Proc Gas Consum v. FERC
U.S. Court of Appeals for the D.C. Circuit
Proc Gas Consum v. FERC, 177 F.3d 995 (D.C. Cir. 1999)
Proc Gas Consum v. FERC
Opinion
United States Court of Appeals for the district of columbia circuit
No. 98-1075 September Term, 1998
Process Gas Consumers Group, et al., Petitioners
v.
Federal Energy Regulatory Commission, Respondent
Tennessee Gas Pipeline Company, et al., Intervenors
Consolidated with No. 98-1089
Before: Edwards, Chief Judge, Wald and Rogers, Circuit Judges.
O R D E R
It is ORDERED by this Court that the opinion filed on May 21, 1999, is amended as follows:
Page 18, the last full sentence should read:
It is often impossible to offer a higher rate or to request more capacity because the only pipeline capacity that could be of any use to the existing customer is already spoken for.
FOR THE COURT: Mark J. Langer, Clerk
Filed on August 4, 1999