Albaugh v. Litho-Marble Decorating Co.
Albaugh v. Litho-Marble Decorating Co.
Opinion of the Court
delivered the opinion of the Court:
1. In this court a motion was made to dismiss the appeal of Mrs. Harriet S. Blaine and two other defendants who had been proceeded against by process of publication, on the ground that, inasmuch as no appearance had been entered for them, they had no right of appeal, their remedy being, as it was claimed, by a petition for a rehearing in the court below under the provisions of the Act of Maryland of 1773, Ch. 7, Sec. 4. This motion was postponed to the hearing on the merits, and now comes up for determination. We think that the act of Maryland, to which reference is made, is not at all applicable to this case, and that the motion is not well founded. But it is sufficient for us here to say, that the complainant company by its own appeal, which in terms is an appeal from the whole decree, has brought the whole case and all the parties into this court; and it would gain nothing by the allowance of its motion, even if it were otherwise well founded. The motion therefore must be denied.
2. Proceeding to a consideration of the case on its merits^
It is very clear to us that the decree, as against Mrs. Harriet S. Blaine, is erroneous in every aspect of it, and that as to her -the bill of complaint should have been dismissed. If there is any liability in the premises, it is only that of Albaugh and Painter in respect of the leasehold interest which they hold.
3. Whether the complainant’s lien takes precedence of the deed of trust executed in January of 1896, to the defendants, Johns and Porter, to secure the defendant, Euterpe Kinsbury, is a question that admits of grave doubt. The complainant company in October and November of 1895 claimed to have finished its work in the previous September as well as it could have been done under the circumstances. Albaugh and Painter appeared to the world to be in full possession in and after that month of September; and so far as this record shows, there were no workmen there thereafter before the execution of this trust, and there was reason for those dealing with the owners to assume that the work had been finished; and it is not shown that the trustees or beneficiary in the deed of trust had any knowledge of the supplemental contract of December 11, 1895, between the company and Albaugh and Painter. It may, therefore, be questioned whether the trustees and beneficiary in the deed of trust were not justified in dealing with the property, so far as the complainant company is concerned, on the assumption that it had been settled with, the three months allowed by the mechanics’ lien law for the filing of notice
4. The main, and we may say, the substantial controversy in this case is between the complainant company, on the one side, and the defendants, Albaugh and Painter, on the other; and upon the issues between these parties we find ourselves constrained to come to a somewhat different conclusion from that reached by the learned justice who heard the cause in the court below.
The claim of the complainant is for $1,561.50; the decree allows $1,311.50. The difference is the result of a deduction of $250 based exclusively on the testimony of one of the witnesses for the complainant, who testified that in November, 1895, he had inspected the work for the company, that it was not then in first class condition, and that it would require about $250 to put it in first class condition. But all this was before the execution of the supplemental contract of December, 1895; and as, under that supplenaental contract, there was work by the company in the summer of 1896 to complete the work in accordance with the requirements of the original contract, and as it is claimed by the company that the work was then corhpleted, it is not apparent how an arbitrary sum of $250, applicable enough perhaps in the previous condition of the work, can be held to be equally applicable in the subsequent stage. If, after the work of the company’s employees in the summer of 1896, there was still deficiency either in the quantity or quality, the record is wholly without proof of the amount of it, or of the sum of money that would be necessary to supply the deficiency. It appears to us, therefore, that the deduction of the sum of $250 from the complainant’s demand is unwarranted. The proper deduction, if any, to be made may be more, or it may be less. What we hold is,
In the complainant’s claim of $1,561.50 there is included a charge of $406.50 for extra work, the remainder of the claim being for the work under the original contract. This charge of $406.50, being the aggregate amount of three several items, was included in the bill presented by the complainant to the architect on October 16,1895, and which was certified by the latter as correct, with the exception of one of three items, $36, which was disapproved and erased. Unless there is testimony to overcome this ruling of the architect, and we find no such testimony in the record, the claim for extra work must be reduced from $406.50 to $368.50. This extra work is referred to in the supplemental contract of December 11, 1895; and it is there stated that “the quantity of this work is still in dispute, and the ascertainment of exact quantities of such extra work is reserved for consideration between the parties at the time of final adjustment when contract work is entirely completed.” It does not appear what effort, or whether any effort, was made to ascertain this quantity; and, in view of the provisions of the supplemental contract, there should. have been some testimony on this point.
But these are minor details; the main controversy remains to be adjusted. Did the complainant company perform its work under the contract in accordance with the requirements of the contract ? If it did not, whose was the fault for the failure ? And if the work -was not performed in accordance with the requirements of the contract, what was the amount of the deficiency, and what is the proper amount to be deducted from the contract price on account of' such deficiency ? Unfortunately the testimony does not afford to us the means of answering these questions satisfactorily to ourselves. The testimony is mainly confined to
It would seem that on December 11,1895, the complainant
The testimony, we think, is wholly insufficient on which to base a decree. It is very evident to us that the complainant company is entitled to a recovery to some extent; but the amount of that recovery we are unable to determine; and greatly as we regret to subject the parties to further expense and delay in the matter, we are compelled to make such disposition of the case as will enable the court to come to a satisfactory determination of that amount. This may • be had either by reference of the cause to the auditor of the court, with authority to take further testimony, if need be; or by submission of the question to a jury by the formulation of issues under the "direction of the court, or by the institution of an independent suit.
It is our conclusion that the decree appealed from should be reversed, with costs to be equally apportioned between the complainant company, on the one part, and the defendants, Aibaugh and Painter, on the other; and that the cause should be remanded to the Supreme Court of the District of
And it is so ordered.
Reference
- Full Case Name
- ALBAUGH v. LITHO-MARBLE DECORATING COMPANY LITHO-MARBLE DECORATING COMPANY v. ALBAUGH
- Status
- Published
- Syllabus
- Appellate Practice ; Equity Pleading and Practice ; Answer as Evidence ; Principal and Agent ; Lease ; Mechanics’ Liens; Notice; Priorities. 1. Where the complainant and defendants all appeal from a decree in an equity suit, and the appeal by the complainant is from the whole decree and brings the whole case and all the parties to this court, a motion by the complainant to dismiss the appeal of certain defendants upon the ground that they have no right' of appeal, inasmuch as they had been proceeded against by publication in the court below and no appearance had been there entered for them, will be overruled. 2. An allegation in a bill in equity that two of the defendants acted as agents for a third defendant, when positively denied by the former in their answers and unsupported by any testimony whatever, must be regarded as conclusively disproved by the answers, although a decree pro eonfesso has been taken against the alleged principal upon her failure to answer. 3. A covenant in a lease for the erection by the lessee of a building on the leased premises, to become the property of the lessor at the end of the term, without charge to the lessor, her heirs or assigns, does not create the relation of principal and agent between the lessor and lessee, so as to bind the lessor and her property for the contracts of the lessee made in the performance of the covenant, and under such circumstances a bill in equity to enforce a mechanic’s lien against the leased property • for work and labor done for the lessee in the erection of the building is maintainable only against the leasehold interest. 4. Quaere, whether the lien of a contractor furnishing labor and material for a building will take precedence of a deed of trust executed more than three months after the contractor claimed to have completed his work, during which time he had no men at work and there was reason for persons dealing with the owner to suppose the work had been finished, and where neither the trustees nor the beneficiary under the deed of trust had notice of a supplemental agreement between the owner and contractor, by the terms of which certain defects in the work were to be remedied and in accordance with which additional work was done several months after the date of the deed of trust. S. A decree in a suit to enforce a mechanic’s lien for work done and materials furnished, reversed, upon the ground that the testimony was insufficient upon which to base a decree, and the cause remanded with directions to refer the cause to the auditor for a finding of facts upon the testimony taken and such additional testimony as might be adduced before him, or to have issues formulated for the determination of the facts by a jury, or to permit the parties under the control and direction of the court, to institute a suit at law for the determination of such facts — in the discretion of the lower court.