United States ex rel. Miller & Bentley Equipment Co. v. Kelley
United States ex rel. Miller & Bentley Equipment Co. v. Kelley
Opinion of the Court
Miller & Bentley (use plaintiff), as supplier of equipment to a subcontractor on a Government project in Alaska, has brought this action under the Miller Act, 40 U.S.C. §§ 270a, 270b, against the gen
The equipment involved was rented to the subcontractor by the use plaintiff, and the district court properly concluded that under such circumstances the notice period ordinarily runs from the time the equipment was last available for use on the project. United States ex rel. Carter-Schneider-Nelson, Inc. v. Campbell (9 Cir. 1961), 293 F.2d 816, cert. denied (1962) 368 U.S. 987, 82 S.Ct. 601, 7 L.Ed.2d 524.
The subcontract upon which the furnished equipment was used was terminated January 13, 1959. Use plaintiff was not notified of this fact. The. district court, however, found that as a reasonably prudent supplier it should have learned of it by February 15th. The use plaintiff gave its Miller Act notice to ap-pellees on April 28, 1959. The question here presented is as to the date from which the 90-day notice period starts to run. The district court held that it started to run January 13th, and that notice accordingly came too late. The use plaintiff contends it should not have started to run until February 15th, and that its notice accordingly was timely.
We agree with the district court. After the termination of the subcontract equipment supplied to the subcontractor was not available for use on the project.
The use plaintiff relies on United States for use of Westinghouse Electric Supply Co. v. Endebrock-White Company (4 Cir. 1960), 275 F.2d 57, for the proposition that proof of actual use on the project is not necessary if the materials were furnished for such use and if the supplier, in good faith, reasonably believed that such use was intended by the subcontractor to whom the materials were supplied.
Accepting, arguendo, that application of this rule to the facts of this case would have justified the recovery of rental beyond January 13th, if any recovery at all were permitted, we do not see how it can serve to extend the notice period.
It is clear that an important purpose of the 90-day notice provision is to protect the general contractor and his surety, and to encourage and reassure the general contractor in the prompt payment of the subcontractor after 90 days have elapsed. As this court pointed out in Bowden v. United States for use of Malloy (9 Cir. 1956), 239 F.2d 572, 577-578, cert. denied (1957) 353 U.S. 957, 77 S.Ct. 864, 1 L.Ed.2d 909:
“It cannot be doubted that one purpose of Congress in enacting the Miller Act was the protection of laborers and ma-terialmen. But it is clear, too, we think, from the mechanics provided in the Act for its operation and the accomplishment of its purpose, that it was the intent of Congress to fix a time limit after which the prime contractor could make payment to the subcontractor with certainty that he would not thereafter be faced by claims of those who had supplied labor and materials to the subcontractor.”2
Here the district court took notice of the general proposition that the
Under such circumstances to hold timely the notice filed after that 90-day period would be to disregard unjustifiably the statutory purpose of protecting the general contractor.
Judgment affirmed.
. 40 U.S.C. § 270b(a) provides in part
“[A]ny person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made * *
. See also Noland Co. v. Allied Contractors, Inc. (4 Cir. 1959), 273 F.2d 917, 921; McWaters & Bartlett v. United States for use of Wilson (10 Cir. 1959), 272 F.2d 291, 295; United States for use of McGregor Architectural Iron Co. v. Merritt-Chapman & Scott Corp. (M.D. Pa. 1960), 185 F.Supp. 381, 383.
. See also Noland Co. v. Allied Contractors, Inc., supra. It lias been recognized, however, that this desirability of liberal construction cannot justify ignoring the plainly expressed statutory prerequisites — including the notice of claim requirement — to a valid claim against the general contractor. Bowden v. United States for use of Malloy, supra; United States for use of J. A. Edwards & Co. v. Peter Reiss Construction Co. (E.D.N.Y. 1959) 174 F.Supp. 264, 266, aff’d (2 Cir. 1959) 273 F.2d 880, 78 A.L.R.2d 409, cert. denied (1960) 362 U.S. 951, 80 S.Ct. 864, 4 L.Ed.2d 869; cf. Clifford F. MacEvoy Co. v. United States for use of Calvin Tomkins Co. (1944) 322 U.S. 102, 107, 64 S.Ct. 890, 88 L.Ed. 1163.