Public Power Council v. U.S. Department of Energy
Public Power Council v. U.S. Department of Energy
Opinion of the Court
MEMORANDUM
This litigation arises from the Bonneville Power. Administration’s (“BPA’s”) treatment of refunds owed to one class of customers following our opinions in Portland General Electric Co. v. BPA (PGE), 501 F.3d 1009 (9th Cir. 2007), and Golden Northwest Aluminum, Inc. v. BPA (Golden Northwest), 501 F.3d 1037 (9th Cir. 2007). Following those decisions, BPA issued the Record of Decision (“ROD”) in its WP-07 Supplemental Wholesale Power Rate Case (‘WP-07S ROD”), in which it addressed our opinions and determined the amounts it would pay in refunds, known in BPA documents as the “Look-back Amounts.”
The petitioners in this case filed a petition for review in this court challenging various aspects of the WP-07S ROD. After filing the petition for review, all of the petitioning parties except one, the Western Public Alliance Group (‘WPAG”), entered into a settlement with BPA known as the REP-12 Settlement Agreement. After evaluating the settlement, the BPA Administrator issued a new ROD, known as the REP-12 ROD,
WPAG makes several arguments supporting its assertion that its challenge to the WP-07S ROD’S treatment of the Look-back Amounts survives the issuance of the REP-12 ROD. Each of these arguments is unavailing.
WPAG argues that the REP-12 Settlement Agreement itself anticipated that we could rule on the WP-07S ROD’s treatment of the Lookback Amounts regardless of BPA’s later adoption of the settlement’s terms in the REP-12 ROD. While the Settlement Agreement acknowledges that litigation could affect BPA’s ability to abide by the settlement’s terms, the agreement was drafted prior to BPA’s adoption of the REP-12 ROD, a time during which this litigation was - pending. Further, the REP-12 ROD several times stated BPA’s intent to replace the WP-07S ROD Lookback Amounts remedy, demonstrating that BPA did not intend the terms of the WP-07S ROD to remain relevant to claims related to the Lookback Amounts after the REP-12 ROD was approved. See REP-12 ROD at 30-31, 293, 320-27, 344-49, 365-72.
WPAG further argues that it seeks damages for past wrongs rather than prospective relief, in an attempt to distinguish case law providing that permanent policy changes moot outstanding challenges to
Even if the REP-12 ROD replaced the WP-07S ROD, WPAG argues, its terms cannot be applied to moot WPAG’s claims because (1) BPA unlawfully applied to nonsettling parties terms in the REP-12 Settlement Agreement and (2) a partial settlement cannot moot claims by nonset-tling parties. It is true, as WPAG notes, that the challenged aspect of the WP-07S ROD (failure to include certain payments to PacifiCorp and Puget Sound Energy in the Lookback Amount refunds) is also a feature of the REP-12 ROD, although the overall treatment of the refunds is not precisely the same.- See REP-12 ROD at 253. But, as we recognized in APAC, BPA had the legal authority to establish the remedy ordered by this court in PGE and Golden Northwest for all of its customers so long as that remedy did not exceed its statutory authority. See 733 F.3d at 967-68. BPA exercised this authority not by entering into a partial settlement with some of its customers, but by adopting the terms of the settlement as the policy of the agency via an ROD. See REP-12 ROD at 292; see also Mobil Oil Corp. v. Fed. Power Comm’n, 417 U.S. 283, 297, 312-14, 94 S.Ct. 2328, 41 L.Ed.2d 72 (1974) (upholding Federal Power Commission rates based on a private settlement because the adopted rates complied with the agency’s statutory obligations and were supported by the record). As BPA explained in the REP-12 ROD, “[n]on-signers are bound [by the settlement] only in the sense that they will pay in rates the REP benefits provided under the Settlement, but only after BPA has independently found that the Settlement satisfies the requirements and protections set forth in the Northwest Power Act.” REP-12 ROD at 348.
We conclude that the REP-12 ROD withdrew and replaced the WP-07S ROD as to the remedy owed by BPA under our decisions in PGE and Golden Northwest. WPAG did not challenge the REP-12
DISMISSED as moot.
This disposition is not appropriate for publication and is not precedent except as provided by 9 th Cir. R. 36-3.
. We grant the moving parties’ motion to take judicial notice of the REP-12 ROD. See Transmission Agency of N. Cal. v. Sierra Pac. Power Co., 295 F.3d 918, 924 n. 3 (9th Cir. 2002). The ROD is available at https://www.bpa.gov/ Finance/ResidentialExchangeProgram/ Documents/REP-12-A-02.pdf.