U.S. Court of Appeals for the Fifth Circuit, 1930

City of Manatee v. Gedney & Sons, Inc.

City of Manatee v. Gedney & Sons, Inc.
U.S. Court of Appeals for the Fifth Circuit · Decided June 18, 1930 · Bryan
41 F.2d 516; 1930 U.S. App. LEXIS 2831 (Federal Reporter, Second Series)

City of Manatee v. Gedney & Sons, Inc.

Opinion of the Court

BRYAN, Circuit Judge.

Appellee constructed a sewer system for tbe City of Manatee, Fla., under a contract wbicb provided for tbe payment of upwards of $240,000. Tbe city paid all tbe contract price except $4,000, and defended this suit brought by appellee to recover that amount on tbe ground that tbe work was not properly done, or that defective sewer pipe was used. In support of its defense the city proved that about a year after tbe contract was completed tbe main sewers on two streets were cracked or broken, and filled up with sand; and that there were faulty connections with tbe offsets that led to tbe bouses. Tbe city’s consulting engineer, under whose supervision tbe construction work was done, testified that if tbe sewer pipes bad been up to specifications and if tbe work bad been properly done, in bis opinion tbe sewers would have been in perfect condition. On cross-examination he stated that the foundations were good, but that it was possible that the condition found might have been brought about by a lack of side drainage or by high tides entering them from tbe river. There was no proof that tbe side drainage was insufficient or that tbe. sewers had been affected by high tides. Across tbe river tbe sewer system wbicb was built about tbe same time under similar specifications was not affected by high tides which were caused by a storm in 1926. Tbe construction contract required tbe work to be carried out according to specifications which provided that tbe contractor should not allow water to rise, during construction, in tbe trenches until the cement and mortar used in tbe joints bad hardened, and that tbe trenches should be carefully refilled with proper material after tbe mortar bad set. Testimony of other witnesses tending to show that large quantities of defective, broken, and crushed pipe were to be found in other parts of tbe sewer system was rejected on tbe ground that the conditions complained of might have been brought about by some cause other than defective work or *517material. At the conclusion of the city’s evidence, the trial court directed a verdict for the contractor for the balance claimed.

We are of opinion that there was enough evidence introduced and tendered by the city to make it a jury question whether appellee complied with the requirements of the contract in regard to the furnishing of the kind of pipe specified, and the manner of performing the work of installation. If good material was furnished and properly placed and the joints cemented together in a workmanlike manner, the jury would have been justified in concluding that the sewer system would have remained in good condition. None of the conditions which it was supposed might possibly have affected the sower system was shown to have caused the defects of which the city complains. It was undisputed, under the evidence adduced, that the foundations were good, and the fact that the high tide caused by the storm did not injuriously affect the sewer system on the opposite side of the river would seem to make less likely the theory that high water had anything to do with the breaking of sewer pipes in the city of Manatee. At least it is true, in our opinion, that reasonable men could well come to the conclusion either that the work was faulty or that the sewer pipes used were defective. We therefore think that on the showing made it was error to withdraw the case from the jury.

The judgment is reversed, and the cause remanded for further proceedings not inconsistent with this opinion.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.