Cargill Power Markets, LLC v. Federal Energy Regulatory Commission
Opinion of the Court
JUDGMENT
This petition was considered on the record from the Federal Energy Regulatory Commission and on the briefs and arguments of the parties. It is
ORDERED and ADJUDGED that the petition for review be denied.
Pursuant to D.C. Circuit Rule 36, this disposition will not be published. The Clerk is directed to withhold issuance of the mandate herein until seven days after resolution of any timely petition for rehearing or rehearing en banc. See Fed. R.App. P. 41(b); D.C.Cir. R. 41.
Reference
- Full Case Name
- CARGILL POWER MARKETS, LLC v. FEDERAL ENERGY REGULATORY COMMISSION, Midwest Independent Transmission System Operator, Inc., Intervenors
- Status
- Published