District of Columbia v. Harlan & Hollingsworth Co.
District of Columbia v. Harlan & Hollingsworth Co.
Opinion of the Court
delivered the opinion of the Court:
Counsel for plaintiff contends that the contract provides for the imposition of a penalty, and not liquidated damages, and therefore the District of Columbia was only entitled to deduct from the contract price the amount of damages actually sustained in consequence of plaintiff’s delay in delivering the boat. In England, before the passage of the statute of forfeitures and penalties (8 & 9 Wm. III.), in actions at law on a contract, where the performance of the conditions was secured by a penalty, the recovery was for the full amount of the penalty. Courts of equity, however, could relieve against fraud or mistake. The effect of this statute was to furnish the same relief in a court of law as could be obtained in a court of equity. In Sun Printing & Pub. Asso. v. Moore, 183 U. S.
There is nothing to prevent the parties from stipulating in advance that a certain sum shall be the damages which one shall forfeit to the other for failure to perform the conditions of a valid contract. Especially is this true where the damages
Whether the sum agreed to be paid as damages for the failure to perform the conditions of a contract shall be treated as liquidated damages or as a penalty is to be drawn from the subject-matter of the agreement, the meaning and intent of
It is contended by counsel for plaintiff that the defendant, by the receipt of the engineer of the fire department of June 5th, and the order of the commissioners of July 3d, waived all right to retain liquidated damages. The receipt given by the engineer of the fire department upon the arrival of the boat in Washington cannot be construed into either a release
The order of the commissioners of July 3d, however, presents a more difficult question. Usually the acceptance of work contracted for by one of the parties relieves the other party of liability for delay in the performance of his part of the contract, but such acceptance must be uziconditional, and with full knowledge, on the part of the accepting party, of any default on the part of the other party. Here the acceptance was upon
Reversed.
Reference
- Full Case Name
- DISTRICT OF COLUMBIA v. HARLAN & HOLLINGSWORTH COMPANY
- Cited By
- 6 cases
- Status
- Published
- Syllabus
- Contracts; Damages; Penalties; Release; Acceptance; Municipal Corporations. 1. Parties to a contract may validly stipulate that a certain sum shall be-the damages which one shall forfeit to the other for failure to perform the conditions of the contract, — especially where the damages sustainable may be uncertain in amount, and not easily ascertainable. 2. When an amount agreed upon in a contract as liquidated damages is out of all proportion to any actual damages that could possibly accrue, courts of equity may grant relief; but a court of law has no right to construe a contract contrary to the expressed intention of the parties, in order to make for them a better or more equitable contract. 3. • Whether a sum agreed upon to be paid as damages for the failure to perform the conditions of a contract should be treated as liquidated damages or as a penalty is to be drawn from the subject-matter of the-agreement, the meaning and intent of the parties as expressed in the contract, and the terms used to express that intent; and in determining that intent courts will not be bound by the exact language of the contract. The contract may use the terms “forfeit” and “penalty,” and yet be construed to call for liquidated damages; and, likewise, the words “liquidated damages” used in a contract may be held to mean a penalty. 4. In order to determine whether the amount stipulated in a contract to be forfeited for nonperformance should be construed as a penalty or liquidated damages, an examination should be made of the whole contract, the sum stipulated, the ease or difficulty of measuring the pecuniary loss that would be sustained by the breach, the subject-matter of the contract, and the proportion that the amount stipulated bears to the entire consideration. 5. Where a contract between a ship-building company and a municipality for the construction of a fire boat provides that the company shall forfeit to the municipality $25 for each working day it shall be in default, “which sum of $25 per day is hereby agreed upon as fixed and liquidated damages” that the municipality “will suffer by reason of such default, and not by way of penalty,” the municipality is entitled to deduct from the balance due upon the contract price for the boat, $25 for every day the company is in default in delivering the boat, irrespective of the actual damages sustained, — especially where the company does not claim that the amount named as liquidated damages is out of proportion to the amount of the contract price, and no fraud or mistake or other facts are alleged calling for a reformation of the contract. 6. A receipt given by the ehief engineer of the fire department of the District for a fire boat constructed for the District will not operate as a release of the builder of the boat from the obligations of its contract with the District for the construction of the boat, or as an acceptance of the boat by the District, in the absence of anything to show that the chief engineer was authorized to accept the boat for the District, or that his action was subsequently ratified by the municipal authorities,' — especially where the subsequent action of both parties to the contract negatives the idea that the receipt was intended to so operate. 7. A municipal order accepting a fire boat constructed for the municipality, upon the express condition that the builder will “complete the work on the pumps and appurtenant machinery and substitute the required monitor nozzles, so as to meet fully the requirements of the specifications,” does not relieve the builder of liability under the contract for the building of the boat, for delay in completing the boat according to contract, where it appears that, before and after such conditional acceptance, efforts were made by the builder, with the assistance of the municipal agents, to put the machinery in proper order, and that that ■was not finally accomplished until nearly four months after the order was made.