Simmons v. Jaselli

U.S. Court of Appeals for the D.C. Circuit
Simmons v. Jaselli, 38 App. D.C. 242 (D.C. Cir. 1912)
1912 U.S. App. LEXIS 2115

Simmons v. Jaselli

Opinion of the Court

Mr, Chief Justice Shepard

delivered the opinion of the Court:

1. The objection to the introduction in evidence of plaintiff’s copy of the contract is technical, and the court did not err in permitting both copies to go to the jury. The recitals in the body of the contracts show that they were made with E. Jaselli & Brothers, and both should formally [have] been signed by E. Jaselli & Brothers. Whether the contract was made with E. Jaselli & Brothers, and whether E. Jaselli alone was the party, or whether he had partners, were questions for the jury to determine.

2. There was sufficient evidence to go to the jury on the issues of contract, partnership, and to the amount and character of the work done under the contract, and there was no error in refusing to direct a verdict for the defendant.

3. The special instruction to the effect that if, at the time of doing the work, the plaintiff had a partner or partners who were interested in said work and entitled to share in the profits thereof, he could not recover in this action, was refused and error is assigned thereon. Passing by the question whether the instruction was strictly applicable to the question of the contract, any error in its refusal was cured by the general charge. In that, the- court stated the law defining partnership, and then told the jury that if there was a partnership between plaintiff and *249bis alleged partners, and the contract was with said partnership, the plaintiff was not entitled to a verdict, because of the nonjoinder of said parties.

4. The court went farther than stated above, and in conclusion told the jury that if there was a partnership in fact, and they should find that the contract was made with the plaintiff alone, or in his own name, then if the work had been done according to the contract, and properly done, they should find for the plaintiff. This was excepted to specially. The contract was not executed under seal, and there was evidence tending to show that it was made with plaintiff alone, and that all communications respecting the same were with him, and all payments made to him. These facts, if true, entitled plaintiff to sue in his own name. If he had agreed to make the other alleged members of the association sharers in the profits arising from the contract, they did not therebyhecome parties to the contract and necessary parties plaintiff. Law v. Cross, 1 Black, 533— 537, 17 L. ed. 185-187; The Potomac (Simpson v. Baker) 2 Black, 581-584, 17 L. ed. 263, 264. There was no error in the charge.

5. Error is assigned on the refusal of the following special instruction prayed by defendant:

“The written contract for the work in question in this cause is dated July 30, 1909, and provides that the work should be begun at once and completed within thirty (30) working days, and further that if the work should not be completed within that time, the contractors should forfeit to the owner the sum of tollm peí toy ic® fetoa toy imlwtong Smtoys, ttot the work should remain unfinished. The jury are therefore instructed that if they shall find from the evidence that the work was not completed on or before September 3, 1909, they should allow to the defendant from the contract price, $10 per day for each day, Sundays included, after September 3d, that the work remained unfinished.”

It is contended by the appellee that the language of the contract, providing for a forfeiture upon failure to complete the contract within the time fixed, cannot be regarded as an agreement *250or settlement of liquidated damages; that the term “forfeiture” imports a penalty. In support of this contention are cited Van Buren v. Digges, 11 How. 461-467, 13 L. ed. 771-774, and other cases reviewed in Sun Printing & Pub. Asso. v. Moore, 183 U. S. 646-663 et seq. 46 L. ed. 366-378, 22 Sup. Ct. Rep. 240.

It is not necessary to decide this question. The only plea of defendant was nonassumpsit. While a wide range of defense is permissible under the general plea, apparently including payment, release, etc., it has never been extended to matters of set-off. The claim that defendant is entitled to liquidated damages under a provision of the contract stipulating therefor in case of delay, is an independent matter of defense recoverable by way of set-off, and, to be entertained, must have been pleaded. Code, sec. 1563; Langston v. Maitland, 11 Grill & J. 286-297; 1 Poe, PI. & Pr. sec. 609. There was no error in refusing the instruction.

6. Error is assigned on the Court’s refusal to give the defendant’s third special instruction, to the effect that the agreement provided that the price was to be paid when work was completed to the satisfaction of defendant; that while this would not permit an arbitrary or unreasonable rejection of the work if done in substantial compliance with the contract, and in a first-class manner, yet if the evidence showed that the work was not a first-class job, so that defendant had a right to be dissatisfied therewith, plaintiff is not entitled to recover.

The court in the general charge told the jury that if the work had been done, as agreed on, properly, the plaintiff would be entitled to recover the amount found to be unpaid. If the work was defectively done, plaintiff could recover only what it was worth, and that if he had been paid all that it was fairly worth, the verdict should be for the defendant. This, we think, gave defendant all that he had a right to ask.

7. A special exception was taken to that part of the court’s charge hereinabove stated, permitting the plaintiff to recover the fair value of the work done, in the event that it did not come up to the requirements of the contract, and was yet worth some*251thing in excess of the payments received, because there was no evidence of value, save the price stipulated in the contract. Assuming that there was no evidence justifying a right to recover on a quantum meruit, only, and that the instruction should have been given; yet it is plain that no injury resulted to defendant from its refusal. There was a conflict in the evidence relating to the character of the work done, and the jury decided that issue in favor of the plaintiff by returning a verdict for the full contract price. They were, therefore, not called upon to consider, and never reached the issue of quantum meruit.

Finding no reversible error in the proceedings, the judgment will be affirmed, with costs. Affirmed.

Reference

Full Case Name
SIMMONS v. JASELLI
Status
Published
Syllabus
Contracts; Evidence; Parties; Partnership; Pleading; Appeal and Error. 1. In an action on a written contract by E. 2. In an action on a contract to furnish labor and materials, in' which the issues were as to whether the plaintiff had partners who should have been joined as plaintiffs, and as to the amount and character of the work done and materials furnished under the contract, it was held, on a review of the evidence, that the trial court did not err in refusing to direct a verdict for the defendant. 3. In an action on a written contract for labor and materials furnished, where the trial court refused a special instruction asked by the defendant, to the effect that if, at the time of the doing of the work, the plaintiff had a partner who was interested in the work and entitled to share in the proceeds thereof, he could not recover, but in the charge to the jury defined partnership, and told the jury that if there was a partnership between the plaintiff and his alleged partners, and the contract w’as with the partnership, the plaintiff was not entitled to recover because of the nonjoinder of such parties,— it was held that any error in the refusal of the special instruction was cured by the charge. 4. Where a written contract, not under seal, for labor and materials furnished, was made with the plaintiff alone, and all of the communications concerning the work by the defendant were with the plaintiff and all payments under the contract made to him, he is entitled to sue in his own name, even though he agreed to share with others the profits arising from the contract. 5. In an action of assumpsit on a written contract, evidence by the defendant that, under a provision of the contract stipulating therefor, he is entitled to liquidated damages for delay in performing the contract, is inadmissible under a plea of the general issue; such a claim must be specially pleaded by way of set-off. 6. Where a contract to furnish work and materials on a building provided that the contract price should be paid when the work was completed to the satisfaction of the owner, and then specified how the work should be done and as to the kind of materials to be furnished, it is not error, in an action on the contract for the balance of the contract price, for the trial court to refuse an instruction asked by the defendant, to the effect that, while the agreement would not permit an arbitrary or unreasonable rejection of the work if done in • substantial compliance with the contract in a first-class manner, yet if the evidence showed that the work was not a first-class job, so that the defendant had a right to be dissatisfied therewith, the plaintiff was not entitled to recover. In such a case, a charge by the court that if the work was done as agreed on properly, he is entitled to recover the amount unpaid, while if the work was done defectively, ho can recover only what it was worth, and that if he has been paid all that it was properly worth, the verdict should be for the defendant, gives the defendant all that he has a right to ask. 7. Where in an action to recover the balance of the purchase price specified in a contract for work and labor, the evidence was conflicting as to the character of the work done, and the jury returned a verdict for the plaintiff for the full balance of the contract price as claimed, it was held on an appeal by the defendant from a judgment on the verdict, that even if the court erred in charging the jury that the plaintiff might recover the fair value of the work done in the event it did not come up to the requirements of the contract, and was yet worth something in excess of the payments received — because there was no evidence justifying a recovery of the quantum meruit — such error, in view of the testimony, was not prejudicial to the defendant.