Papalote Creek II, L.L.C. v. Lower Colorado River
Papalote Creek II, L.L.C. v. Lower Colorado River
Opinion
Papalote Creek II, LLC (Papalote) appeals the district court's order compelling Papalote to arbitrate a dispute raised by Lower Colorado River Authority (LCRA)-whether their contractual agreement limits LCRA's liability to $60 million. The arbitration clause requires Papalote and LCRA to arbitrate "any dispute [that]
*452 arises with respect to either [p]arty's performance." Because the dispute that LCRA has raised is an interpretative dispute-not a performance dispute-we reverse and remand.
I.
This is the second time Papalote and LCRA have appeared before us.
See
Lower Colo. River Auth. v. Papalote Creek II, LLC
,
In December 2009, LCRA entered into a Power Purchase Agreement [ (Agreement) ] with [Papalote]. Papalote planned to build an 87-turbine wind farm in Texas ..., and under the [Agreement], LCRA agreed to purchase all of the energy ... at a fixed price for an 18-year term.
Relevant to this appeal are four sections of the [Agreement]: § 4.3, § 9.3, § 13.1, and § 13.2. First, § 4.3, which is entitled "Liquidated Damages Due to [LCRA's] Failure to Take," provides a formula for how to calculate the liquidated damages that LCRA would owe to Papalote in the event that LCRA failed to take all of the Project's energy. As noted above, LCRA is required to take all of the energy generated by the Project. However, should LCRA fail to do so, § 4.3 details how to calculate Papalote's "exclusive remedy" of liquidated damages. This liquidated damages calculation would depend in part on the difference between the [Agreement's] fixed price and the price that Papalote is otherwise able to obtain in selling the energy.
Second, § 9.3, which is entitled "Limitation on Damages for Certain Types of Failures," provides the following: [Papalote's] aggregate liability for [its failure to construct and operate the wind farm by the agreed-upon date] shall be limited in the aggregate to sixty million dollars ($60,000,000). [LCRA's] damages for failure to perform its material obligations under [the Agreement] shall likewise be limited in the aggregate to sixty million dollars ($60,000,000)....
Finally, § 13.1 and § 13.2 provide a two-step arbitration procedure. The first step, as dictated in § 13.1, requires, inter alia, that "[i]f any dispute arises with respect to either Party's performance hereunder," the senior officers of LCRA and Papalote meet in an attempt to resolve the dispute. Under the second step, as outlined in § 13.2, if the dispute is not resolved through the first step within a certain timeframe, either party may submit that dispute "to binding arbitration[.]" ...
Papalote completed construction of the Project in 2010, and in the ensuing years, LCRA complied with its obligations under the [Agreement] by purchasing all of the energy generated by the Project. In April 2015, however, LCRA initiated discussions with Papalote regarding the [Agreement].... [I]n June 2015, LCRA sent Papalote a letter stating that, pursuant to § 13.2, LCRA was "initiat[ing] the arbitration process to resolve the dispute between LCRA and Papalote regarding LCRA's limitation of liability under the [Agreement] and its impact on LCRA's performance obligations." LCRA also noted that it "intends to continue to fully perform its obligations under the [Agreement] during this arbitration process." ... Papalote rejected LCRA's request to proceed to arbitration, reasoning that "[a]n academic *453 question about the damages LCRA might owe for a hypothetical breach simply does not constitute a 'dispute' that is proper for arbitration under the [Agreement]." Papalote also argued that a dispute over LCRA's potential liability limitation was not covered by the arbitration provision in the PPA, which was limited to disputes regarding performance obligations.
Following Papalote's refusal to arbitrate, LCRA filed a petition to compel arbitration in Texas state court on June 30, 2015. Papalote timely removed the petition to federal district court on the basis of diversity jurisdiction.... In February 2016, the district court granted LCRA's petition to compel arbitration.... [T]he district court framed the question as "whether the dispute LCRA seeks to arbitrate-whether or not LCRA's liability would be capped at $60 million in the event it elected to purchase from Papalote less than the total amount of energy it contracted to buy-qualifies as a dispute 'with respect to either Party's performance' under the [Agreement]." In answering that question, the district court recognized that, "in a certain sense, one could understand 'performance' to concern only those promises which were the essence of the [Agreement]-the sale and production of wind energy-and conceptualize the buyer's obligation to pay for failing to take as compensation for its failure to perform, rather than as an independent performance obligation." The district court reasoned, however, that "the better view here ... is that LCRA's bargained-for-obligation to pay Papalote a specified sum if LCRA takes less than all of the energy produced is itself a performance obligation under the [Agreement]."
Although Papalote appealed the order compelling arbitration, the district court denied a stay of arbitration pending appeal.
In the previous appeal, Papalote argued that LCRA's dispute: (1) was not ripe when the district court compelled arbitration; and (2) was outside the scope of the arbitration clause. We agreed with Papalote that the dispute was not ripe because LCRA was still taking energy from Papalote when the district court compelled arbitration.
On remand, the district court dismissed LCRA's initial suit concerning its petition to compel arbitration. In Papalote's separate suit to vacate the arbitration award, the district court lifted the stay, and LCRA filed a cross-motion to affirm the arbitration award and, alternatively, to compel another arbitration. Consistent with this court's judgment in Papalote I , the district court vacated the arbitration award as it was the fruit of an order that the district court had entered without subject matter jurisdiction. However, holding that the dispute was now ripe and again concluding that the dispute fell within the scope of the arbitration clause, the district court once again compelled arbitration. Papalote appeals, contending that LCRA's dispute is outside of the scope of the arbitration clause.
II.
A.
We review
de novo
whether the district court properly compelled arbitration.
Hays v. HCA Holdings, Inc.
,
Determining the scope of an arbitration clause is a matter of contract.
Hebbronville Lone Star Rentals, LLC v. Sunbelt Rentals Indus. Servs., LLC
,
The parties may agree upon a broad language in the arbitration clause either by incorporating "[t]he standard
*455
broad arbitration provision recommended by the American Arbitration Association" or by creating their own broad provision.
United Offshore Co. v. So. Deepwater Pipeline Co.
,
Alternatively, the parties may agree upon a narrow language in the arbitration clause by deviating from the broad standard provisions and by limiting arbitration only to a subset of disputes that may arise out of the contract.
See
United Offshore
,
We have previously observed that if an arbitration clause "restricts [the arbitrator's] power to an interpretation of the contract, it leaves the arbitrator powerless to decide matters on which the agreement is silent."
United Offshore
,
The opposite is also true: If the arbitration clause limits arbitration to performance-related disputes, then the arbitrator cannot decide other matters, such as interpretative disputes.
Cf.
Negrin
,
We can imagine a case in which both parties agree that for example some form of notice is a condition precedent to performance, and the only dispute is over whether the notice was given. That dispute would be arbitrable if the arbitration clause included performance disputes, not if it did not.
Selcke v. New England Ins. Co.
,
Here, Papalote and LCRA agreed to submit to binding arbitration "[i]f any dispute arises with respect to either Party's performance." This clause clearly signifies the parties' intent to limit arbitration to performance-related disputes only, and the arbitration clause neither requires nor authorizes arbitration of disputes that are not performance-related disputes, such as disputes related to the interpretation of the Agreement.
B.
Because the Agreement limits arbitration to "any dispute [that] arises with respect to either Party's performance," LCRA's dispute-whether the Agreement limits LCRA's liability to $60 million-is arbitrable only if it constitutes a dispute with respect to either LCRA's or Papalote's performance. We hold that LCRA's dispute is a dispute related to the interpretation of the Agreement, not a performance-related dispute, and thus does not fall within the scope of the Agreement's arbitration clause.
Interpretative disputes arise when the parties disagree over a text's meaning. See Interpretation, Black's Law Dictionary (10th ed. 2014) ("The ascertainment of a text's meaning[.]"). Here, LCRA's own demand letter to Papalote frames LCRA's dispute as an interpretative dispute: The letter states that "[t]he dispute is whether LCRA's liability is limited to $60,000,000 under the [Agreement's § 9.3]." And even LCRA's brief on appeal observes that this dispute is "about the meaning of the [Agreement's] liability limitation." LCRA's Br. at 35 (emphasis added).
As Papalote points out, one needs only to examine the Agreement to determine what the Agreement says and means, and what LCRA and Papalote had intended while drafting the Agreement.
See
Selcke
,
In resisting this conclusion, LCRA heavily relies on the phrase "with respect *457 to," which, it contends, means "relating to." LCRA argues that, because the interpretative dispute " relat [ es ] to LCRA's ongoing and future performance under the [Agreement]," the interpretative dispute is a dispute "with respect to" performance. However, § 9.3 is a damages provision, not a provision about performance, and LCRA's interpretative dispute is with respect to damages, not performance. Therefore, even if we agree with LCRA's broad reading of the phrase "with respect to," LCRA cannot prevail. Because LCRA's interpretative dispute is outside the scope of the arbitration clause, the district court erred in compelling Papalote to arbitrate.
III.
For the foregoing reasons, we REVERSE the district court's order compelling arbitration and REMAND for further proceedings consistent with this opinion.
We are not alone in making this observation. The previous panel of this court has made similar observations-albeit in dictum-that this dispute revolved around interpretation.
See
Papalote I
,
Reference
- Full Case Name
- PAPALOTE CREEK II, L.L.C., Formerly Known as Papalote Creek Windfarm II, L.L.C., Plaintiff-Appellant, v. LOWER COLORADO RIVER AUTHORITY, Defendant-Appellee.
- Cited By
- 17 cases
- Status
- Published