U.S. Court of Appeals for the Fifth Circuit, 2016

Lake Eugenie Land & Development, Inc. v. BP Exploration

Lake Eugenie Land & Development, Inc. v. BP Exploration
U.S. Court of Appeals for the Fifth Circuit · Decided October 17, 2016 · Clement, Owen, Prado
669 F. App'x 704

Lake Eugenie Land & Development, Inc. v. BP Exploration

Opinion of the Court

PER CURIAM: *

The Andry Law Firm, LLC (“Andry”) moved the district court to enforce its purported settlement with BP Exploration & Production, Inc. (“BP”) and “order the Claims Administrator to promptly pay [Andry’s] final award in the amount of $7,818,693.95.” The district court summarily denied Andry’s motion. Andry appeals, *705asserting that this court has appellate jurisdiction pursuant to 28 U.S.C. § 1291.

Section 1291 “generally vests courts of appeals with jurisdiction over appeals from final decisions of the district courts.” Cunningham v. Hamilton Cty., 527 U.S. 198, 203, 119 S.Ct. 1915, 144 L.Ed.2d 184 (1999) (internal quotation marks omitted). A decision is final when “it ends the litigation on the merits and leaves nothing for the court to do but execute the judgment.” Id. at 204, 119 S.Ct. 1915 (internal quotation marks omitted). The district court’s decision here is not a final decision because it clearly does not end the litigation between Andry and BP. The decision simply allows the Claims Administrator to comply with the district court’s previous order “to process the claim in accordance with its applicable rules and policies.”

We therefore DISMISS this appeal for lack of appellate jurisdiction.

Pursuant to 5th Cir. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5th Cir. R. 47.5.4.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.