Simmons v. Jaselli
Simmons v. Jaselli
Opinion of the Court
delivered the opinion of the Court:
“The written contract for the work in question in this cause is dated July 30, 1909, and provides that the work should be begun at once and completed within thirty (30) working days, and further that if the work should not be completed within that time, the contractors should forfeit to the owner the sum of tollm peí toy ic® fetoa toy imlwtong Smtoys, ttot the work should remain unfinished. The jury are therefore instructed that if they shall find from the evidence that the work was not completed on or before September 3, 1909, they should allow to the defendant from the contract price, $10 per day for each day, Sundays included, after September 3d, that the work remained unfinished.”
It is contended by the appellee that the language of the contract, providing for a forfeiture upon failure to complete the contract within the time fixed, cannot be regarded as an agreement
It is not necessary to decide this question. The only plea of defendant was nonassumpsit. While a wide range of defense is permissible under the general plea, apparently including payment, release, etc., it has never been extended to matters of set-off. The claim that defendant is entitled to liquidated damages under a provision of the contract stipulating therefor in case of delay, is an independent matter of defense recoverable by way of set-off, and, to be entertained, must have been pleaded. Code, sec. 1563; Langston v. Maitland, 11 Grill & J. 286-297; 1 Poe, PI. & Pr. sec. 609. There was no error in refusing the instruction.
The court in the general charge told the jury that if the work had been done, as agreed on, properly, the plaintiff would be entitled to recover the amount found to be unpaid. If the work was defectively done, plaintiff could recover only what it was worth, and that if he had been paid all that it was fairly worth, the verdict should be for the defendant. This, we think, gave defendant all that he had a right to ask.
Finding no reversible error in the proceedings, the judgment will be affirmed, with costs. Affirmed.
Reference
- Full Case Name
- SIMMONS v. JASELLI
- Status
- Published
- Syllabus
- Contracts; Evidence; Parties; Partnership; Pleading; Appeal and Error. 1. In an action on a written contract by E. 2. In an action on a contract to furnish labor and materials, in' which the issues were as to whether the plaintiff had partners who should have been joined as plaintiffs, and as to the amount and character of the work done and materials furnished under the contract, it was held, on a review of the evidence, that the trial court did not err in refusing to direct a verdict for the defendant. 3. In an action on a written contract for labor and materials furnished, where the trial court refused a special instruction asked by the defendant, to the effect that if, at the time of the doing of the work, the plaintiff had a partner who was interested in the work and entitled to share in the proceeds thereof, he could not recover, but in the charge to the jury defined partnership, and told the jury that if there was a partnership between the plaintiff and his alleged partners, and the contract w’as with the partnership, the plaintiff was not entitled to recover because of the nonjoinder of such parties,— it was held that any error in the refusal of the special instruction was cured by the charge. 4. Where a written contract, not under seal, for labor and materials furnished, was made with the plaintiff alone, and all of the communications concerning the work by the defendant were with the plaintiff and all payments under the contract made to him, he is entitled to sue in his own name, even though he agreed to share with others the profits arising from the contract. 5. In an action of assumpsit on a written contract, evidence by the defendant that, under a provision of the contract stipulating therefor, he is entitled to liquidated damages for delay in performing the contract, is inadmissible under a plea of the general issue; such a claim must be specially pleaded by way of set-off. 6. Where a contract to furnish work and materials on a building provided that the contract price should be paid when the work was completed to the satisfaction of the owner, and then specified how the work should be done and as to the kind of materials to be furnished, it is not error, in an action on the contract for the balance of the contract price, for the trial court to refuse an instruction asked by the defendant, to the effect that, while the agreement would not permit an arbitrary or unreasonable rejection of the work if done in • substantial compliance with the contract in a first-class manner, yet if the evidence showed that the work was not a first-class job, so that the defendant had a right to be dissatisfied therewith, the plaintiff was not entitled to recover. In such a case, a charge by the court that if the work was done as agreed on properly, he is entitled to recover the amount unpaid, while if the work was done defectively, ho can recover only what it was worth, and that if he has been paid all that it was properly worth, the verdict should be for the defendant, gives the defendant all that he has a right to ask. 7. Where in an action to recover the balance of the purchase price specified in a contract for work and labor, the evidence was conflicting as to the character of the work done, and the jury returned a verdict for the plaintiff for the full balance of the contract price as claimed, it was held on an appeal by the defendant from a judgment on the verdict, that even if the court erred in charging the jury that the plaintiff might recover the fair value of the work done in the event it did not come up to the requirements of the contract, and was yet worth something in excess of the payments received — because there was no evidence justifying a recovery of the quantum meruit — such error, in view of the testimony, was not prejudicial to the defendant.