Defendant-appellee Bissett has moved to dismiss this appeal from a preliminary injunction as moot. The motion is DENIED.
Second, JDA seeks to enforce a provision of the non-competition agreement that extends its term for any period of time in which Bissett is found to be in violation of the covenant not to compete. The validity of that term is in dispute between the parties, and the dispute has not been addressed by the district court. On this record, we cannot say that Bissett has established that a case or controversy no longer exists over the preliminary injunction.
MOTION TO DISMISS FOR MOOTNESS DENIED.