Kingrey v. New York, C. & St. L. R. Co.
Kingrey v. New York, C. & St. L. R. Co.
Opinion of the Court
Plaintiff brought this suit to recover
for personal injuries received by him while employed as a riveter in the erection of a bridge at Cleveland, Ohio, over the railroad right of way, for eliminating grade crossings. The injuries were received
The collision was caused by an awning or sunshade which project- ' ed from the side of the cab, about 1% inches when up and 11 inches or more when down. The grounds Of alleged negligence charged included (in addition to several others) failure to sound whistle, signal, or warning, or to maintain watchmen or flagmen, for the purpose of apprising plaintiff of the approach of the train, or at a sufficient distance from the work to warn the oncoming train of plaintiff’s dangerous position, and in operating the train with a cab awning so projecting over the rails as to be likely to strike plaintiff. The claimed errors on the part of the trial court, as summarized in plaintiff’s brief, will be referred to in their order.
The specific instruction requested previous to the giving of the charge (and to whose refusal exception was taken) was that the plaintiff “was an invitee on the tracks, and it was the duty of the railroad company to exercise ordinary care not ,to injure such invitee, and after they knew or ought to have known of the presence of the plaintiff, they must exercise reasonable care not to interfere with him.” This request was denied, for the reason that it was understood by the court to mean that defendant “ought to have known of plaintiff’s position there, and in the light of that knowledge ought to have taken some definite form of precaution”; the judge adding that he could not “give that as a binding instruction.” No suggestion was made that the court misconceived the meaning of the request. On the contrary, at the conclusion of the charge, counsel suggested an instruction (also refused against exception) “that, because the plaintiff was invited to be at the place and at work there, they [defendant] must take cognizance of the fact and be held to have knowledge of the fact.”
“The only time we asked for any protection, for the workmen for our own self-protection from the railroad company was when we had our equipment 15 * * fouling the main line during the course of the erection of steel only. When driving rivets, * * * every man was cautioned by myself, and we were all to be on the lookout for any trains or anything» that might come along and hit the scaffold at any time.”
He says, also, that he ordered the men to keep a lookout for the trains when they were driving rivets, that there were nine men other than plaintiff who were to be looking out, and that the foreman was absolutely to look out for them too. Plaintiff testified that, when a scaffolding was swung down from an overhead bridge like that, and he knew a train was coming, they would always pull the scaffold up until the train went by; that, had they known the train was coming, he would have pulled the scaffold up higher, so as to give greater clearance than was then had; also that he would have gotten out of the way — grabbed the column on the lacings; that up to that morning they had.been the only riveting gang on that particular job, and that he had not done any riveting on that job before that morning (it is inferable that the colliding train came through within about half an hour after plaintiff began work); and that the boss was usually staying on the job and “would holler when a train was coming.” He also said that he had seen a passenger train go east that morning, but that he did not hear the engine in question before it came, and did not know that the train which caused the collision was coming.
The jury was instructed that if the ordinary method of operation which the plaintiff was carrying on, and of which defendant knew or should have known, was safe in the operation of the ordinary and usually equipped rolling stock, it would owe the further duty not to-operate such rolling stock past the scaffold where plaintiff was working equipped in a different way, which might add different hazards,. without taking further and additional precautions by way of lookout on the train or giving notice to plaintiff. The context indicates that by “equipped in a different way” reference was made to the cab awning. We see nothing to criticize in the use of the words above italicized. In view of the state of the evidence, we think the charge as given was sufficiently favorable to plaintiff in the respects under consideration.
“If one comes into court and aslrs that a jury or court award to Mm a judgment, the effect of which is to transfer property from the possession of one man to another, it is the law that he is entitled to have it only when by the greater weight of the evidence he satisfies 12 men that he is entitled to have some one else’s property turned over'to him in satisfaction of Ms claim of this injury.”
No exception was taken to this instruction. The criticism of the word “satisfies” we think not well made. The jury should be satisfied of the correctness of its conclusions both in criminal and in civil
The judge gave a careful charge, and at considerable length. We cannot think that he intended to “charge the plaintiff out of court.” Upon a consideration of the entire record of the trial, we are unable to say that there has been a miscarriage of’ justice, that the plaintiff was there denied a fair trial, or that, unless for denial of motion for new trial, plaintiff is entitled to a reversal of the judgment.
Presumably these contentions were forcibly pressed on the trial. The judge, in denying the motion for a new trial, said: “The fact is that this unfortunate plaintiff owes his injuries to his own neglect.” Defendant introduced, on the trial, testimony of a witness that at the time of the collision the cab awning was not down, but was “right up tight to the cab,” as well as the testimony of another witness that the awning was but halfway up, and so projected about 7 or 8 inches from the cab. If either of these statements was true, the collision could not have occurred unless the planks extended further into the clearance space than asserted by witnesses, apparently well informed of the facts, as might have occurred in the absence of spreader bolts.
One Bolán, who admittedly was working with plaintiff on the platform when the collision occurred, but who did not attend the trial,, made affidavit, presented upon the motion for new trial, that pursuant to a promise to plaintiff to attend the trial (without subpoena) he arrived in,Cleveland — from Pittsburgh — the day before the trial was
Bolan’s affidavit further states that when plaintiff was injured there was a clearance of about 15 inches between the scaffold and the cab; that the awning was down and projected at least 16 inches from the side of the cab; that the train approached without sounding bell or whistle, and that he had no warning of its approach; that the construction foreman did not give plaintiff or any one else any warning to look out for any train (plaintiff does not seem to have disputed the foreman’s testimony, which was given after plaintiff had testified); that the train in question was running about 15 miles an hour, and was not in sight when the driving of the particular rivets on which they were engaged was commenced; that the scaffold was at no time lowered on the day in question, as was testified to by at least two witnesses; that the two inner planks were securely fastened, and that the four planks were about 6 feet long and extended about 5 inches over the needle beams. There was presented an affidavit of another person who says he and another named man built the scaffold in question, and worked continuously on the job from that time until plaintiff’s accident, and were present when it occurred; that the planks used were but 6 feet long and extended only 4 inches over the sides of the needle beams; that the center planks had safety bolts, which prevented the planks and scaffolding from moving; that he removed some bolts from one of the planks knocked off by -the collision and assisted in removing plaintiff to the hospital; that there was at least 18 to 20 inches’ clearance between' the planks and the sides of the passing train; that the awning was down at the time-of the accident; that the scaffold was not lowered on the morning of the accident, nor at any time after its construction. There were also affidavits by three persons by way of impeachment of the testimony of one of defendant’s witnesses. The contents of two other affidavits call for no mention.
Defendant made no response to these affidavits or to the motion for new trial. Its counsel say in brief that the court disposed of the motion sua sponte, without notice to counsel on either side. Defendant’s counsel characterize appellant’s charge as “preposterous and unthinkable on its face.” - We think the motion should not have been denied without showing that defendant’s claim agent did not commit the asserted misconduct. We appreciate that the charge of misconduct may be utterly untrue in fact, but we think it cannot be pronounced, as matter of law, on its face preposterous (and unthinkable. Granting
Granting, for the purposes of this opinion, that, except as the motion involved defendant’s alleged responsibility through its agent for the asserted fraud and contempt of the trial court, we should be inclined to regard the motion as addressed to the discretion of the Judge, and thus not reviewable, because denied in the exercise of judicial discretion, we think the dismissal of the application without examination of the truth of the alleged fraud and contempt of court was not matter of discretion. As the merits of the application have not been inquired into, the judgment should not be reversed merely for failure to make such inquiry; to do so would be to punish defendant without hearing. But we think due regard for the\ administration of justice requires that such hearing be had.
Following the precedent in Wolf v. United States (C. C. A. 6) 292 Fed. 673, 678, 679, and Hindman v. United States (C. C. A.) 292 Fed. 679, 683, the judgment of the District Court is affirmed, with instructions to hear and decide the motion for new trial, if re-presented within 10 days from the going down of mandate, upon giving defendant opportunity to be heard-thereon, and, if it be made to appear that defendant’s agent or representative has been guilty of the asserted misconduct, to set aside the judgment and grant a new trial. Unless such misconduct shall appear, the motion for new trial is submitted to the sound discretion of the court; subject to the contingencies above provided, the existing judgment to stand. The costs of this court will be divided.
“Track” apparently does not mean “rail,” but “train” or track clearance.
070rehearing
On Motion for Rehearing.
Plaintiff in error asks a rehearing and a reversal of the judgment upon the sole ground that the trial court did not deny a motion for new trial sua sponte, and without notice to counsel for either side, as stated in brief of defendant in error and recited in our opinion, but that the motion was not disposed of until more than 60 days after it was filed, nor until long after the rule period for making reply had expired.
We think, however, that our order of affirmance should stand, subject to hearing and decision of motion for new trial. We think wé should presume that failure to reply was not intended as an admission of the truth of the fraud and contempt of court charged, but rather that it was due to a belief, as now claimed by counsel, that the charge was “preposterous and unthinkable on its face,” which proposition, we think, should not be accepted as matter of law. If the asserted charge of misconduct of defendant’s representative is found, to be true, a new trial should be granted; if found untrue, upon actual hearing on the merits, in view of what is said in our previous opinion, we should not feel warranted in imperatively ordering a new trial.
Petition for rehearing denied.
Reference
- Full Case Name
- KINGREY v. NEW YORK, C. & ST. L. R. CO.
- Status
- Published