Opinion of the Court
Plaintiff (plaintiff in error here) brought suit to recover for losses incurred by reason of defendant’s alleged breach of contract. July 28, 1920, plaintiff agreed to manufacture and install certain bank fixtures and equipment in defendant’s bank building at a specified price, which defendant agreed to pay. The contract was in writing, and attached to it were plans and specifications of the materials to be furnished and the work to be done. It was, among oilier things, provided that, unless otherwise agreed, plaintiff should prepare and furnish any necessary measurements, and that the work under the contract should be completed by the plaintiff within four months from the delivery to and approval by defendant of such measurements, but that if the plaintiff should be delayed by reason of strikes, or other causes not necessary to recite, the time fixed for the completion oí the contract should be extended for a period equal to the time so lost.
Plaintiff alleged the existence of a strike by its workmen at the time the contract was made, and that it was thereby delayed in taking measurements, and preparing and forwarding plans to defendant, until October 25, 1920, but that it could and would have fully performed the contract within less than four months thereafter, and was prevented from doing so by the refusal of defendant to accept performance. The action was defended upon the plea that plaintiff failed to manufacture
The evidence on behalf of the plaintiff was to the effect that its agent took measurements of the bank building, and that they were approved by the defendant at or before the execution of the contract; that, almost immediately thereafter, the plaintiff made contracts with others for the manufacture of portions of the fixtures and equipment according to these measurements; that it furnished to the defendant blueprints of the measurements on the date alleged in the declaration, but that the defendant failed to return the same and refused to accept the fixtures and equipment, or to allow them to be installed, or to pay for the same. It was shown on cross-examination of plaintiff’s witness, that the measurements in question could have been prepared by a draughtsman within a day or two.
The president of the defendant bank testified that the contract would never have been entered into unless there had included in it a provision requiring the work to be completed within four months from its date; that he was assured by the company’s agent, who signed the contract, that the fixtures and equipment would be furnished within less time; that the agent of the company then and there drew the plans and specifications, and he indorsed his approval thereon; that, in reliance upon the assurances of plaintiff’s agent, alterations were made in the bank building, the old fixtures taken out,» but reinstalled because of the delay in furnishing the new equipment; and that the bank was not iñformed of the existence of the strike in plaintiff’s factory until the receipt of a letter from it, dated December 6, 1920. ■
The case was submitted to the jury, and resulted in a verdict for the defendant, and judgment was entered accordingly. The only error assigned is upon the following instruction;
“Now, with regard to the strike, if you believe from the evidence that, at the time this contract was entered into, the plaintiff’ was suffering or undergoing in its shop or place of business in St. Louis a strike, which it then knew or had reason to believe would prevent it from complying with this contract within the time provided, it was the duty of the plaintiff to communicate that fact to the defendant; and, if it failed to do it, then you may find that the plaintiff was guilty of fraud in concealing that fact, and disregard that provision of the contract entirely.”
The judgment is affirmed.