Union Pac. R. v. Mitchell-Crittenden Tie Co.
Opinion of the Court
This .is an action .by the Tie Company to recover of the Railroad Company the unpaid balance of the value of 378,392 cross-ties which the plaintiff had sold and delivered to the defendant. At the trial the parties stipulated that the price and value of these ties was $95,606.26, that 90 per cent, of this amount had been paid, and that the remaining $9,560.62 had been retained by
“In caso default is made by the party of the first part in delivery of the full quantity of cross-ties herein contracted for at the time specified, the 10 per cent, of contract price retained shall he applied by party of the second part in satisfaction of its liquidated damages.”
No evidence of the actual damages sustained by the Railroad Company on account of the failure to deliver the 21,608 Lies was introduced or offered, and the court instructed the jury to return a verdict for the plaintiff for the $9,560.62 and interest.
There was, therefore, no error in the court’s direction to the jury to return a verdict for the Tie Company, and the judgment in its favor is affirmed.
Reference
- Full Case Name
- UNION PAC. R. CO. v. MITCHELL-CRITTENDEN TIE CO.
- Cited By
- 3 cases
- Status
- Published
- Syllabus
- (Syllabus by the Court.) 1. Damages. (§, 79*) — Liquidated Damages — Construction of Contract. Where the amount of damages for the breach of a contract is uncertain and difficult of ascertainment, and an agreement is made which discloses the intention of the parties that a sum certain shall constitute the amount of the liquidated damages for the breach, the agreement, will be enforced. But where the contract fails to disclose such an intention, or leaves the intention of the parties in doubt, and the amount specified is unreasonable, the agreement will not be construed to be a contract for liquidated damages. [Ed. Note. — Eor other cases, see Damages, Dec. Dig. § 79.*] 2. Damages (§ 78*) — Liquidated Damages — Oonstbuction of Conteact— Eacts — Conclusion. Parties agreed that the vendor would sell and deliver to the vendee 400,000 cross-ties within an agreed time, that the vendee would pay during the succeeding month 90 per cent, of the value of the ties delivered each month, and that if the vendor failed to deliver the full quantity within the stipulated time the retained 10 per cent, of the contract price of those delivered should be applied in satisfaction of the liquidated damages of the vendee. The vendor delivered 378,392 ties, of the value of $95,606.26, but made default in the delivery of 21,608 ties. Held, the contract was not .that the retained 10 per cent, of the value of the ties delivered should constitute the amount of the liquidated damages of the vendee for the vendor’s failure to deliver all the tics within the time agreed, but the agreement was that this 10 per cent, should be retained to secure, and, as soon ,as these damages were liquidated, should be applied to pay, the vendee’s damages on account of the vendor’s failure to deliver all the ties. [Ed. Note. — Ear other cases, see Damages, Dec. Dig. § 78.*]