Wm. N. Flynt Granite Co. v. Darling
Wm. N. Flynt Granite Co. v. Darling
Opinion of the Court
In January, 1908, E. W. Darling, the plaintiff below, made an agreement with Wm. N. Elynt Granite Company, a corporation, to unload from cars in East St. Louis, to cart to and set all the cut granite in the bank and office building on the northeast corner of Broadway and Pine streets in St. Louis for $18,300. The granite company promised to pay Darling this amount for these services, that the granite should be cut ready for setting, that the company would do any necessary fitting and would furnish shipping receipts and schedules of the stone shipped in advance of its arrival in East St. Louis. Darling set the granite and then sued the company for a balance due him under the contract and in a second count for damages for delaying him 57 days at an expense of $116 a day in the completion of his work caused by the company’s failure to deliver the granite in the time and manner it had agreed to furnish it. The granite company denied all liability for this delay, and there was a verdict and judgment for $1,160 against it on this second count. On the trial of this issue of delay the plaintiff below was on the stand with the time books of his emplo’yés in his hands. He had testified that he had been out of the city where the work was being done during the time he claimed that the granite company had caused the delay and the unnecessary expense of .his employés for which he was seeking to recover damages, at one time as long as 18 days, and altogether about 80 days, that his foreman, John McBeth, had been present daily and had made the entries in the time books, and that McBeth was in the city where the trial was conducted. Thereupon counsel for the granite company objected to the competency of Darling to testify to the entries in the time books or from them, and these objections were overruled, and the cbmpany excepted. The objection was well founded. The witness was not competent to verify entries in the time books or to testify from them as memoranda because he did not make them at the times of the transactions they record, he was not present when many of them were made, he did not verify them at the times they were made, and he did not know whether or not they were correct. The time books were nothing but written hearsay, and written hearsay is not more competent than oral hearsay.
The plaintiff below covenanted in the contract to unload from the cars in East St. Louis'and to cart to the building in St. Louis all the cut granite required for the structure, and the granite company agreed to furnish him-with 'all the shipping receipts and schedules of stone shipped in advance of its arrival in East St. Louis. The granite company pleaded as a counterclaim that it was compelled to pay and did pay $211 demurrage to the railroad company because the plaintiff did not unload several of the cars within 48 hours of their arrival. The plaintiff admitted that he undertook to unload the cars, but in his answer denied all the other averments of the defendant relative to this counterclaim, and alleged that if there was. any delay beyond the 48 hours it was caused by the defendant. At the trial the fact was admitted that the defendant paid the railway company in accordance with one of the
The judgment below must, therefore, be reversed, and the case must be remanded to the court below, with directions to grant a new trial.
And it is so ordered:
Case-law data current through December 31, 2025. Source: CourtListener bulk data.