United States v. Randall & Blake
Opinion of the Court
This appeal involves a suit brought under the Miller Act, 40 U.S.C. §§ 270a-270d. A supplier for a government construction project brought suit against the general contractor and its surety because the supplier was never paid in full. The district court granted summary judgment in favor of the supplier. The general contractor and its surety appeal on several grounds. We affirm in part and remand in part.
I.
The Miller Act provides protection for subcontractors and their suppliers engaged in federal construction projects. Ordinarily, these persons would be protected by state liens. State liens cannot attach, however, to federal property. To give protection to these persons, the Miller Act re
In 1979, the Army Corps of Engineers hired Randall & Blake, Inc. to construct recreational facilities at Granger Lake, Texas. As required by the Miller Act, Randall & Blake secured a payment bond from United States Fidelity & Guaranty Company (USF & G). Randall & Blake subcontracted the paving work to Austin Paving Company. Austin Paving, in turn, contracted with Geer Construction Company to supply asphalt! Between April 23, 1980 and July 22, 1980, Geer Construction supplied 6,202 tons of hot-mix asphalt to Austin Paving for use on the Granger Lake project. Austin Paving paid only some of Geer’s invoices, leaving Geer with two unpaid invoices totalling $63,634. On September 9, 1980, Geer Construction sent letter notices to Randall & Blake and USF & G informing them of Geer’s potential claim under the Miller Act.
On December 3, 1980, Austin Paving brought a Miller Act suit against Randall & Blake and USF & G, alleging that it had not been paid in full under its contract.
II.
The appellants, Randall & Blake and USF & G, challenge the timeliness of Geer Construction’s Miller Act claim. An action brought under the Act must be commenced within one year from the last day on which the claimant supplied labor or materials for the project.
Geer Construction filed its motion to intervene on May 11, 1981, within the one year limitation period. Its original complaint was not filed until the court granted the intervention on July 14,1982, well after the one year period had expired. Another two years passed until Geer filed its amended complaint. The appellants argue that the filing of the amended complaint marked the commencement of Geer’s Miller Act claim, because it was the first time that Geer properly pleaded the elements of a Miller Act claim. Specifically, they point
Rule 15(c) provides, in part:
Whenever the claim or defense asserted in the amended pleading arose out of the conduct, transaction, or occurrence set forth or attempted to be set forth in the original pleading, the amendment relates back to the date of the original pleading.
Thus, Geer’s amended complaint relates back if it asserts the same claim “set forth or attempted to be set forth ” in the original complaint. We find that Geer’s original complaint sufficiently set forth a Miller Act claim against Randall & Blake and USF & G to allow the amended complaint to relate back under Rule 15(c).
In its first complaint, Geer Construction specifically alleged that (1) it had provided asphalt to Austin Paving for use on the government project identified in Austin Paving’s complaint; (2) it had not been paid on invoices totalling $63,634; and (3) it had complied with the 90-day notice requirements of 40 U.S.C. § 270b (the Miller Act). The complaint did not specifically name USF & G as a defendant nor specifically request relief under the Miller Act. The complaint did, however, incorporate by reference the first five paragraphs of Austin Paving’s complaint. Those paragraphs specifically alleged that the action arose “under the Miller Act” and that USF & G was a defendant.
The allegations of the complaint, both explicit and incorporated by reference, were adequate to notify the appellants that they were being sued under the Miller Act. The complaint clearly set forth the three substantive elements of a Miller Act claim: the supplier supplied materials, the supplier was not paid, and the supplier intended the materials to be used on the government’s project.
The only specific pleading requirement imposed by the Miller Act is that the action be brought in the name of the United States.
The appellants argue that even if the amended complaint relates back to the original complaint, the action is still untimely because the original complaint was not filed until after the expiration of the limitation period. They refer us to Rule 3 of the federal rules. This rule provides: “A civil action is commenced by filing a complaint with the court.” Geer Construction argues, in response, that the limitation period should have tolled when it filed its motion to intervene, which was filed before the expiration of the limitation period. We have found no appellate decision that addresses this question. We have found, however, almost unanimous agreement among the district courts addressing the question: the filing of the motion for intervention, and not the later approval of the motion and actual filing of the complaint, determines the commencement of the action for purposes of the statute of limitations.
III.
The appellants contend that there are factual disputes in this case that should have precluded a summary judgment. The district court found none and neither do we. Geer Construction supported its motion for summary judgment with convincing documentary evidence, affidavits, and depositions. The parties do not dispute that Geer Construction provided the amount of asphalt that it claims to have provided. The parties do not dispute that Austin Paving failed to pay all of Geer’s invoices.
The only apparent dispute concerns the price of the asphalt. Geer’s proposal to Austin Paving and every invoice show that the agreed price for the asphalt was $16 per ton f.o.b. Austin Paving has admitted that it owes that amount. Nevertheless, the appellants contend that the actual price was $14 per ton and that the documents between Geer and Austin Paving were back-dated to indicate a higher figure. There is absolutely no evidence in the record that substantiates the claim of backdating or otherwise suggests that the price of the asphalt was other than $16 per ton. Indeed, appellants’ own evidence rebuts their contentions. Randall & Blake introduced copies of their own correspondence in which Austin Paving requested an additional allowance on its subcontract because Geer was charging $16 per ton for asphalt instead of $14 as earlier estimated. Randall & Blake refused the allowance because it contended that its contract with Austin Paving did not provide for cost escalations. Whether Randall & Blake is liable to Austin Paving for the higher price of the asphalt is of no relevance to this action. The relevant question in this Miller Act claim is how much did Austin Paving agree to pay to Geer Construction.
We have often noted the appropriateness of summary judgments in Miller Act cases: “when a movant makes out a convincing showing that genuine issues of fact are lacking, we require that the adversary adequately demonstrate by receivable facts that a real, not formal, controversy exists, and, of course, he does not do that by mere denial or holding back evidence.”
Randall & Blake makes one final objection to the summary judgment: the failure of Geer’s amended complaint to pray expressly for relief against Randall & Blake. It is too late for Randall & Blake to complain about this omission. When Geer filed its amended complaint, Randall & Blake answered. Geer’s motion for summary judgment expressly requested a judgment against Randall & Blake, but Randall & Blake did not object on the grounds that it had not been made a defendant. Rule 15(b) of the federal rules provides: “When issues not raised by the pleadings are tried by express or implied consent of the parties, they shall be treated in all respects as if they had been raised in the pleadings.” By answering the amended complaint, by resisting the summary judgment motion, and by not complaining about the defect earlier, Randall & Blake conceded that it was a defendant to Geer’s complaint. The summary judgment against it was proper.
IV.
The appellants challenge the district court’s award of prejudgment and post-judgment interest to Geer Construction. The district court granted prejudgment interest at the rate of one and one-half percent per month on the amount of $1000 and one percent per month on the balance of $62,634, based on the interest charges specified on the two unpaid invoices, and post-judgment interest at the “legal rate”. The appellants argue that the court erred because their was no agreement for interest; if there was, it was only for a single one percent charge; the rates awarded are usurious under Texas law; and the award of postjudgment interest at the legal rate is vague and unenforceable. Alternatively, they request that this Court certify the question of interest to the Texas Supreme Court. We deny the request for certification and remand on the issue of usury.
Because the right that Geer asserts in this action is provided by the Miller Act, the scope of the remedies afforded that right is a question of federal law.
Texas law provides that prejudgment interest accrues on a contractual debt at the rate agreed to by the parties.
Appellants argue that the contractual rate cannot be imposed because it is usurious. The monthly rates charged by Geer Construction compute to annual rates of twelve and eighteen percent. At the time Geer sent its invoices, the maximum rate of interest that could be charged to a non-corporate debtor was ten percent;
On remand, if the district court concludes that Austin Paving is a corporation, the appellants’ challenge of usury fails and the prejudgment interest award stands. If the district court concludes otherwise, the appellants are not liable for prejudgment interest. Under Texas law, Geer could not recover usurious interest from Austin Paving.
The appellants question the award of postjudgment interest at the legal rate. This rate is set by 28 U.S.C. § 1961, which, since 1982, has provided for a uniform federal rate of postjudgment interest on all judgments entered in federal courts.
We have considered all the arguments raised by the appellants, whether or not discussed in this opinion. The judgment of the district court is REMANDED for determination of prejudgment interest and AFFIRMED in all other aspects.
. 40 U.S.C. § 270a(a)(2) (1982).
. 40 U.S.C. § 270b (1982).
. The complaint was brought in the name of J.R. Canion d/b/a Austin Paving Company.
. We limit our consideration on this appeal to those issues presented in the case between Geer Construction and Randall & Blake and USF & G. The appellants attempt to raise, other issues concerning the claims against Austin Paving. These issues are not before us because they arise in that portion of the proceedings for which there has been no fined judgment.
. 40 U.S.C. § 270b(b) (1982).
. United States v. Fidelity and Deposit Co., 813 F.2d 697, 699 (5th Cir. 1987); see also United States ex rel. Harvey Gulf Int'l Marine, Inc. v. Maryland Casualty Co., 573 F.2d 245, 247 (5th Cir. 1978).
. United States ex rel. Carlson v. Continental Casualty Co., 414 F.2d 431, 433 (5th Cir. 1969).
. Blanchard v. Terry & Wright, Inc., 331 F.2d 467, 469 (6th Cir.), cert. denied, 379 U.S. 831, 85 S.Ct. 62, 13 L.Ed.2d 40 (1964).
. We are unconvinced by USF & G’s protestations that it did not have notice because the first complaint failed to name it as a defendant. The caption of the complaint named USF & G as a defendant. The complaint incorporated by reference the third paragraph of Austin Paving's complaint, which does expressly name USF & G as a defendant. USF & G thought it was a defendant; it answered Geer’s original complaint.
. 40 U.S.C. 270b(b) (1982).
. Hendry Corp. v. American Dredging Co., 318 F.2d 299, 301 (5th Cir. 1963).
. E.g., Hendry Corp. v. American Dredging Co., 318 F.2d 299, 301 (5th Cir. 1963); Blanchard v. Terry & Wright, Inc., 331 F.2d 467, 469 (6th Cir.), cert. denied, 379 U.S. 831, 85 S.Ct. 62, 13 L.Ed.2d 40 (1964); 6 Wright & Miller, Federal Practice and Procedure § 1551 at 689 (1971).
. E.g., DiCostanzo v. Chrysler Corp., 71 F.R.D. 223, 224 (D.Mass. 1976); Braxton v. Virginia Folding Box Co., 72 F.R.D. 124, 126 (E.D.Va. 1976); SEC v. Keller Bros. Securities Co., 30 F.R.D. 532, 533-34 (D.Mass. 1962); Jack v. Travelers Ins. Co., 22 F.R.D. 318, 319 (E.D.Mich. 1958).
. See United States ex rel. Carter Equip. Co. v. H.R. Morgan, Inc., 554 F.2d 164 (5th Cir. 1977);
. United States ex rel. Carlson v. Continental Casualty Co., 414 F.2d 431, 435 (5th Cir. 1969); Bruce Construction Corp. v. United States, 242 F.2d 873, 875 (5th Cir. 1957).
. F.D. Rich Co. v. United States ex rel. Industrial Lumber Co., 417 U.S. 116, 127, 94 S.Ct. 2157, 2164, 40 L.Ed.2d 703 (1974); United States ex rel. Harvey Gulf Int'l Marine, Inc. v. Maryland Casualty Co., 573 F.2d 245, 247 (5th Cir. 1978); United States ex rel. Carter Equip. Co. v. H.R. Morgan, Inc., 554 F.2d 164, 166 (5th Cir. 1977).
. United States ex rel. Georgia Electric Supply Co., 656 F.2d 993, 997 (5th Cir. Unit B 1981).
. Id.
. Tex.Rev.Civ.Stat.Ann. art. 5069-1.03 (Vernon Supp. 1987); Delta (Delaware) Petroleum & Energy Corp. v. Houston Fishing Tools Co., 670 S.W.2d 295, 297 (Tex.Civ.App. 1983).
. Preston Farm & Ranch Supply, Inc. v. BioZyme Enterprises, 625 S.W.2d 295, 298 (Tex. 1982); Delta (Delaware) Petroleum & Energy Corp. v. Houston Fishing Tools Co., 670 S.W.2d 295, 297 (Tex.Civ.App. 1983).
. Tex.Rev.Civ.Stat.Ann. art. 5069-1.04 (Vernon 1971);
. Tex.Rev.Civ.Stat.Ann. art. 1302-2.09 (Vernon 1980).
. Although Austin Paving brought its complaint in the name of J.R. Canion and J.R. Canion, Jr., a partnership d/b/a Austin Paving, other evidence in the record indicates that Austin Paving is a registered corporation in the State of Texas. The appellants argue that the allegations of Austin Paving in its pleadings are binding on this Court. We do not agree because Austin Paving is not a party to this appeal, nor a party to the action between Geer and the appellants. The issue remains a disputed question of fact that must be resolved by the district court.
. First State Bank of Bedford v. Miller, 563 S.W.2d 572, 576 (Tex. 1978); Wall v. East Texas Teachers Credit Union, 533 S.W.2d 918, 921 (Tex. 1976).
. 40 U.S.C. § 270b(a); see United States ex rel. Carter Equip. Co. v. H.R. Morgan, Inc., 554 F.2d 164, 165 (5th Cir. 1977); United States ex rel. Carlson v. Continental Casualty Co., 414 F.2d 431, 433 (5th Cir. 1969).
. We do not suggest that Randall and Blake and USF & G are entitled to claim the full panoply of usury defenses and penalties provided by Texas law. The penalty provisions of the usury laws — forfeit of principal, attorney’s fees, etc. — are strictly personal to the immediate borrower, in this case Austin Paving, and are not afforded to guarantors and sureties such as Randall & Blake and USF & G. See Houston Sash & Door Co. v. Heaner, 577 S.W.2d 217, 222 (Tex. 1979).
Because the question of interest can be resolved without deciding an important, unsettled, and controlling issue of Texas law, certification is not appropriate. See Florida ex rel. Shevin v. Exxon Corp., 526 F.2d 266, 274-76 (5th Cir.), cert. denied, 429 U.S. 829, 97 S.Ct. 88, 50 L.Ed.2d 92 (1976).
. See Reaves v. Ole Man River Towing, Inc., 761 F.2d 1111, 1113 (5th Cir. 1985).
Reference
- Full Case Name
- UNITED STATES of America, for the Use and Benefit of J.R. CANION, and Odell Geer Construction Co., Inc., Intervening v. RANDALL & BLAKE, and United States Fidelity & Guaranty Co.
- Cited By
- 7 cases
- Status
- Published