United States of America Ex Rel. Dover Elevator Company, Etc. v. General Insurance Company of America, a Washington Corporation
Cases that cite this one
14 later published cases cite this decision. The 13 that cite it most often are listed here.
- United States of America v. Forrest B. White, JR. Masonry, Inc. (District Court, W.D. Kentucky 2020)
- United States v. Fidelity and Deposit Company of Maryland (5th Cir. 1987)
- United States ex rel. Texas Bitulithic Co. v. Fidelity & Deposit Co. (5th Cir. 1987)
- Hanover Area Sch. Dist. v. Sarkisian Bros., Inc. (District Court, M.D. Pennsylvania 1981)
- American Masons' Supply Co. v. F. W. Brown Co. (Conn. 1978)
- United States v. Gullard (9th Cir. 1974)
- United States of America, for the Use and Benefit of Material Service Division of General Dynamics Corporation v. The Home Indemnity Company (7th Cir. 1973)
- United States v. Continental Casualty Company (United States District Court Eastern District of Louisiana 1973)
- United States Ex Rel. R. Rudnick & Co. v. Daniel, Urbahn, Seelye & Fuller (District Court, N.D. Illinois 1973)
- United States ex rel. Moritz v. Merle A. Patnode Co. (District Court, E.D. Wisconsin 1971)
- Sam Finley, Inc. v. Pilcher, Livingston & Wallace, Inc. (United States District Court for the Southern District of Georgia 1970)
- United States Ex Rel. Benefit of T Square Equipment Corp. v. Gregor J. Schaefer Sons, Inc. (District Court, E.D. New York 1967)
- Tony Delduca, Doing Business as Delduca Trucking Service v. United States Fidelity & Guaranty Company (5th Cir. 1966)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion
This action was brought in the District Court under the Miller Act, 1 by a materialman against a bonding company, to recover the value of materials furnished on a public improvement. The defense was that the action was not brought prior to “the expiration of one year after the date of final settlement of such contract,” as required by Section 270b (b) of the Act which was in force at the time the contract was entered into.
The Miller Act was amended by Public Law 86-135, effective August 4, 1959, so as to provide for the filing of suit not later than one year from the date on which the last labor was performed or material furnished by the claimant. The purpose of the amendment was to eliminate all responsibility of the Government for fixing dates on which the period for filing suits against Miller Act Payment Bonds commences to run. U. S. Code Congressional and Administrative News, 86th Cong. 1st Sess. p. 1995 (1959).
The prime contract and the bond were dated June 22, 1959, which was prior to the amendment of the Act. If the Act prior to its amendment is applicable, it is conceded that plaintiff’s suit was untimely since it was not brought within one year from the final settlement of the contract. It was brought, however, within one year after the last material was furnished, which was timely under the amendment.
It is settled that the Act in force at the time of the execution of the contract controls. Title Guaranty & Surety Co. v. United States to the Use of Harlan & Hollingsworth, 228 U.S. 567, 33 S.Ct. 614, 57 L.Ed. 969 (1913).
The limitation provided in the Act was not to be treated as an ordinary statute of limitation. The Act created a new right and prescribed the remedy therefor. The filing of suit within the limitation period was a condition precedent to the exercise of the right. United States ex rel. Texas Portland Cement Co. v. McCord, 233 U.S. 157, 34 S.Ct. 550, 58 L.Ed. 893 (1914); United States ex rel. Soda v. Montgomery, 253 F.2d 509 (C.A.3, 1958); United States for the Use and Benefit of General Electric Co. v. Southern Construction Co., 229 F. Supp. 873 (W.D.La., 1964).
Section 3 of Public Law 86-135 provided :
“The rights of laborers and ma-terialmen under contracts entered into before the effective date of this amendment shall not be affected.”
We construe this language to mean that the rights of claimants under existing contracts were not to be affected by the amendment.
The fact that the payment bond, although dated June 22, 1959, was not accepted by the Government until August 5, 1959, did not impair the rights of the parties. The contractor was *196 bound under his contract on June 22, 1959, and was required to furnish the bond.
In our opinion the District Judge was correct in dismissing the complaint.
Affirmed.
. 40 U.S.C. § 270a et seq. as amended.