according to the evidence, was of a firm formation, which did not cave. The cave-in was below the pipe that could not be moved. I-t- is not made to appear that any amount of pipe of the required dimension could have met the difficulty.
. There was no suggestion, at the time of the trouble with the stuck pipe, that it resulted from any failure upon White’s part to perform his part, of the. contract. Nor was there any contention, when plaintiff was undertaking to get the well in a condition for delivery, that the trouble could be met if he would do his duty under the contract.
The facts seem to be that, exercising the option which the contract gave them, thé contractors concluded to use the old Mook well. This well had been abandoned by Mook because of the impracticability of completing it to 2,000 feet, and the difficulties which the original contractor could not overcome were not successfully met by the new contractors.
While the contractors reached a depth of 2,000 feet, and thereby, to that extent, tested the territory, and by so doing benefited the owner, yet the contract specifically provided that no payment should be made, except upon completion of the well, with a good clean hole.' The contract price was a large one. Two-thirds of the distance had already been drilled. If the well could be completed without trouble, the contract would be an exceedingly profitable one. To get the benefit of this chance, the contractors assumed risks that went against them. They are not, under the terms of the contract, entitled to anything, having failed to furnish the only thing for which White agreed to pay.
Upon the evidence submitted the trial judge held that the facts were too indefinitely developed to authorize a judgment. This statement or holding by the judge is criticized as a refusal to make a finding upon the evidence; but, in legal effect, it amounts to no more than that the plaintiffs, seeking damages upon the theory that they were entitled to recover the contract price, «less the cost of drilling a well, had failed to establish such cost. White was under obligations to furnish piping for one well, seasonably begun, but not for another, proposed to be started a year and a half after the contract was made. But if the obligation to furnish additional piping had existed, and if White breached the contract, it would be necessary to sustain the holding of the District Judge, as the evidence as to the cost of a well was conflicting.
Upon each of the propositions upon which the plaintiffs have depended, conflicting testimony was introduced, upon which the District Judge found in favor of the defendant. Under the law we would not be authorized to overrule these findings, and the judgment will have to be
Affirmed.
Reference
- Full Case Name
- BAIN v. WHITE
- Status
- Published