Emack v. Campbell
Emack v. Campbell
Opinion of the Court
delivered the opinion of the Court :
1. With reference to the first question, the contention is that the notices of lien, although in the usual form heretofore generally followed in this District, do not conform to the requirements of the law.
The notices in the present case are all substantially in the same form. That of the complainants in the suit is in the following terms:
“Notice is hereby given that we intend to hold a mechanics’ lien upon Lots 37, 38, 39, 40 and 41, in Emack’s subdivision of lots in Square 516, situated in the city of Washington, in the District of Columbia, and the buildings thereon, for the sum of nine hundred and seventy tVo dollars ($970.25), with interest from-189 — , being amount due us for labor and material (lumber) furnished for the construction of said buildings under and by virtue of a contract with W. P. Kerby & Bro., the owner’s contractors.”
The others only differed from this in the matter of amount and the statement of the materials furnished or work done, as sand, bricks, and brick work. It is argued that these notices do not comply with the requirement of the law that the person giving such notice and claiming the lien shall “specifically set forth the amount claimed” (Rev. Stat. for D. C., Sec. 693, Act of July 2, 1884, 23 Stat. 64, Sec. 2); and that due compliance with the law demands the incorporation of an itemized account in the notice.
We can not accede to this view. The verbal criticism by which the term “specifically,” as used in the Act of Congress, is sought to be interpreted as the equivalent of the expression “in detail,” does not seem to us to be sound, or to be in conformity either with the letter or with the spirit of the law. The act undoubtedly requires explicitness and certainty; it requires that the owner of the property, for the purpose of protecting himself in his further dealings with his contractor, should have full and accurate notice of the' claims of those
We think that the notices of lien given in the present instance were sufficient in law.
2. In the second place, it is contended that three of the four parties here claiming liens are not entitled to relief in the present suit, because they have taken no affirmative action, by way of cross-bill, petition, bill, or otherwise, to ask for relief. ' The complainants in the original bill of complaint, of course, are not included in this objection, which is aimed only at the lien claimants who were made defendants' to that bill.
One of these lien claimants, James T. Summers, who had filed his notice of lien in due form, such as we have just held to be sufficient, and who was subsequently made a party to the bill as defendant, caused his appearance to be entered to the bill, but never answered or took any other action whatever in the case. His claim, however, was fully admitted by the appellant, Marion Emack, in her answer to the bill, although she denied the sufficiency of his notice of lien on the ground which has already been disposed of, and denied also his right to relief in this suit on the ground, now under consideration, of the absence of affirmative action
The other two of these three lien claimants, Henry W. Eno and the Capitol Hill Brick Company, filed their answer’s to the bill of complaint, and in those answers stated their claims as fully as though they filed original bills, or cross-bills, or petitions in this suit.
It is true, as a general rule, that a defendant in equity can not have affirmative relief, unless he makes himself a complainant, either by petition or by cross-bill, or by transfer in some way from the position of a defendant to that of a complainant, and asks for affirmative relief. But this rule is subject to well-known exceptions; and principal among those exceptions'is the case where a fund or property is in the control of the court to be administered by the court and distributed among those entitled to it in accordance with their respective interests, as those interests appear in the suit. In creditor’s suits, for example, when the estate of a deceased person is to be administered in equity, it is not necessary for persons who appear before the auditor of the court upon general notice to come in and prove their claims, to file any bill, cross-bill, petition, or pleading of any kind to entitle them to become parties to the suit, and to have thereafter all the rights of parties, although it is always proper in such cases to file a petition, or something in the nature, of a petition. So, likewise, in a suit for the foreclosure of a mortgage, if there are subsequent mortgagees who are made parties to the bill of complaint as defendants, it is not necessary, and it is not usual, that they should take affirmative action in order to entitle themselves to a participation in the proceeds of sale of the property, and numerous other illustrations might be cited. It has never been the practice in this District, or elsewhere so far as we are advised, for persons holding or claiming mechanics’ liens, who have
3. Objection is made to the claim of the Capitol Hill Brick Company on the ground, as alleged, that its notice of lien was not filed in time.
The facts in regard to this point, as disclosed by the record before us, are these: The houses, with reference to which .the controversy arose, were finished, according to the allegation of the bill of complaint, “on or about the first day of July, A. D.,1893. Both in the answer of the brick company and in that of Mrs. Emack, this allegation was admitted to be true. The notice of lien was not filed until October 6, 1893, more than three months after the first day of July, notwithstanding that the law requires that the notice should be filed within three months after the completion of the building in order to make the lien effective. But it will be noticed that neither the bill of complaint nor the answers determine with precision the date of such completion; they simply aver that it was about the 1st of July, A. D. 1893; and the precise time is thereby left to be more accurately ascertained by the testimony of witnesses. Such testimony is not wanting in the case; and it is the testimony of Charles G. Emack, the husband of the principal defendant, Mrs. Marion Emack, and who was likewise her agent in the whole transaction. In his deposition, to be found in the record, he says that the work on the houses was completed “probably some time about the middle of July.” Even this
4. Among the assignments of error is one to the effect that the decree appealed from is in substance a personal decree against the appellant, Mrs. Marion Emack, and that in such case no personal decree is authorized by law. But as the appellees have conceded upon the argument that no personal decree against Mrs. Emack was intended or could be rendered validly in the cause, this assignment of error is abandoned.
5. A question is made, which affects the accounting in the case, whether a provision in the contract between Mrs. Emack and the builders, Kerby & Brother, was for a penalty or for liquidated damages. The provision is in these words: “Should the contractors fail to finish the work at or before the time agreed upon (February 1, 1893), they shall pay to or allow the proprietor, by way of liquidated damages, the sum of five dollars per diem for each and every day thereafter the said works remain incomplete.” The work remained incomplete, according to the testimony of Charles G. Emack, which seems to be accepted by all parties as correct, for about five and one-half months — that is, until about the middle of July, 1893; but Mrs. Emack has fixed upon a lesser period of one hundred and fifty days as the time for which she is entitled to the stipulated allowance; which for that time, and at the rate specified, amounts to $750. This sum she claims that she is entitled to deduct from the contract price payable by her for the buildings.
But with reference to this amount her husband and agent, Charles G. Emack, in his deposition already mentioned, testified as follows:
“There was a compromise of these penalties or forfeitures, whichever you call.them, later on. It was agreed between*194 Messrs. Munroe and Campbell (who, as already stated, undertook as the sureties of Kerby & Brother to complete the contract made by these latter with Mrs. Emack.) and ir^self that we would divide the amount of the forfeitures, which was $750; that I would relinquish my claim to half of it and let (that) half of it go back into the fund.”
We must presume that this “compromise” was made for a proper consideration; and that therefore the allowance claimed by the appellant for delay in the completion of the work, the amount of which is not specifically stated in her answer, is to be reduced from $750 to $375.
The court below, in its preliminary decree, mentioned the sum of $750 as the amount claimed in this regard, and disallowed it, and made no allowance whatever for damages for the delay of the contractors. The claim, of course, was not, and could not properly have been, taken into consideration, in the accounting before the auditor, in view of this preliminary ruling by the court.
In this action of the court we think there was error. The appellant should have been allowed to deduct from the money payable by her the sum of $375, the amount ultimately agreed upon as the proper compensation to her for the delay of the contractors.
It is said that courts of equity will not enforce forfeitures, and that here was a forfeiture, although it is called by the name of “liquidated damages.” The books are full of discussions on the difference between penalties and liquidated damages in contracts providing for compensation to parties injured by default or failure of antagonistic parties to perform their agreements; and it must be said that the courts have frequently been astute in restricting by construction the scope of such provisions beyond the meaning and purpose of the parties in interest. The general rule on the subject, as administered by the courts of equity, is well stated in the American and English Encyclopsedia of Law, Title, “Liquidated Damages,” where the author of the article says:
*195 “ It may be stated- as a rule of general application that a stipulation for the payment of a specified sum upon the nonperformance of the contract in which it is contained, is to be treated as a penalty rather than as liquidated damages, if the intention of the parties as to its effect appears at all doubtful, or is of equivocal interpretation. It is also customary to consider such a stipulation as a penalty, in the absence of clear and convincing proof of a contrary intention by the parties at the time of the execution of the contract, where the covenant is certain and the damages for a breach thereof easily ascertainable, especially if the amount named is greatly out of proportion to the actual damage.”
But the limitations of the rule, if we admit such to be the rule, are plain and palpable in the statement of the rule itself. If the parties have distinctly and by express terms contracted for stipulated damages, and not for a penalty; if the intention is not at all doubtful or the language used equivocal; if the damages for a breach of the contract are not easily ascertainable; if the damages specified as liquidated damages are in themselves not unreasonable, it is not apparent why we should not take the contract of parties to be what they themselves have stated it to be. It is perfectly competent in law for parties to stipulate for liquidated damages in the place of penalties, to compensate for the violation of the covenants contained in such contracts; and if they have done so in clear and unmistakable terms, at least the burden of proof should be upon him who alleges the contrary, and courts should not lightly distort the, contract from that which it says to that which it might be thought they should have said.
What Sir George Jessel, Master of the Rolls, in the case of Wallis v. Smith, Law Rep. 21, Chancery Division, 243, 266, said upon the question is very appropriate here. He said: “I have always thought, and still think, that it is of the utmost importance as regards contracts between adults — persons not under disability, and at arm’s length — that the
See, also, Bagley v. Peddie, 16 N. Y. 469; Mason v. Callender, 2 Minn. 302; Gotheal v. Talmage, 9 N. Y. 551; Chase v. Allen, 13 Gray, 42; Hall v. Crowley, 87 Mass. 304; Folsom v. McDonough, 60 Mass. 208; Warrell v. McClanaghan, 5 Strobhart (S. Car.), 115.
The case of Folsom v. McDonough, 60 Mass. 208, just cited, was very like the present case. In it there was a provision in a building contract that the contractor should pay to the owner of the property a certain specified sum,for each day for which the work should remain unfinished after the time limited in the contract for its completion. And of the same character also was the case of Warrell v. McClanaghan, 5 Strobhart, 115, excepting that the sum to be paid was for each month instead of each day. So, also, was the case of Hall v. Crowley, 87 Mass. 304, where it was said by the court:
“The sum named is for doing one certain and specific job of work within a prescribed time, and not for an omission to comply with divers separate and independent stipulations of different degrees of importance, the failure to perform each of which would occasion very different and unequal amounts of damage to the defendant. Nor is it to be overlooked that the loss or injury which would accrue to the owner by the non-completion of the houses seasonably, According to the terms of the contract, would be difficult to prove and still more difficult to estimate in money. All these circumstances indicate very clearly that the intent of, the parties was to insert in their agreement a fixed measure of damages, and not to name a sum as a penalty merely.”
Both upon reason and upon authority we think that,
Again, to the proposition that courts of equity will not enforce forfeitures, even if the provision in the present case should be regarded as a penalty, and not as liquidated damages, it may well be objected here that the appellant has not called upon the court to enforce anything, and that she is simply desirous not to be disturbed in the enjoyment of that which she has. She holds the money in her own hands wherewith to compensate herself for the-default of the contractors; she has the legal right to hold it, and the legal right to pay herself therewith; and a court of equity is not authorized by any principle of equity or by any rule of law to reach into her purse and to compel her to forego this legal right, merely because it might not itself enforce the right, if called on by her as a complainant so to do. We have so held in the recent case of Anderson v. Reid, ante, p.
But whether the provision in question is for a penalty or for liquidated damages, the appellant is entitled in any event to compensation for the damage sustained by her through the failure of the contractors to perform their contract within the specified time. She was allowed no compensation whatever in the decrees of the court below, and no opportunity to prove the damage. In this we think thatt under any aspect of the case, there was plain error. We think that the appellant should have been allowed to deduct from the money in her hands the sum of $375, as liquidated damages.
6. The remaining assignments of error have reference to the mode of the statement of the account by the auditor of the court.
Remaining in the hands of the appellant there is a balance of the amount stipulated to be paid for the construction of the houses in controversy, amounting, according to the auditor’s statement, to $1,775.52. This should be diminished by the sum of $375, tobe allowed to the appellant for her liquidated damages before mentioned, and also by the amount of the costs of this appeal, not yet taxed, and which are to be allowed to her out of the fund in her hands. The outstanding liens or claims chargeable against this fund, according to the auditor’s report and at the time of that report, including both principal and interest, amounted to the aggregate sum of $3,217.76. Included in this aggregate sum were certain claims paid or satisfied by the appellant, and stated by the auditor to amount to $762.15. There were seven of these claims; five the appellant had paid in full; two she had settled for fifty cents on the dollar. The face amount of these last two was $386; she settled them for $193. As the aggregate amouut of the claims was in excess of the fund from which they were to be paid, it was
It ought not to be difficult for the parties to agree between themselves as to how the account should now stand. But if they can not agree thereon, it will be proper to refer the cause again to the auditor, with directions to state the account upon the basis in this opinion indicated.
It follows from what we have said that the decree of the Supreme Court of the District of Columbia rendered in this cause must be reversed, with costs, which are to be reimbursed
And it is so ordered.
Reference
- Full Case Name
- EMACK v. CAMPBELL
- Status
- Published
- Syllabus
- Mechanics’ Liens; Notice oe Lien; Equity Practice; Building Contracts; Liquidated Damages; Accounting. 1. Under the Mechanics’Lien Law of this District requiring that notices of lien shall “specifically set forth the amount claimed,” it is necessary only to set forth precisely the amount claimed, and not the items that go to make up that amount. 2. It is not necessary for persons claiming mechanics’ liens, who have been made parties defendant to a suit brought by other claimants of similar liens to enforce them, to file cross-bills or to take other affirmative action in order to participate in the fund to be realized by the suit. 3. A notice of lien filed October 6, 1893, under the Mechanics’ Lien Law of this District, requiring the notice to be filed within three months after the completion of the building, is sufficient where the testimony is that the work on the houses was completed “probably sometime about the middle of July,” 1893, although the bill of complaint alleges, and the lienor, who was made a defendant to the bill, and the owner, in their answers admit that the houses were completed “on or about the first day of July, 1893.” 4. Where a building contract provides that the contractors shall pay to the owner, by way of liquidated damages, a certain sum for every day the buildings shall remain incomplete after the day fixed for their completion, the provision will be enforced, in the absence of anything to show that it is unreasonable, harsh or oppressive, or that the amount stipulated is greatly in excess of a fair rental value of the premises upon the completion of the houses. 5. When the aggregate o.f claims for which mechanics’ liens are filed exceeds the balance in the owner’s hands, such balance should be distributed pro rata; and for claims which have already ■been paid or satisfied by the owner out of such balance, she. should, on an accounting, be given credit according to the pro rata share to which such claimants would have been entitled.